$21,623.43Avg low bid / EACH
$23,532.04Avg of all bids
—Avg engineer's estimate
108Jobs · 108 EACH
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2026 | 11 | 11 | $14,808.55 | $13,513.01 |
| 2025 | 14 | 14 | $20,717.43 | $20,481.26 |
| 2024 | 12 | 12 | $18,541.67 | $22,463.64 |
| 2023 | 5 | 5 | $46,820.00 | $60,117.27 |
| 2022 | 14 | 14 | $20,892.71 | $20,580.56 |
| 2021 | 13 | 13 | $22,250.21 | $26,113.75 |
| 2020 | 12 | 12 | $21,600.33 | $29,944.48 |
| 2019 | 14 | 14 | $20,004.43 | $19,670.25 |
| 2018 | 13 | 13 | $23,444.31 | $24,341.48 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jun 12, 2026 | 76U81 | Madison, St. ClairDistrict 8 | 1 EACH | $40,000.00 | M & M Concrete, Inc. |
| Feb 27, 2026 | 64V15 | VariousDistrict 2 | 1 EACH | $7,500.00 | Interstate Maintenance, Incorporated |
| Feb 27, 2026 | 64V11 | Rock IslandDistrict 2 | 1 EACH | $8,700.00 | Pressure Washing Unlimited Inc. |
| Feb 27, 2026 | 68K11 | VariousDistrict 4 | 1 EACH | $49,000.00 | All States Painting, Inc. |
| Feb 27, 2026 | 64V12 | WinnebagoDistrict 2 | 1 EACH | $8,000.00 | All States Painting, Inc. |
| Feb 27, 2026 | 64V13 | Winnebago, BooneDistrict 2 | 1 EACH | $2,500.00 | M & M Concrete, Inc. |
| Feb 27, 2026 | 64V14 | VariousDistrict 2 | 1 EACH | $3,150.00 | All States Painting, Inc. |
| Jan 16, 2026 | 64V08 | VariousDistrict 2 | 1 EACH | $8,950.00 | Pressure Washing Unlimited Inc. |
| Jan 16, 2026 | 64V09 | Rock Island HenryDistrict 2 | 1 EACH | $9,669.00 | Pressure Washing Unlimited Inc. |
| Jan 16, 2026 | 64V10 | VariousDistrict 2 | 1 EACH | $7,125.00 | All States Painting, Inc. |
| Jan 16, 2026 | 72047 | VariousDistrict 6 | 1 EACH | $18,300.00 | All States Painting, Inc. |
| Nov 7, 2025 | 64V05 | Rock IslandDistrict 2 | 1 EACH | $65,000.00 | Interstate Maintenance, Incorporated |
| Nov 7, 2025 | 64V07 | Carroll, Rock Island WhitesideDistrict 2 | 1 EACH | $49,000.00 | M & M Concrete, Inc. |
| Apr 25, 2025 | 62W87 | CookDistrict 1 | 1 EACH | $35,000.00 | Lorig Construction Company |
| Mar 7, 2025 | 64U08 | WinnebagoDistrict 2 | 1 EACH | $8,800.00 | Pressure Washing Unlimited Inc. |
| Mar 7, 2025 | 64U10 | VariousDistrict 2 | 1 EACH | $4,750.00 | Pressure Washing Unlimited Inc. |
| Mar 7, 2025 | 64U11 | VariousDistrict 2 | 1 EACH | $8,025.00 | Pressure Washing Unlimited Inc. |
| Mar 7, 2025 | 66N42 | LasalleDistrict 3 | 1 EACH | $40,000.00 | Interstate Maintenance, Incorporated |
| Mar 7, 2025 | 64U09 | Winnebago, BooneDistrict 2 | 1 EACH | $2,350.00 | Pressure Washing Unlimited Inc. |
| Mar 7, 2025 | 64U07 | Rock IslandDistrict 2 | 1 EACH | $9,500.00 | Pressure Washing Unlimited Inc. |
| Jan 17, 2025 | 68J35 | VariousDistrict 4 | 1 EACH | $25,500.00 | M & M Concrete, Inc. |
| Jan 17, 2025 | 72007 | VariousDistrict 6 | 1 EACH | $18,000.00 | Interstate Maintenance, Incorporated |
| Jan 17, 2025 | 64T35 | VariousDistrict 2 | 1 EACH | $6,000.00 | All States Painting, Inc. |
