| Bid code | Description | Unit | Jobs ▼ | Avg low bid | Last let |
|---|---|---|---|---|---|
| 67100100 | MOBILIZATION | L SUM | 7,653 | $159,438.46 | Sep 18, 2026 |
| 40600290 | BIT MATLS TACK CT | POUND | 3,725 | $0.6725 | Sep 18, 2026 |
| 70300150 | SHRT TRM PAVT MK REM | SQ FT | 3,472 | $0.8705 | Sep 18, 2026 |
| 70300100 | SHORT TERM PAVT MKING | FOOT | 3,233 | $0.6744 | Sep 18, 2026 |
| 70107025 | CHANGEABLE MESSAGE SN | CAL DA | 2,894 | $42.94 | Sep 18, 2026 |
| 20200100 | EARTH EXCAVATION | CU YD | 2,878 | $21.74 | Sep 18, 2026 |
| 78100100 | RAISED REFL PAVT MKR | EACH | 2,747 | $36.42 | Sep 18, 2026 |
| 78300200 | RAISED REF PVT MK REM | EACH | 2,680 | $14.63 | Sep 18, 2026 |
| Z0076604 | TRAINEES TPG | HOUR | 2,432 | $15.00 | Sep 18, 2026 |
| 67000400 | ENGR FIELD OFFICE A | CAL MO | 2,363 | $2,568.09 | Sep 18, 2026 |
| X7010216 | TRAF CONT & PROT SPL | L SUM | 2,263 | $104,052.22 | Sep 18, 2026 |
| Z0013798 | CONSTRUCTION LAYOUT | L SUM | 2,261 | $47,241.27 | Sep 18, 2026 |
| 40600982 | HMA SURF REM BUTT JT | SQ YD | 2,248 | $14.59 | Sep 18, 2026 |
| Z0076600 | TRAINEES | HOUR | 2,213 | $0.8000 | Sep 18, 2026 |
| 78000200 | THPL PVT MK LINE 4 | FOOT | 2,210 | $0.7080 | Sep 18, 2026 |
| 44000600 | SIDEWALK REM | SQ FT | 2,037 | $2.59 | Sep 18, 2026 |
| 25000400 | NITROGEN FERT NUTR | POUND | 2,012 | $2.19 | Sep 18, 2026 |
| 25000600 | POTASSIUM FERT NUTR | POUND | 2,006 | $2.19 | Sep 18, 2026 |
| 78000600 | THPL PVT MK LINE 12 | FOOT | 1,966 | $3.11 | Sep 18, 2026 |
| 78000650 | THPL PVT MK LINE 24 | FOOT | 1,925 | $5.83 | Sep 18, 2026 |
| 28000400 | PERIMETER EROS BAR | FOOT | 1,885 | $3.07 | Sep 18, 2026 |
| 44000100 | PAVEMENT REM | SQ YD | 1,877 | $14.86 | Sep 18, 2026 |
| 78000400 | THPL PVT MK LINE 6 | FOOT | 1,850 | $0.9522 | Sep 18, 2026 |
| 42400800 | DETECTABLE WARNINGS | SQ FT | 1,839 | $34.72 | Sep 18, 2026 |
| 28000250 | TEMP EROS CONTR SEED | POUND | 1,824 | $1.73 | Sep 18, 2026 |
| 78000100 | THPL PVT MK LTR & SYM | SQ FT | 1,800 | $5.45 | Sep 18, 2026 |
| 66900200 | NON SPL WASTE DISPOSL | CU YD | 1,784 | $49.10 | Sep 18, 2026 |
| 66900530 | SOIL DISPOSAL ANALY | EACH | 1,780 | $1,372.18 | Sep 18, 2026 |
| 44000500 | COMB CURB GUTTER REM | FOOT | 1,774 | $9.37 | Sep 18, 2026 |
| 70100450 | TRAF CONT-PROT 701201 | L SUM | 1,751 | $10,276.12 | Sep 18, 2026 |
| 50800205 | REINF BARS, EPOXY CTD | POUND | 1,746 | $1.70 | Sep 18, 2026 |
| Z0030850 | TEMP INFO SIGNING | SQ FT | 1,744 | $19.92 | Sep 18, 2026 |
| 40600990 | TEMPORARY RAMP | SQ YD | 1,664 | $17.40 | Sep 18, 2026 |
