D2 BC 2020-4
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Interstate Maintenance, Incorporated Low bidder | $159,652 | ||
| 2 | M & M Concrete, Inc. | $169,999 | +6.5% | |
| 3 | All States Painting, Inc. | $188,000 | +17.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Interstate Main… | #2 M & M Concrete,… | #3 All States Pain… |
|---|---|---|---|---|---|---|---|---|
| 1 | 59200101 | BRIDGE WASHING N1 | 1 | EACH | $8,008.00 | $8,500.00 | $12,000.00 | |
| 2 | 59200102 | BRIDGE WASHING N2 | 1 | EACH | $8,008.00 | $8,500.00 | $8,000.00 | |
| 3 | 59200103 | BRIDGE WASHING N3 | 1 | EACH | $8,008.00 | $6,600.00 | $8,000.00 | |
| 4 | 59200104 | BRIDGE WASHING N4 | 1 | EACH | $8,008.00 | $10,400.00 | $12,000.00 | |
| 5 | 59200105 | BRIDGE WASHING N5 | 1 | EACH | $8,008.00 | $8,500.00 | $10,000.00 | |
| 6 | 59200106 | BRIDGE WASHING N6 | 1 | EACH | $8,008.00 | $8,500.00 | $8,000.00 | |
| 7 | 59200107 | BRIDGE WASHING N7 | 1 | EACH | $8,008.00 | $8,500.00 | $10,000.00 | |
| 8 | 59200108 | BRIDGE WASHING N8 | 1 | EACH | $8,008.00 | $8,500.00 | $10,000.00 | |
| 9 | 59200109 | BRIDGE WASHING N9 | 1 | EACH | $8,008.00 | $6,600.00 | $8,000.00 | |
| 10 | 59200110 | BRIDGE WASHING N10 | 1 | EACH | $8,008.00 | $8,500.00 | $12,000.00 | |
| 11 | 59200111 | BRIDGE WASHING N11 | 1 | EACH | $8,008.00 | $6,600.00 | $10,000.00 | |
| 12 | 59200112 | BRIDGE WASHING N12 | 1 | EACH | $8,008.00 | $8,500.00 | $12,000.00 | |
| 13 | 59200113 | BRIDGE WASHING N13 | 1 | EACH | $8,008.00 | $6,600.00 | $10,000.00 | |
| 14 | 59200114 | BRIDGE WASHING N14 | 1 | EACH | $8,008.00 | $8,500.00 | $8,000.00 | |
| 15 | 59200115 | BRIDGE WASHING N15 | 1 | EACH | $8,008.00 | $6,900.00 | $8,000.00 | |
| 16 | 59200116 | BRIDGE WASHING N16 | 1 | EACH | $8,008.00 | $6,900.00 | $8,000.00 | |
| 17 | 59200117 | BRIDGE WASHING N17 | 1 | EACH | $8,008.00 | $6,900.00 | $6,000.00 | |
| 18 | 59200118 | BRIDGE WASHING N18 | 1 | EACH | $8,008.00 | $6,900.00 | $6,000.00 | |
| 19 | 59200119 | BRIDGE WASHING N19 | 1 | EACH | $8,008.00 | $8,800.00 | $8,000.00 | |
| 20 | 67100100 | MOBILIZATION | 1 | L SUM | $5,000.00 | $10,199.00 | $10,000.00 | |
| 21 | 70100310 | TRAF CONT-PROT 701421 | 1 | L SUM | $1,000.00 | $9,000.00 | $1,000.00 | |
| 22 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $500.00 | $500.00 | $1,000.00 | |
| 23 | 70100825 | TRAF CONT-PROT 701456 | 1 | L SUM | $500.00 | $250.00 | $1,000.00 | |
| 24 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $500.00 | $350.00 | $1,000.00 |