Filtered by: Highway: IL-15 Clear all
| Let date | Contract / PPS | County / Division | Highway | Description | Estimate | Status | Low bidder | |
|---|---|---|---|---|---|---|---|---|
| — | 6-00790-0000 6007900000 | District 6 | IL-159 | Miscellaneous Improvement Drainage AT ALTON ST IN BUNKER HILL | $100,000 | Planned | ||
| — | 6-01283-0000 6012830000 | District 6 | IL-159 | Rehabilitation - Pavement Designed Overlay S OF ALTON ST IN BUNKER HILL TO MADISON CO LINE | $2,300,000 | Planned | ||
| — | 6-01417-0000 6014170000 | District 6 | IL-159 | Rehabilitation - Pavement Standard Overlay, Storm Sewer (New), Curb And Gutter N OF NORTH ST TO S OF ALTON ST IN BUNKER HILL | $3,500,000 | Planned | ||
| — | 6-01417-0003 6014170003 | District 6 | IL-159 | Rehabilitation - Pavement Utility Adjustment N OF NORTH ST TO S OF ALTON ST IN BUNKER HILL | $150,000 | Planned | ||
| — | 6-01524-0000 6015240000 | District 6 | IL-159 | Rehabilitation - Pavement Culvert Replacement 0.2 MI S OF ILL 16 IN ROYAL LAKES TO N OF NORTH ST IN BUNKER HILL | $4,800,000 | Planned | ||
| — | 7-50386-0000 7503860000 | District 7 | IL-15 | Rehabilitation - Pavement Designed Overlay, ADA Improvements Jefferson Co Line to 0.1 Mi W of 870E N of Sims | $13,060,000 | Planned | ||
| — | 7-50908-0000 7509080000 | District 7 | IL-15 | Rehabilitation - Pavement Designed Overlay, ADA Improvements Wayne Co Line to Wabash Co Line | $10,550,000 | Planned | ||
| — | 7-51024-0000 7510240000 | District 7 | IL-15 | Rehabilitation - Pavement Designed Overlay Edwards Co Line to 0.2 Mi E of Empire St in Mt Carmel | $11,020,000 | Planned | ||
| — | 7-52767-0000 7527670000 | District 7 | IL-1IL-15 | Rehabilitation - Pavement Standard Overlay, ADA Improvements, Traf Signal Modernization W 9th St to W of Greathouse Creek in Mt Carmel | $3,910,000 | Planned | ||
| — | 7-52897-0000 7528970000 | District 7 | IL-15 | Rehabilitation - Pavement Standard Overlay, ADA Improvements W 3rd St in Mt Carmel to Indiana State Line | $1,110,000 | Planned | ||
| — | 7-52908-0000 7529080000 | District 7 | IL-15 | Preservation - Bridges Bridge Deck Repairs, Bridge Deck Overlay At Shoe Creek & Skillet Fork Overflow N of Shaefer Ln | $1,910,000 | Planned | ||
| — | 7-52942-0000 7529420000 | District 7 | IL-15 | Miscellaneous Improvement Culvert Replacement 0.3 Mi W of CR 715E N of Wayne City to 0.3 Mi W of US 45 W of Fairfield (Various Structures) | $1,940,000 | Planned | ||
| — | 7-79210-0000 7792100000 | District 7 | IL-15 | Reconstruction - Bridges Bridge Replacement At Stream 0.1 Mi E of CR 400 N of Belmont | $1,220,000 | Planned | ||
| — | 8-00178-0000 8001780000 | District 8 | IL-153 | Reconstruction - Bridges Bridge Replacement At Mary's River 1 Mi N of Eden | $3,000,000 | Planned | ||
| — | 8-00331-0000 8003310000 | District 8 | IL-15 | Reconstruction - Bridges Bridge Replacement At Nashville Creek W of Willowbrook Dr in Nashville | $3,200,000 | Planned | ||
| — | 8-00584-0000 8005840000 | District 8 | IL-150IL-3State St | Reconstruction - Pavement Pavement Replacement, ADA Improvements ILL 3 (Opdyke St) to Murphysboro Rd in Chester | $10,000,000 | Planned | ||
| — | 8-00584-0400 8005840400 | District 8 | IL-150IL-3State St | Reconstruction - Pavement Utility Adjustment ILL 3 (Opdyke St) to Murphysboro Rd in Chester | $200,000 | Planned | ||
| — | 8-00591-0000 8005910000 | District 8 | IL-15IL-4 | Reconstruction - Bridges Bridge Replacement Kaskaskia River 0.2 mi E of Jct ILL 4 in Fayetteville; Kaskaskia Overflow 0.4 mi & 0.6 mi E of Jct ILL 4 | $66,000,000 | Planned | ||
| — | 8-00623-0000 8006230000 | District 8 | IL-150IL-4 | Reconstruction - Pavement Pavement Replacement, ADA Improvements ILL 4 to Green St in Steeleville | $21,000,000 | Planned | ||
