| Let date | Contract / PPS | County / Division | Highway | Description | Estimate | Status | Low bidder | |
|---|---|---|---|---|---|---|---|---|
| — | 9-01051-0000 9010510000 | District 9 | IL-145IL-34 | Reconstruction - Bridges Culvert Replacement Stream 1.3 Mi N of ILL 145 | $1,000,000 | Planned | ||
| — | 9-01056-0000 9010560000 | District 9 | IL-3 | Rehabilitation - Pavement Standard Overlay Raddle Rd to ILL 149 | $3,500,000 | Planned | ||
| — | 9-01057-0000 9010570000 | District 9 | IL-3 | Rehabilitation - Pavement Standard Overlay ILL 149 to 0.5 Mi N of Power Plant Rd n of Grand Tower | $3,200,000 | Planned | ||
| — | 9-01060-0000 9010600000 | District 9 | IL-37 | Rehabilitation - Pavement Standard Overlay Main St (Old ILL 13) to N of Wildcat Dr in Marion | $9,000,000 | Planned | ||
| — | 9-01060-0104 9010600104 | District 9 | IL-37 | Rehabilitation - Pavement Utility Adjustment Main St (Old ILL 13) to N of Wildcat Dr in Marion | $1,500,000 | Planned | ||
| — | 9-01062-0000 9010620000 | District 9 | IL-37 | Rehabilitation - Pavement Standard Overlay 0.1 mi S of Cleveland St in West Frankfort to 0.1 Mi n of 18th St in Johnston City | $2,400,000 | Planned | ||
| — | 9-01065-0000 9010650000 | District 9 | IL-34 | Rehabilitation - Pavement Standard Overlay Brown St in Benton to Saline Co Line | $6,400,000 | Planned | ||
| — | 9-01066-0000 9010660000 | District 9 | IL-34 | Rehabilitation - Pavement Standard Overlay Franklin Co Line to 0.2 Mi E of Harco Rd | $2,400,000 | Planned | ||
| — | 9-01070-0000 9010700000 | District 9 | IL-37 | Rehabilitation - Pavement Standard Overlay ILL 15 to ILL 148 in Mt Vernon | $14,000,000 | Planned | ||
| — | 9-01070-0104 9010700104 | District 9 | IL-37 | Rehabilitation - Pavement Utility Adjustment ILL 15 to ILL 148 in Mt Vernon | $1,000,000 | Planned | ||
| — | 9-01074-0000 9010740000 | District 9 | IL-3 | Rehabilitation - Pavement Standard Overlay Pigeon Roost Rd in Olive Branch to 2.2 Mi NW of ILL 127 | $1,800,000 | Planned | ||
| — | 9-01097-0000 9010970000 | District 9 | IL-13IL-34 | Preservation - Pavements Smart Overlay Poplar St to US 45 in Harrisburg | $1,600,000 | Planned | ||
| — | 9-01118-0000 9011180000 | District 9 | IL-3 | Rehabilitation - Pavement Standard Overlay ILL 146 at Cape T to 0.1 Mi W of ILL 3 in Thebes | $2,800,000 | Planned | ||
| — | 9-01119-0000 9011190000 | District 9 | IL-3US-51 | Rehabilitation - Pavement Standard Overlay 2 Mi S of ILL 127 to 0.2 Mi S of New Cross St in Future City | $4,600,000 | Planned | ||
| FY 2025 | 1-75939-0000 1759390000 | District 1 | Front StIL-31 | Initial Construction - Pa Additional Lanes Ill 120 to Bull Valley Rd | $29,650,000 | Planned | ||
| FY 2025 | 1-75939-0010 1759390010 | District 1 | Front StIL-31 | Reconstruction - Pavement Reconstruction, Widening Existing Pavement, Traf Signal Modernization Ill 120 to Bull Valley Rd | $44,475,000 | Planned | ||
| FY 2025 | 1-75939-0200 1759390200 | District 1 | Front StIL-31 | Initial Construction - Pa Additional Lanes, ADA Improvements Bull Valley Rd to ILL 176 (Terra Cotta Ave) | $40,000,000 | Planned | ||