| 66901001 | REG SUB P-CONST PLAN | LSUM | 1,640 | $3,344.95 | Sep 18, 2026 |
| 66901003 | REG SUB F CON REPORT | LSUM | 1,637 | $1,797.34 | Sep 18, 2026 |
| 63200310 | GUARDRAIL REMOV | FOOT | 1,584 | $6.86 | Sep 18, 2026 |
| 25000500 | PHOSPHORUS FERT NUTR | POUND | 1,560 | $2.11 | Sep 18, 2026 |
| 72501000 | TERMINAL MARKER - DA | EACH | 1,527 | $38.86 | Sep 18, 2026 |
| 63100167 | TR BAR TRM T1 SPL TAN | EACH | 1,519 | $3,590.01 | Sep 18, 2026 |
| 70102635 | TR CONT & PROT 701701 | L SUM | 1,502 | $4,780.08 | Sep 18, 2026 |
| 72000100 | SIGN PANEL T1 | SQ FT | 1,490 | $29.05 | Sep 18, 2026 |
| 70400100 | TEMP CONC BARRIER | FOOT | 1,485 | $27.95 | Sep 18, 2026 |
| 66901006 | REG SUB MON | CAL DA | 1,464 | $795.32 | Sep 18, 2026 |
| 48102100 | AGG WEDGE SHLD TYPE B | TON | 1,426 | $35.81 | Sep 18, 2026 |
| 42400200 | PC CONC SIDEWALK 5 | SQ FT | 1,421 | $8.53 | Sep 18, 2026 |
| 70102640 | TR CONT & PROT 701801 | L SUM | 1,403 | $3,783.12 | Sep 18, 2026 |
| 44000200 | DRIVE PAVEMENT REM | SQ YD | 1,382 | $14.76 | Sep 18, 2026 |
| 40600370 | LONG JOINT SEALANT | FOOT | 1,352 | $2.97 | Sep 18, 2026 |
| 21101615 | TOPSOIL F & P 4 | SQ YD | 1,344 | $4.43 | Sep 18, 2026 |
| 70102620 | TR CONT & PROT 701501 | L SUM | 1,321 | $19,015.57 | Sep 18, 2026 |
| 20800150 | TRENCH BACKFILL | CU YD | 1,314 | $38.06 | Sep 18, 2026 |
| 28200200 | FILTER FABRIC | SQ YD | 1,313 | $3.52 | Sep 18, 2026 |
| 70100460 | TRAF CONT-PROT 701306 | L SUM | 1,313 | $27,922.40 | Sep 18, 2026 |
| 70400200 | REL TEMP CONC BARRIER | FOOT | 1,285 | $8.24 | Sep 18, 2026 |
| 25100630 | EROSION CONTR BLANKET | SQ YD | 1,280 | $1.31 | Sep 18, 2026 |
| 78001110 | PAINT PVT MK LINE 4 | FOOT | 1,261 | $0.1203 | Sep 18, 2026 |
| 42001300 | PROTECTIVE COAT | SQ YD | 1,252 | $0.5181 | Sep 18, 2026 |
| 40800050 | INCIDENTAL HMA SURF | TON | 1,246 | $200.88 | Sep 18, 2026 |
| 63000001 | SPBGR TY A 6FT POSTS | FOOT | 1,227 | $31.52 | Sep 18, 2026 |
| 28000305 | TEMP DITCH CHECKS | FOOT | 1,214 | $12.30 | Sep 18, 2026 |
| 78300202 | PVT MKG REM WTR BLAST | SQ FT | 1,204 | $1.01 | Sep 18, 2026 |
| 20400800 | FURNISHED EXCAVATION | CU YD | 1,201 | $18.60 | Sep 18, 2026 |
| 50300300 | PROTECTIVE COAT | SQ YD | 1,195 | $2.25 | Sep 18, 2026 |
| 78200005 | GRDRAIL REF TYPE A | EACH | 1,191 | $12.66 | Sep 18, 2026 |
| 50300255 | CONC SUP-STR | CU YD | 1,190 | $1,357.21 | Sep 18, 2026 |
| 78009004 | MOD URETH PM LINE 4 | FOOT | 1,179 | $0.6385 | Sep 18, 2026 |
| 50300225 | CONC STRUCT | CU YD | 1,158 | $1,011.86 | Sep 18, 2026 |
| 70103815 | TR CONT SURVEILLANCE | CAL DA | 1,137 | $151.70 | Sep 18, 2026 |
