D2 BC 2022-9
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Interstate Maintenance, Incorporated Low bidder | $28,750 | ||
| 2 | All States Painting, Inc. | $36,400 | +26.6% | |
| 3 | M & M Concrete, Inc. | $47,000 | +63.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Interstate Main… | #2 All States Pain… | #3 M & M Concrete,… |
|---|---|---|---|---|---|---|---|---|
| 1 | 59200101 | BRIDGE WASHING N1 | 1 | EACH | $12,000.00 | $15,000.00 | $15,000.00 | |
| 2 | 59200102 | BRIDGE WASHING N2 | 1 | EACH | $12,000.00 | $15,000.00 | $15,000.00 | |
| 3 | 67100100 | MOBILIZATION | 1 | L SUM | $4,000.00 | $3,000.00 | $3,000.00 | |
| 4 | 70100800 | TRAF CONT-PROT 701401 | 1 | L SUM | $750.00 | $3,400.00 | $14,000.00 |