D2 BC 2025-09
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Pressure Washing Unlimited Inc. Low bidder | $20,900 | ||
| 2 | All States Painting, Inc. | $21,240 | +1.6% | |
| 3 | Interstate Maintenance, Incorporated | $26,900 | +28.7% | |
| 4 | M & M Concrete, Inc. | $26,900 | +28.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Pressure Washin… | #2 All States Pain… | #3 Interstate Main… | #4 M & M Concrete,… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | 59200101 | BRIDGE WASHING N1 | 1 | EACH | $8,800.00 | $9,950.00 | $10,000.00 | $9,400.00 | |
| 2 | 59200102 | BRIDGE WASHING N2 | 1 | EACH | $8,800.00 | $9,950.00 | $10,000.00 | $9,400.00 | |
| 3 | 67100100 | MOBILIZATION | 1 | L SUM | $1,300.00 | $1,240.00 | $6,800.00 | $1,500.00 | |
| 4 | 70100800 | TRAF CONT-PROT 701401 | 1 | L SUM | $2,000.00 | $100.00 | $100.00 | $6,600.00 |