| 40600400 | MIX CR JTS FLANGEWYS | TON | 1,125 | $162.22 | Sep 18, 2026 |
| 25000210 | SEEDING CL 2A | ACRE | 1,117 | $2,294.38 | Sep 18, 2026 |
| 28000500 | INLET & PIPE PROTECT | EACH | 1,106 | $192.28 | Sep 18, 2026 |
| 20100110 | TREE REMOV 6-15 | UNIT | 1,085 | $26.88 | Sep 18, 2026 |
| 28000510 | INLET FILTERS | EACH | 1,080 | $161.73 | Sep 18, 2026 |
| 50102400 | CONC REM | CU YD | 1,053 | $1,628.41 | Sep 18, 2026 |
| 51500100 | NAME PLATES | EACH | 1,022 | $778.02 | Sep 18, 2026 |
| 40600275 | BIT MATLS PR CT | POUND | 1,005 | $0.3811 | Sep 18, 2026 |
| 20201200 | REM & DISP UNS MATL | CU YD | 989 | $24.19 | Sep 18, 2026 |
| Z0048665 | RR PROT LIABILITY INS | L SUM | 983 | $11,444.01 | Sep 18, 2026 |
| 72800100 | TELES STL SIN SUPPORT | FOOT | 971 | $17.86 | Sep 18, 2026 |
| 20100210 | TREE REMOV OVER 15 | UNIT | 959 | $43.94 | Sep 18, 2026 |
| 25200110 | SODDING SALT TOLERANT | SQ YD | 955 | $11.61 | Sep 18, 2026 |
| 50105220 | PIPE CULVERT REMOV | FOOT | 954 | $24.09 | Sep 18, 2026 |
| 60605000 | COMB CC&G TY B-6.24 | FOOT | 952 | $39.65 | Sep 18, 2026 |
| 25200200 | SUPPLE WATERING | UNIT | 945 | $25.73 | Sep 18, 2026 |
| 78000500 | THPL PVT MK LINE 8 | FOOT | 933 | $1.79 | Sep 18, 2026 |
| 70300220 | TEMP PVT MK LINE 4 | FOOT | 928 | $0.1244 | Jan 21, 2022 |
| 60603800 | COMB CC&G TB6.12 | FOOT | 914 | $33.56 | Sep 18, 2026 |
| 50200100 | STRUCTURE EXCAVATION | CU YD | 913 | $37.28 | Sep 18, 2026 |
| 44213200 | SAW CUTS | FOOT | 912 | $3.82 | Sep 18, 2026 |
| 25100115 | MULCH METHOD 2 | ACRE | 895 | $1,547.31 | Sep 18, 2026 |
| 44004250 | PAVED SHLD REMOVAL | SQ YD | 892 | $14.68 | Sep 18, 2026 |
| 44000155 | HMA SURF REM 1 1/2 | SQ YD | 889 | $2.64 | Sep 18, 2026 |
| 70300221 | TEMP PVT MK LINE 4 - PAINT | FOOT | 867 | $0.1555 | Sep 18, 2026 |
| X7030005 | TEMP PAVT MKING REMOV | SQ FT | 857 | $0.2017 | Apr 29, 2022 |
| 78009006 | MOD URETH PM LINE 6 | FOOT | 839 | $0.9693 | Sep 18, 2026 |
| 85000200 | MAIN EX TR SIG INSTAL | EACH | 839 | $2,478.04 | Sep 18, 2026 |
| 50800515 | BAR SPLICERS | EACH | 838 | $42.95 | Sep 18, 2026 |
| 60255500 | MAN ADJUST | EACH | 819 | $917.83 | Sep 18, 2026 |
| 63100085 | TRAF BAR TERM T6 | EACH | 810 | $3,930.65 | Sep 18, 2026 |
| 78009012 | MOD URETH PM LINE 12 | FOOT | 790 | $3.50 | Sep 18, 2026 |
1–100 of 13,847Next ›
Averages are weighted by quantity. "Avg low bid" uses the apparent low bidder's unit prices; "Avg all bids" uses every bidder; "Avg estimate" is TxDOT's engineer's estimate. Built from TxDOT bid tabulations loaded into Bid Potato.