| FY 2025 | 1-75939-0201 1759390201 | District 1 | Front StIL-31 | Initial Construction - Pa Utility Adjustment S of ILL 120 (Belvidere Rd) to N of ILL 176 (Terra Cotta Ave) | $4,000,000 | Planned | ||
| FY 2025 | 1-75939-0202 1759390202 | District 1 | Front StIL-31 | Initial Construction - Pa Utility Adjustment S of ILL 120 (Belvidere Rd) to N of ILL 176 (Terra Cotta Ave) | $4,000,000 | Planned | ||
| FY 2025 | 1-75939-0800 1759390800 | District 1 | Front StIL-31 | Miscellaneous Improvement Miscellaneous Bull Valley Rd to ILL 176 (Terra Cotta Ave) | $500,000 | Planned | ||
| FY 2025 | 1-75939-1200 1759391200 | District 1 | Front StIL-31 | Reconstruction - Pavement Culvert (New) Bull Valley Rd to ILL 176 (Terra Cotta Ave) | $60,000,000 | Planned | ||
| FY 2025 | 1-75939-3001 1759393001 | District 1 | Front StIL-31 | Miscellaneous Improvement Tree Removal S of ILL 120 (Belvidere Rd) to N of ILL 176 (Terra Cotta Ave) | $400,000 | Planned | ||
| FY 2025 | 1-81379-0010 1813790010 | District 1 | IL-31 | Preservation - Bridges Bridge Joint Replace/Repair, Bridge Deck Overlay At Nippersink Creek | $1,000,000 | Planned | ||
| FY 2025 | 1-81615-0000 1816150000 | District 1 | IL-38Roosevelt Rd | Rehabilitation - Pavement Standard Overlay E of Nicoll Way to Edson Ave | $4,800,000 | Planned | ||
| FY 2025 | 1-81648-0000 1816480000 | District 1 | Elm StIL-31 | Rehabilitation - Pavement Standard Overlay W of Martin Rd to E Green St | $3,500,000 | Planned | ||
| FY 2025 | 4-02024-2408 4020242408 | District 4 | IL-110IL-336US-136 | Preservation - Pavements Crack & Joint Sealing 0.6 Mi S of US 136 to US 67 (N) | $200,000 | Planned | ||
| FY 2025 | 5-53367-0000 5533670000 | District 5 | IL-32 | Preservation - Bridges Bridge Deck Overlay At Sangamon River 4.3 mi S of Cisco | $2,500,000 | Planned | ||
| FY 2025 | 7-50210-0000 7502100000 | District 7 | IL-130IL-33 | Rehabilitation - Pavement Designed Overlay, ADA Improvements, Traf Signal Modernization ILL 33: W of West End Ave to N Van Buren St in Newton & ILL 130: Embarras River N of Newton to Edwards St in Newton | $8,650,000 | Planned | ||
| FY 2025 | 7-50239-0000 7502390000 | District 7 | IL-33US-40US-45 | Initial Construction - Pa Additional Lanes, Storm Sewer (New), Curb And Gutter Banker St to Salt Creek in Effingham | $4,220,000 | Planned | ||
| FY 2025 | 7-50239-0050 7502390050 | District 7 | IL-33US-40US-45 | Reconstruction - Pavement Reconstruction Banker St to Salt Creek in Effingham | $16,820,000 | Planned | ||
| FY 2025 | 7-50239-0400 7502390400 | District 7 | IL-33US-40US-45 | Miscellaneous Improvement Demolition Banker St to E of Long St in Effingham | $1,500,000 | Planned | ||
| FY 2025 | 7-50362-0500 7503620500 | District 7 | IL-32 | Reconstruction - Bridges Bridge Replacement At Streams 0.5, 2.1, 3 & 3.4 Mi S of Shelby Co Line | $1,030,000 | Planned | ||
| FY 2025 | 7-50362-4000 7503624000 | District 7 | IL-32 | Rehabilitation - Pavement Designed Overlay Shelby Co Line to ILL 33 | $5,140,000 | Planned | ||