| Jan 17, 2025 | 64T39 | VariousDistrict 2 | 1 EACH | $8,050.00 | Pressure Washing Unlimited Inc. |
| Jan 17, 2025 | 64T40 | Rock Island HenryDistrict 2 | 1 EACH | $10,069.00 | Pressure Washing Unlimited Inc. |
| Nov 8, 2024 | 64T36 | Carrol, Rock Island WhitesideDistrict 2 | 1 EACH | $50,000.00 | M & M Concrete, Inc. |
| Nov 8, 2024 | 64T37 | Rock IslandDistrict 2 | 1 EACH | $55,000.00 | M & M Concrete, Inc. |
| Mar 8, 2024 | 64S99 | Rock IslandDistrict 2 | 1 EACH | $10,000.00 | M & M Concrete, Inc. |
| Mar 8, 2024 | 64S26 | WinnebagoDistrict 2 | 1 EACH | $10,500.00 | All States Painting, Inc. |
| Mar 8, 2024 | 64S34 | VariousDistrict 2 | 1 EACH | $5,200.00 | M & M Concrete, Inc. |
| Mar 8, 2024 | 64S35 | VariousDistrict 2 | 1 EACH | $8,500.00 | M & M Concrete, Inc. |
| Mar 8, 2024 | 64S36 | Boone, WinnebagoDistrict 2 | 1 EACH | $2,300.00 | M & M Concrete, Inc. |
| Jan 19, 2024 | 68H78 | VariousDistrict 4 | 1 EACH | $35,000.00 | All States Painting, Inc. |
| Jan 19, 2024 | 64S42 | VariousDistrict 2 | 1 EACH | $9,000.00 | All States Painting, Inc. |
| Jan 19, 2024 | 64S46 | Henry, Rock IslandDistrict 2 | 1 EACH | $11,000.00 | Interstate Maintenance, Incorporated |
| Jan 19, 2024 | 64S47 | VariousDistrict 2 | 1 EACH | $9,000.00 | Interstate Maintenance, Incorporated |
| Jan 19, 2024 | 72616 | VariousDistrict 6 | 1 EACH | $17,000.00 | All States Painting, Inc. |
| Nov 17, 2023 | 64S43 | Rock IslandDistrict 2 | 1 EACH | $70,000.00 | Interstate Maintenance, Incorporated |
| Nov 17, 2023 | 64S45 | VariousDistrict 2 | 1 EACH | $41,000.00 | Interstate Maintenance, Incorporated |
| Jun 16, 2023 | 66N43 | Grundy, LasalleDistrict 3 | 1 EACH | $40,600.00 | All States Painting, Inc. |
| Mar 10, 2023 | 68H30 | VariousDistrict 4 | 1 EACH | $65,000.00 | M & M Concrete, Inc. |
| Jan 20, 2023 | 72043 | VariousDistrict 6 | 1 EACH | $17,500.00 | All States Painting, Inc. |
| Nov 18, 2022 | 64R81 | VariousDistrict 2 | 1 EACH | $40,000.00 | M & M Concrete, Inc. |
| Nov 18, 2022 | 64R73 | WinnebagoDistrict 2 | 1 EACH | $12,000.00 | Interstate Maintenance, Incorporated |
| Nov 18, 2022 | 64R82 | VariousDistrict 2 | 1 EACH | $12,750.00 | All States Painting, Inc. |
| Nov 18, 2022 | 64R74 | Boone, WinnebagoDistrict 2 | 1 EACH | $2,500.00 | M & M Concrete, Inc. |
| Nov 18, 2022 | 64R83 | Henry, Rock IslandDistrict 2 | 1 EACH | $9,000.00 | All States Painting, Inc. |
| Nov 18, 2022 | 64R75 | VariousDistrict 2 | 1 EACH | $5,500.00 | M & M Concrete, Inc. |
| Nov 18, 2022 | 64R84 | VariousDistrict 2 | 1 EACH | $8,300.00 | All States Painting, Inc. |
| Nov 18, 2022 | 64R76 | VariousDistrict 2 | 1 EACH | $9,600.00 | All States Painting, Inc. |
| Nov 18, 2022 | 64R80 | Rock IslandDistrict 2 | 1 EACH | $79,400.00 | Interstate Maintenance, Incorporated |
| Aug 5, 2022 | 76P12 | MadisonDistrict 8 | 1 EACH | $6,608.00 | Thomas Industrial Coatings, Inc. |
