| Let date | Contract / PPS | County / Division | Highway | Description | Estimate | Status | Low bidder | |
|---|---|---|---|---|---|---|---|---|
| Jan 19, 2018 | 85660 | LeeDistrict 2 | Resurfacing CH 22/Eldena Road from US 52 to South Eldena Road. | — | Executed | Martin & Company Excavating $325,315 · | ||
| Jan 19, 2018 | 85661 | LeeDistrict 2 | Resurfacing Harmon Road from US 30 to Sterling Road. | — | Executed | Martin & Company Excavating $249,800 · | ||
| Mar 9, 2018 | 85664 | LeeDistrict 2 | Replace bridge carrying Amboy Road over Branch of Main Ditch, .1 mile east of IL 26. | — | Executed | Curnyn Construction Co. $311,459 · | ||
| Apr 27, 2018 | 64H59 | LeeOgleDistrict 2 | Removal and replacement of two concrete box culverts carrying IL 38 over drainage ditches. SN 052-1107 is 0.1 mile east of of Daysville Road in Franklin Grove and SN 071-1191 is 0.2 mile east of Center Rd west of Rochelle. | — | Executed | Phoenix Corporation of the Quad Cities $782,777 · | ||
| Apr 27, 2018 | 64M52 | LeeDistrict 2 | clean and paint bridge SN 052-0058 carrying Shady Oaks Road over I-39, 3.0 miles north of the LaSalle County line. | — | Executed | Venus Painting Co. $178,630 · | ||
| Jan 18, 2019 | 64N24 | LeeDistrict 2 | Removal and replacement of culvert in the south leg of the intersection of IL 251 and US 30. | — | Executed | O'Brien Civil Works, Inc. $118,640 · | ||
| Mar 8, 2019 | 64N11 | LeeDistrict 2 | Clean and paint structural steel on SN 052-055 carrying Chicago Road over I-39. | — | Executed | Civil Coatings and Construction Inc. $382,590 · | ||
| Mar 8, 2019 | 64N12 | LeeDistrict 2 | Clean and paint structural steel on SN 052-0054 carrying Beemerville Road over I-39. | — | Executed | Civil Coatings and Construction Inc. $196,150 · | ||
| Mar 8, 2019 | 64N28 | LeeDistrict 2 | Expansion joint replacement, deck patching, and concrete overlay on SN 052-0060 carrying US 52 over the Green River. | — | Rejected | Sjostrom & Sons, Inc. $387,637 · | ||
| Mar 8, 2019 | 85676 | LeeDistrict 2 | Resurfacing Inlet Road from Green Wing Road to Shaw Road. | — | Executed | Martin & Company Excavating $492,578 · | ||
| Jan 17, 2020 | 64M43 | LeeOgleDistrict 2 | Cold milling, patching, and resurfacing from Wilson St in Polo to 0.1 mile N of Liberty Ct in Dixon. | — | Executed | Civil Constructors, Inc. $5,375,394 · | ||
| Mar 6, 2020 | 64M29 | LeeDistrict 2 | Miscellaneous intersection and sidewalk improvements at US 52 and Main St in Amboy. | — | Executed | O'Brien Civil Works, Inc. $158,779 · | ||
| Apr 24, 2020 | 64M45 | LeeDistrict 2 | Cold milling, pavement patching, and HMA resurfacing on IL 26 from Bloody Gulch Rd in Dixon to US 30. | — | Executed | Civil Constructors, Inc. d/b/a/ Helm Civil $2,479,194 · | ||
| Apr 24, 2020 | 85685 | LeeDistrict 2 | Resurfacing, sidewalk replacement, and pavement markings on various routes in City of Dixon. | — | Executed | Martin & Company Excavating $996,062 · | ||
| Apr 24, 2020 | 85693 | LeeDistrict 2 | Resurfacing 4th Avenue from Galena Avenue to Lincoln Highway in Dixon. | — | Executed | Martin & Company Excavating $571,769 · | ||
| Jan 15, 2021 | 64P67 | LeeDistrict 2 | Cold milling and Hot Mix Asphalt Resurfacing from 0.1 mile west to 0.1 mile East of Franklin Creek located West of Franklin Grove. | — | Executed | Porter Brothers Asphalt & Sealing $57,761 · | ||
| Mar 5, 2021 | 64M35 | LeeDistrict 2 | ADA curb ramp improvements along US 52 from Wasson Road to Bluff Street in Amboy. | — | Executed | Stenstrom Excavation & Blacktop, Inc. $358,849 · | ||
| Mar 5, 2021 | 85710 | LeeDistrict 2 | Cold-In-Place Recycling with HMA overlay on Shaw Road from Brooklyn to IL 251. | — | Executed | Rock Road Companies, Inc. $626,028 · | ||
