D2 BC 2023-05
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | All States Painting, Inc. Low bidder | $81,900 | ||
| 2 | M & M Concrete, Inc. | $97,750 | +19.4% | |
| 3 | Interstate Maintenance, Incorporated | $99,998 | +22.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 All States Pain… | #2 M & M Concrete,… | #3 Interstate Main… |
|---|---|---|---|---|---|---|---|---|
| 1 | 59200101 | BRIDGE WASHING N1 | 1 | EACH | $9,300.00 | $10,100.00 | $11,337.25 | |
| 2 | 59200102 | BRIDGE WASHING N2 | 1 | EACH | $8,300.00 | $10,100.00 | $11,337.25 | |
| 3 | 59200103 | BRIDGE WASHING N3 | 1 | EACH | $8,300.00 | $7,700.00 | $11,337.25 | |
| 4 | 59200104 | BRIDGE WASHING N4 | 1 | EACH | $9,800.00 | $13,600.00 | $11,337.25 | |
| 5 | 59200105 | BRIDGE WASHING N5 | 1 | EACH | $8,300.00 | $9,100.00 | $11,337.25 | |
| 6 | 59200106 | BRIDGE WASHING N6 | 1 | EACH | $8,300.00 | $9,100.00 | $11,337.25 | |
| 7 | 59200107 | BRIDGE WASHING N7 | 1 | EACH | $8,300.00 | $10,100.00 | $11,337.25 | |
| 8 | 59200108 | BRIDGE WASHING N8 | 1 | EACH | $11,300.00 | $15,200.00 | $11,337.25 | |
| 9 | 67100100 | MOBILIZATION | 1 | L SUM | $4,500.00 | $6,000.00 | $9,000.00 | |
| 10 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $1,500.00 | $250.00 | $100.00 | |
| 11 | 70100700 | TRAF CONT-PROT 701406 | 1 | L SUM | $2,000.00 | $5,500.00 | $100.00 | |
| 12 | 70102625 | TR CONT & PROT 701606 | 1 | L SUM | $2,000.00 | $1,000.00 | $100.00 |