| Jun 17, 2022 | 66M35 | Bureau, LasalleDistrict 3 | 1 EACH | $45,000.00 | All States Painting, Inc. |
| Mar 11, 2022 | 68G58 | Marshall, Tazewell, MasonDistrict 4 | 1 EACH | $22,000.00 | Interstate Maintenance, Incorporated |
| Jan 21, 2022 | 62M54 | CookDistrict 1 | 1 EACH | $15,840.00 | D. Construction, Inc. |
| Jan 21, 2022 | 72N08 | VariousDistrict 6 | 1 EACH | $24,000.00 | All States Painting, Inc. |
| Nov 5, 2021 | 64P98 | VariousDistrict 2 | 1 EACH | $43,000.00 | All States Painting, Inc. |
| Nov 5, 2021 | 64R07 | VariousDistrict 2 | 1 EACH | $7,500.00 | All States Painting, Inc. |
| Nov 5, 2021 | 64P99 | VariousDistrict 2 | 1 EACH | $12,000.00 | All States Painting, Inc. |
| Nov 5, 2021 | 64R00 | Henry, Rock IslandDistrict 2 | 1 EACH | $8,000.00 | All States Painting, Inc. |
| Nov 5, 2021 | 64R01 | VariousDistrict 2 | 1 EACH | $7,500.00 | All States Painting, Inc. |
| Nov 5, 2021 | 64R05 | VariousDistrict 2 | 1 EACH | $8,875.00 | All States Painting, Inc. |
| Nov 5, 2021 | 64P97 | Rock IslandDistrict 2 | 1 EACH | $68,500.00 | All States Painting, Inc. |
| Nov 5, 2021 | 64R06 | Winnebago, BooneDistrict 2 | 1 EACH | $9,023.77 | Interstate Maintenance, Incorporated |
| Jun 11, 2021 | 62M41 | CookDistrict 1 | 1 EACH | $37,855.00 | Areatha Construction Co., Inc. |
| Jan 15, 2021 | 72M42 | PikeDistrict 6 | 1 EACH | $17,500.00 | White Construction LLC |
| Jan 15, 2021 | 68F63 | Marshall, Tazewell, MasonDistrict 4 | 1 EACH | $24,999.00 | Interstate Maintenance, Incorporated |
| Jan 15, 2021 | 72M38 | Adams, HancockDistrict 6 | 1 EACH | $39,500.00 | All States Painting, Inc. |
| Jan 15, 2021 | 72M41 | Cass, MenardDistrict 6 | 1 EACH | $5,000.00 | All States Painting, Inc. |
| Nov 6, 2020 | 64P24 | VariousDistrict 2 | 1 EACH | $8,000.00 | All States Painting, Inc. |
| Nov 6, 2020 | 60W34 | WillDistrict 1 | 1 EACH | $25,000.00 | D. Construction, Inc. and P. T. Ferro Construction Company JV |
| Nov 6, 2020 | 64P17 | VariousDistrict 2 | 1 EACH | $8,448.00 | Interstate Maintenance, Incorporated |
| Nov 6, 2020 | 64P18 | WinnebagoDistrict 2 | 1 EACH | $4,500.00 | M & M Concrete, Inc. |
| Nov 6, 2020 | 64P19 | VariousDistrict 2 | 1 EACH | $7,000.00 | All States Painting, Inc. |
| Sep 18, 2020 | 64P20 | VariousDistrict 2 | 1 EACH | $12,000.00 | All States Painting, Inc. |
| Sep 18, 2020 | 64P21 | Rock IslandDistrict 2 | 1 EACH | $86,807.00 | Interstate Maintenance, Incorporated |
| Sep 18, 2020 | 64P22 | VariousDistrict 2 | 1 EACH | $43,299.00 | Interstate Maintenance, Incorporated |
| Sep 18, 2020 | 64P23 | VariousDistrict 2 | 1 EACH | $8,000.00 | All States Painting, Inc. |
| Sep 18, 2020 | 72M37 | ScottDistrict 6 | 1 EACH | $4,150.00 | Halverson Construction Co., Inc. |
| Jan 17, 2020 | 68F18 | Mason, MarshallDistrict 4 | 1 EACH | $27,500.00 | M & M Concrete, Inc. |
| Jan 17, 2020 | 72K09 | VariousDistrict 6 | 1 EACH | $24,500.00 | M & M Concrete, Inc. |