| Apr 23, 2021 | 64M91 | LeeDistrict 2 | 0.80 miles, Cold milling, pavement patching, HMA resurfacing, ADA improvement and traffic signal modernization from West of Page drive to US 52/IL 26 in Dixon. | — | Executed | Martin & Company Excavating $2,016,252 · | ||
| Apr 23, 2021 | 64P30 | LeeDistrict 2 | Cold milling, pavement patching and hot-mix asphalt resurfacing along US 52 from Water Street in Amboy to North of Henkle Road. | — | Executed | Advanced Asphalt Company $4,129,760 · | ||
| Apr 23, 2021 | 64P72 | LeeDistrict 2 | Cleaning and painting structural steel on SN 052-0059 carrying Welland Road over 1-39. | — | Executed | Three Star Painting, Inc. $190,000 · | ||
| Nov 5, 2021 | 64M41 | LeeDistrict 2 | 0.37 mile, Removal and replacement of concrete box culverts carrying IL 251 over drainage from 0.5 mile South of US 30 to 0.3 mile North of Tower Road. (SN's 052-1064, 1066, C003, 1076, 1077) | — | Executed | Fischer Excavating, Inc. $1,566,058 · | ||
| Jan 21, 2022 | 85718 | LeeDistrict 2 | Resurfacing Franklin Road from west city limits of Franklin Grove to US 30, and Gap Road from IL 38 to Franklin Road. | — | Executed | Martin & Company Excavating $988,644 · | ||
| Jan 20, 2023 | 64R54 | LeeDistrict 2 | Expansion joint replacement, miscellaneous repairs and deck concrete wearing surface on SN 052-0031 carrying US 30 over UP RR, 0.9 miles East of Whiteside County line. | — | Executed | Civil Constructors, Inc. d/b/a/ Helm Civil $699,832 · | ||
| Jan 20, 2023 | 85700 | LeeDistrict 2 | Construction of a shared-use path, concrete curb and gutter, driveways, drainage adjustments, boardwalk structures, retaining walls, lighting, and landscaping along an abandoned railroad from South Peoria Avenue to Depot Avenue in Dixon. | — | Executed | Martin & Company Excavating $4,313,104 · | ||
| Jan 20, 2023 | 85730 | LeeDistrict 2 | Resurfacing, sidewalks, curb and guttr, segmantal block wall, signing and pavement markings on various routes in Dixon. | — | Executed | Martin & Company Excavating $2,010,320 · | ||
| Mar 10, 2023 | 64S22 | LeeDistrict 2 | Milling and resurfacing the Amboy Maintenance yard. | — | Executed | Civil Constructors, Inc. d/b/a/ Helm Civil $219,492 · | ||
| Jun 16, 2023 | 64R58 | LeeDistrict 2 | Lighting at I-39 AT US 30. | — | Executed | William Charles Construction Co, LLC $335,994 · | ||
| Mar 8, 2024 | 64B39 | LeeDistrict 2 | Structure replacement ditches in US 30 ROW 1 mile and 1.5 mile west of IL 251. | — | Executed | Martin & Company Excavating $3,724,770 · | ||
| Apr 26, 2024 | 64S30 | LeeDistrict 2 | Deck repair, joint replacement, deck overlay, and other miscellaneous repairs on SN 052-0061 over Coon Creek, 3.2 miles South of Amboy. | — | Executed | Martin & Company Excavating $585,814 · | ||
| Apr 26, 2024 | 85757 | LeeDistrict 2 | HMA resurfacing with aggregate shoulders on Indian Road from the Bureau County Line to Van Petten Road, and on Van Petten Road from the Whiteside County Line to Indian Head Road. | — | Executed | Martin & Company Excavating $1,065,955 · | ||
| Sep 20, 2024 | 64S29 | LeeDistrict 2 | Deck repair, joint replacement, deck overlay and other miscellaneous repairs on SN 052-0062 over UP RR at the the south edge of Dixon. | — | Executed | Civil Constructors, Inc. d/b/a/ Helm Civil $1,009,879 · | ||
| Sep 20, 2024 | 64S90 | LeeDistrict 2 | Partial cleaning and painting of structural steel on SN 052-0031 carrying US 30 over UPRR, 0.9 miles east of Whiteside County line. | — | Executed | Venus Painting Co. $106,609 · | ||