| FY 2025 | 7-50993-0000 7509930000 | District 7 | IL-32IL-33 | Rehabilitation - Pavement Designed Overlay W of Ford Ave to 0.1 Mi W of Evergreen Ave in Effingham | $1,770,000 | Planned | ||
| FY 2025 | 7-51023-0000 7510230000 | District 7 | IL-33 | Rehabilitation - Pavement Designed Overlay, ADA Improvements, Traf Signal Modernization W of Pine St in Dieterich to Jasper Co Line | $2,010,000 | Planned | ||
| FY 2025 | 7-76910-8732 7769108732 | District 7 | IL-32 | Safety New Shoulders, Safety Improvements Hydro Gear Dr in Sullivan to ILL 16 in Windsor | $1,870,000 | Planned | ||
| FY 2025 | 8-00433-0000 8004330000 | District 8 | IL-111IL-3 | Rehabilitation - Bridges Bridge New Deck Over Rogers Ave & Bloomer Dr 1 mi N of Jct ILL 111/140 in Alton | $9,700,000 | Planned | ||
| FY 2025 | 9-00083-0000 9000830000 | District 9 | IL-37 | Miscellaneous Improvement Traf Signal Modernization, Intersection Reconstn, Intersection Improvement At Boyton St in Marion | $3,500,000 | Planned | ||
| FY 2025 | 9-00083-0104 9000830104 | District 9 | IL-37 | Miscellaneous Improvement Utility Adjustment At Boyton St in Marion | $500,000 | Planned | ||
| FY 2025 | 9-00714-2623 9007142623 | District 9 | IL-37 | Preservation - Bridges Bridge Deck Overlay Hodges Bayou 1.4 Mi S of Olmstead | $400,000 | Planned | ||
| FY 2025 | 9-00964-0000 9009640000 | District 9 | IL-37 | Rehabilitation - Pavement Standard Overlay N Douglas St to 0.1 Mi S of Cleveland St in West Frankfort | $1,500,000 | Planned | ||
| FY 2025 | 9-00977-0000 9009770000 | District 9 | IL-37 | Rehabilitation - Pavement Standard Overlay Marion Co Line to N&S RR 3.5 mi S of Dix | $2,800,000 | Planned | ||
| FY 2025 | 9-00978-0000 9009780000 | District 9 | IL-37 | Rehabilitation - Pavement Standard Overlay Loop Rd at NCL Mt Vernon to ILL 15 in Mt Vernon | $1,800,000 | Planned | ||
| FY 2025 | 9-00978-0200 9009780200 | District 9 | IL-37 | Reconstruction - Pavement Pavement Replacement At I-64 Intchg | $2,000,000 | Planned | ||
| FY 2025 | 9-01050-1000 9010501000 | District 9 | IL-14IL-37 | Safety Intersection Reconstn Benton Square (Roundabout) | $1,500,000 | Planned | ||
| FY 2025 | 9-01061-0000 9010610000 | District 9 | IL-37 | Rehabilitation - Pavement Standard Overlay 0.1 Mi n of 18th St to 4th St in Johnston City | $800,000 | Planned | ||
| FY 2025 | 9-92870-0000 9928700000 | District 9 | IL-3 | Reconstruction - Bridges Bridge Replacement Drainage Ditch 0.5 Mi W of ILL 127 | $2,500,000 | Planned | ||
| FY 2025 | 9-98775-0100 9987750100 | District 9 | IL-3 | Reconstruction - Bridges Bridge Replacement Worthen Bayou 1.2 Mi S of ILL 149 | $3,000,000 | Planned |
101–148 of 148‹ Prev
Lettings: IDOT Transportation Bulletin (Notice of Letting and Contract Detail pages). Planned projects: IDOT Multi-Year Highway Improvement Program (roadway, structure and spot layers on the IDOT open data hub), listed by program year, not let date. "Added" is the first date Bid Potato saw the job. Always confirm against the official proposal before bidding.