| Nov 8, 2019 | 64N78 | VariousDistrict 2 | 1 EACH | $7,000.00 | All States Painting, Inc. |
| Nov 8, 2019 | 64N81 | VariousDistrict 2 | 1 EACH | $8,008.00 | Interstate Maintenance, Incorporated |
| Sep 20, 2019 | 64N82 | VariousDistrict 2 | 1 EACH | $10,000.00 | All States Painting, Inc. |
| Sep 20, 2019 | 64N83 | Rock IslandDistrict 2 | 1 EACH | $71,664.00 | Interstate Maintenance, Incorporated |
| Sep 20, 2019 | 64N84 | VariousDistrict 2 | 1 EACH | $41,292.00 | Interstate Maintenance, Incorporated |
| Sep 20, 2019 | 64N85 | VariousDistrict 2 | 1 EACH | $9,000.00 | All States Painting, Inc. |
| Sep 20, 2019 | 64N86 | VariousDistrict 2 | 1 EACH | $9,000.00 | All States Painting, Inc. |
| Sep 20, 2019 | 64N79 | WinnebagoDistrict 2 | 1 EACH | $6,600.00 | M & M Concrete, Inc. |
| Jun 14, 2019 | 66K10 | Grundy, LasalleDistrict 3 | 1 EACH | $24,000.00 | All States Painting, Inc. |
| Apr 26, 2019 | 64N52 | VariousDistrict 2 | 1 EACH | $7,598.00 | Interstate Maintenance, Incorporated |
| Apr 26, 2019 | 64N53 | WinnebagoDistrict 2 | 1 EACH | $6,400.00 | M & M Concrete, Inc. |
| Apr 26, 2019 | 64N54 | VariousDistrict 2 | 1 EACH | $8,000.00 | All States Painting, Inc. |
| Mar 8, 2019 | 68E68 | Tazewell, Marshall, MasonDistrict 4 | 1 EACH | $50,000.00 | All States Painting, Inc. |
| Jan 18, 2019 | 72K03 | Adams, HancockDistrict 6 | 1 EACH | $21,500.00 | Interstate Maintenance, Incorporated |
| Nov 9, 2018 | 64M95 | Rock IslandDistrict 2 | 1 EACH | $60,900.00 | Interstate Maintenance, Incorporated |
| Nov 9, 2018 | 64M96 | Carroll, Rock Island WhitesideDistrict 2 | 1 EACH | $37,967.00 | Interstate Maintenance, Incorporated |
| Nov 9, 2018 | 64M97 | Henry, Rock Island WhitesideDistrict 2 | 1 EACH | $8,500.00 | All States Painting, Inc. |
| Nov 9, 2018 | 64M98 | Henry, Rock IslandDistrict 2 | 1 EACH | $8,500.00 | All States Painting, Inc. |
| Nov 9, 2018 | 64M99 | VariousDistrict 2 | 1 EACH | $8,000.00 | All States Painting, Inc. |
| Jun 15, 2018 | 64M72 | Rock Island, WhitesideDistrict 2 | 1 EACH | $11,706.00 | Interstate Maintenance, Incorporated |
| Jun 15, 2018 | 64M60 | Henry, Rock IslandDistrict 2 | 1 EACH | $9,296.00 | Interstate Maintenance, Incorporated |
| Jun 15, 2018 | 64M67 | VariousDistrict 2 | 1 EACH | $10,515.00 | Interstate Maintenance, Incorporated |
| Jun 15, 2018 | 64M68 | Rock IslandDistrict 2 | 1 EACH | $10,621.00 | Interstate Maintenance, Incorporated |
| Jun 15, 2018 | 64M70 | VariousDistrict 2 | 1 EACH | $16,684.00 | Interstate Maintenance, Incorporated |
| Jun 15, 2018 | 64M71 | Rock Island WhitesideDistrict 2 | 1 EACH | $39,093.00 | Interstate Maintenance, Incorporated |
| Apr 27, 2018 | 68E01 | Marshall, Tazewell, MasonDistrict 4 | 1 EACH | $64,000.00 | All States Painting, Inc. |
| Jan 19, 2018 | 72J85 | Adams, HancockDistrict 6 | 1 EACH | $18,994.00 | Interstate Maintenance, Incorporated |