| Sep 20, 2024 | 85762 | LeeDistrict 2 | Construction of a pedestrian bridge, shared--use path, lighting, HMA pavement, sidewalk, drainage improvements and modular block retaining wall along Page Drive, Lincoln Statue Drive, and through Page Park in Dixon. | — | Executed | Civil Constructors, Inc. d/b/a/ Helm Civil $14,126,560 · | ||
| Jan 17, 2025 | 64M10 | LeeDistrict 2 | Removal and replacement of an existing box culvert carrying US 30 over a creek located 0.1 mile west of Atkinson Road. | — | Executed | Martin & Company Excavating $746,263 · | ||
| Mar 7, 2025 | 64R02 | LeeDistrict 2 | Reconstruction of sidewalk ramps for those with disabilities at ramps deemed uncompliant, patching, milling, and resurfacing along various state routes in Dixon, Illinois. Gross Length 4,163 ft. | — | Executed | Martin & Company Excavating $4,036,696 · | ||
| Mar 7, 2025 | 85775 | LeeDistrict 2 | Surface Profile Milling, Cold-in-Place Recycling, and HMA Resurfacing on Perry Road from IL 251 to the BNSF Railroad in Steward. | — | Executed | Martin & Company Excavating $640,103 · | ||
| Apr 25, 2025 | 64T79 | LeeDistrict 2 | Pavement patching along IL 38 from Franklin Grove to Ashton (9.22 miles gross length). | — | Executed | O'Brien Civil Works, Inc. $310,362 · | ||
| Apr 25, 2025 | 85773 | LeeDistrict 2 | Replace the bridge carrying Brooklyn Road over Willow Creek, 0.5 mile north of US 30. | — | Executed | Martin & Company Excavating $950,396 · | ||
| Jun 13, 2025 | 64M76 | LeeDistrict 2 | Remove and replace culvert over a drainage way 0.3 mile south of US 30, north of Amboy on US 52. | — | Executed | Martin & Company Excavating $493,527 · | ||
| Jun 13, 2025 | 64T31 | LeeDistrict 2 | Crack joint sealing on US 52 from Water St in Amboy to north of Henkel Rd and on IL 2 from Page Dr in Dixon to US 52/IL 26. 4,227 ft gross length. | — | Executed | Denler, Inc. $255,552 · | ||
| Jun 13, 2025 | 64U41 | LeeDistrict 2 | .3 miles of longitudinal joint repair along IL 38 in Franklin Grove. | — | Executed | Martin & Company Excavating $58,245 · | ||
| Jan 16, 2026 | 64T96 | LeeDistrict 2 | Bridge repairs and joint replacement on SN 052-0068, carrying IL 251 over Bureau Creek, 0.80 miles north of Lee County line. | — | Executed | Martin & Company Excavating $369,059 · | ||
| Jan 16, 2026 | 64U21 | LeeDistrict 2 | 8 Miles Cold-In Place Eldena Road to US 30. | — | Executed | Martin & Company Excavating $4,655,130 · | ||
| Feb 27, 2026 | 64U03 | LaSalleLeeDistrict 2 | 19.3 miles, ultra-thin bonded wearing course, microsurfacing joint repairs, pavement patching, and rest_area improvements from LaSalle County Line_to Ogle County Line. | — | Executed | Rock Road Companies, Inc. $14,540,979 · | ||
| Apr 24, 2026 | 64T73 | LeeDistrict 2 | 2.32 miles US 30 to Wasson Rd in Amboy (designed overlay, cold milling), 0.80 miles Wasson Rd to Water St in Amboy (standard overlay, cold milling). | — | Executed | Martin & Company Excavating $1,988,394 · | ||
| Apr 24, 2026 | 64U85 | LeeDistrict 2 | 1 mile of patching from Lowell Park Rd. to Fellows St. in Dixon. | — | Executed | Civil Constructors, Inc. d/b/a/ Helm Civil $564,716 · | ||
| Apr 24, 2026 | 85793 | LeeDistrict 2 | Resurfacing on Brooklyn Road from US 30 to IL 251. | — | Executed | Martin & Company Excavating $1,489,962 · | ||
| Apr 24, 2026 | 85797 | LeeDistrict 2 | Replace the bridge carrying Indian Head Road over Red Oak Ditch. | — | Executed | Martin & Company Excavating $582,765 · |
1–49 of 49
Lettings: IDOT Transportation Bulletin (Notice of Letting and Contract Detail pages). Planned projects: IDOT Multi-Year Highway Improvement Program (roadway, structure and spot layers on the IDOT open data hub), listed by program year, not let date. "Added" is the first date Bid Potato saw the job. Always confirm against the official proposal before bidding.