| — | 8-00623-0400 8006230400 | District 8 | IL-150IL-4 | Reconstruction - Pavement Utility Adjustment ILL 4 to Green St in Steeleville | $200,000 | Planned | ||
| — | 8-00623-2000 8006232000 | District 8 | IL-150IL-4 | Preservation - Bridges Bridge Joint Replace/Repair, Bridge Deck Overlay, Drains (Replace/Repair) At Mary's River W of Steeleville | $1,400,000 | Planned | ||
| — | 8-00624-0000 8006240000 | District 8 | IL-150IL-4 | Reconstruction - Pavement Pavement Replacement, ADA Improvements Clyde Steele St to Howard Ave in Percy | $11,400,000 | Planned | ||
| — | 8-00624-0400 8006240400 | District 8 | IL-150IL-4 | Reconstruction - Pavement Utility Adjustment Clyde Steele St to Howard Ave in Percy | $200,000 | Planned | ||
| — | 8-00625-0000 8006250000 | District 8 | IL-150IL-4 | Reconstruction - Pavement Pavement Replacement Green St in Steeleville to Clyde Steele St in Percy | $8,700,000 | Planned | ||
| — | 8-00625-2000 8006252000 | District 8 | IL-150IL-4 | Preservation - Bridges Bridge Joint Replace/Repair, Bridge Deck Overlay At Cox Creek E of Steeleville ECL | $900,000 | Planned | ||
| — | 8-00626-0000 8006260000 | District 8 | IL-150IL-4 | Reconstruction - Pavement Pavement Replacement Howard Ave in Percy to Perry Co Line | $5,500,000 | Planned | ||
| — | 8-00860-0000 8008600000 | District 8 | IL-154 | Rehabilitation - Pavement Designed Overlay, ADA Improvements Grand Ave to Burns Ave in Sparta | $3,500,000 | Planned | ||
| — | 8-00870-0000 8008700000 | District 8 | IL-154 | Preservation - Bridges Bridge Painting, Bridge Repair, Bridge Joint Replace/Repair Kaskaskia River | $9,000,000 | Planned | ||
| — | 8-00921-0000 8009210000 | District 8 | IL-157 | Rehabilitation - Pavement Designed Overlay 0.2 Mi N of Horseshoe Lake Rd to St. Clair Co Line in Collinsville | $10,000,000 | Planned | ||
| — | 8-00959-0000 8009590000 | District 8 | IL-159 | Preservation - Bridges Bridge Painting, Bridge Joint Replace/Repair, Bridge Deck Overlay Over CSX RR in Collinsville | $11,300,000 | Planned | ||
| — | 8-00977-0000 8009770000 | District 8 | IL-15 | Reconstruction - Pavement Pavement Replacement, Pump Station, ADA Improvements 26th St in East St Louis to 0.2 mi W of A&S RR in Cahokia Heights | $52,000,000 | Planned | ||
| — | 8-00977-0400 8009770400 | District 8 | IL-15 | Reconstruction - Pavement Utility Adjustment 26th St in East St Louis to 0.2 mi W of A&S RR in Cahokia Heights | $5,000,000 | Planned | ||
| — | 8-82159-0050 8821590050 | District 8 | IL-159 | Safety Intersection Reconstn, ADA Improvements At Beltline Rd in Collinsville | $5,700,000 | Planned | ||
| — | 8-89196-0100 8891960100 | District 8 | IL-157 | Reconstruction - Bridges Bridge Replacement, Bridge Approach Roadway, Scour Mitigation At Little Canteen Creek 0.1 mi S of O'Fallon Dr in Caseyville | $9,000,000 | Planned | ||
| — | 8-89262-0100 8892620100 | District 8 | IL-157 | Reconstruction - Bridges Bridge Replacement, Scour Mitigation At Goose Lake Canal 0.8 mi E of I-255 in Cahokia Heights | $5,900,000 | Planned | ||
| — | 8-89423-0100 8894230100 | District 8 | IL-159 | Reconstruction - Bridges Bridge Replacement At Douglas Creek 0.2 Mi S of Douglas Rd in Smithton | $3,700,000 | Planned | ||
| — | 9-00169-0000 9001690000 | District 9 | IL-15 | Reconstruction - Bridges Bridge Replacement Ryse Creek 3.6 Mi E of Washington Co Line | $3,000,000 | Planned | ||
| — | 9-00215-0000 9002150000 | District 9 | IL-151 | Reconstruction - Bridges Culvert Replacement Spring Creek 2 Mi S of Ava SCL | $1,000,000 | Planned | ||
| — | 9-00216-0000 9002160000 | District 9 | IL-15 | Reconstruction - Bridges Bridge Replacement Bear Creek 5.4 Mi E of Mt Vernon | $1,200,000 | Planned | ||
| — | 9-00579-0000 9005790000 | District 9 | IL-150 | Rehabilitation - Pavement Standard Overlay 0.2 Mi N of Reeses Hill Rd N of Cutler to ILL 154 | $1,400,000 | Planned | ||
| — | 9-00663-0000 9006630000 | District 9 | IL-152 | Rehabilitation - Pavement Standard Overlay, New Shoulders ILL 127 to US 51 | $12,000,000 | Planned | ||
| — | 9-00714-2629 9007142629 | District 9 | IL-15 | Preservation - Bridges Bridge Deck Overlay Over CN RR 1.5 Mi W of Wayne Co | $300,000 | Planned | ||
| — | 9-00842-0100 9008420100 | District 9 | IL-13IL-154 | Reconstruction - Pavement Reconstruction Grant St to S Walnut St in Pinckneyville | $2,000,000 | Planned | ||
| — | 9-00853-0000 9008530000 | District 9 | IL-154 | Reconstruction - Bridges Bridge Replacement Beaucoup Creek E of Pinckneyville | $8,000,000 | Planned | ||
| — | 9-00865-0000 9008650000 | District 9 | IL-15 | Miscellaneous Improvement Culvert Rehabilitation 6.2 Mi E of Mt Vernon | $400,000 | Planned | ||
| — | 9-00918-0000 9009180000 | District 9 | IL-150 | Reconstruction - Bridges Bridge Replacement 1.3 Mi S of ILL 154 | $600,000 | Planned | ||
| — | 9-00928-0000 9009280000 | District 9 | IL-154 | Reconstruction - Bridges Bridge Replacement Rend Lake 3.3 Mi E of Sesser ECL | $8,000,000 | Planned | ||
| — | 9-00928-0100 9009280100 | District 9 | IL-154 | Reconstruction - Bridges Bridge Replacement Rend Lake 4.4 mi E of Sesser ECL | $10,000,000 | Planned | ||
| — | 9-00966-0000 9009660000 | District 9 | IL-154 | Rehabilitation - Pavement Standard Overlay Randolph Co Line to Grant St in Pinckneyville | $4,500,000 | Planned | ||
| — | 9-00981-0000 9009810000 | District 9 | IL-151 | Rehabilitation - Pavement Standard Overlay ILL 4 in Ava to ILL 3 | $3,200,000 | Planned | ||
| — | 9-00989-0000 9009890000 | District 9 | IL-148IL-154 | Rehabilitation - Pavement Standard Overlay Jefferson Co Line to 1.9 mi S of ILL 154 | $1,500,000 | Planned | ||
| — | 9-01011-0000 9010110000 | District 9 | IL-15 | Miscellaneous Improvement Culvert Rehabilitation 0.1 Mi W of Wayne Co Line | $400,000 | Planned | ||
| — | 9-01101-0000 9011010000 | District 9 | IL-151 | Reconstruction - Bridges Bridge Replacement 0.3 Mi N of ILL 3 | $1,200,000 | Planned | ||
| FY 2025 | 7-52945-0000 7529450000 | District 7 | IL-15 | Preservation - Bridges Bridge Deck Repairs, Bridge Joint Replace/Repair, Bridge Deck Overlay At Skillet Fork & Skillet Fork Overflow 0.5 & 0.2 Mi SW of CR 635E | $1,500,000 | Planned | ||
| FY 2025 | 7-79230-0000 7792300000 | District 7 | IL-15 | Preservation - Bridges Bridge Deck Repairs, Bridge Joint Replace/Repair, Bridge Deck Overlay At Little Wabash River 0.3 Mi E of CR 2500E | $3,110,000 | Planned | ||
| FY 2025 | 8-00591-0600 8005910600 | District 8 | IL-15IL-4 | Reconstruction - Bridges Bridge Replacement Kaskaskia River 0.2 mi E of Jct ILL 4 in Fayetteville; Kaskaskia Overflow 0.4 mi & 0.6 mi E of Jct ILL 4 (IPD Pre-Construction Services) | $500,000 | Planned | ||
| FY 2025 | 8-79150-2000 8791502000 | District 8 | IL-150 | Reconstruction - Bridges Bridge Replacement Mississippi River at Chester | $23,605,000 | Planned | ||
| FY 2025 | 9-00663-0104 9006630104 | District 9 | IL-152 | Rehabilitation - Pavement Utility Adjustment ILL 127 to US 51 | $500,000 | Planned |
1–58 of 58
Lettings: IDOT Transportation Bulletin (Notice of Letting and Contract Detail pages). Planned projects: IDOT Multi-Year Highway Improvement Program (roadway, structure and spot layers on the IDOT open data hub), listed by program year, not let date. "Added" is the first date Bid Potato saw the job. Always confirm against the official proposal before bidding.