4,924Let jobs
$18,253,865,633Total low bids
$20,260,575,946Total estimates
-9.9%Low bids vs estimates
All dates results
Bid tabs (Excel) ExcelCSV| Let date | CCSJ | County / District | Project | Estimate | Low bid | Low bidder | % vs est. | Bidders |
|---|---|---|---|---|---|---|---|---|
| Nov 4, 2026 | 6508-43-001BPM - A00223826 | Donley Childress |
FY27 Bridge Preventative MaintenanceUS0287 · Bridge Preventative Maintenance - Sealed | $1,130,180 | $701,941 | BLACKSMITH VENTURES LLC | -37.9% | 16 |
| Nov 4, 2026 | 0500-01-158F 2027(017) | Galveston Houston |
IH 45 at Causeway Bridge LightingIH 45 · Traffic Control Devices | $510,426 | $607,082 | DECO CONTRACTORS, INC. | +18.9% | 5 |
| Nov 4, 2026 | 0353-01-031F 2027(022) | Wise Fort Worth |
SH 114 at Alliance BlvdSH 114 · Intersection & Operational Imprv | $620,363 | $482,224 | XIT PAVING AND CONSTRUCTION INC. | -22.3% | 7 |
| Nov 3, 2026 | 0015-13-432F 2026(789) | Travis Austin |
CapEx-C - UT Advanced Construction UTACIH 35 · Widen Freeway | $409,816,599 | $412,233,374 | AUSTIN BRIDGE & ROAD SERVICES, LP | +0.6% | 6 |
| Nov 3, 2026 | 0044-06-079F 2027(024) | Montague Wichita Falls |
US 82, St Jo to Cooke CLUS 82 · Seal Coat | $13,456,738 | $12,173,490 | BREEDON INVESTMENTS USA INC. | -9.5% | 6 |
| Nov 3, 2026 | 2552-01-062F 2027(238) | El Paso El Paso |
SL375 MILL & INLAY (IH 10 | TOM MAYS PK)SL 375 · Restoration | $14,597,735 | $11,850,861 | ALLEN CONCRETE, LLC | -18.8% | 6 |
| Nov 3, 2026 | 0220-01-038F 2027(043) | Hidalgo Pharr |
US 281 - OverlayUS 281 · Overlay | $12,874,559 | $11,560,279 | FOREMOST PAVING, INC. | -10.2% | 2 |
| Nov 3, 2026 | 0059-05-048F 2027(074) | Shelby Lufkin |
SH 7_Flat Fork Creek to US 84 - SCSH 7 · Seal Coat | $10,317,165 | $10,730,970 | CLARK CONSTRUCTION OF TEXAS, INC. | +4.0% | 5 |
| Nov 3, 2026 | 0168-09-191BR 2027(067) | Randall Amarillo |
IH 27 NB/WESTERN AVE BRG FY 27 BMIPIH 27 · Bridge Maintenance | $5,816,554 | $5,800,486 | COPPELL CONSTRUCTION CO., INC. | -0.3% | 8 |
| Nov 3, 2026 | 6509-25-001RMC - A00223986 | Harris Houston |
Sweeping and Debris North & West 2027IH0069 · Routine Maintenance Project - Sealed | $3,805,043 | $4,495,312 | SWEEPING CORPORATION OF AMERICA, LLC | +18.1% | 2 |
| Nov 3, 2026 | 0901-00-066C 901-00-66 | Lamar Paris |
2027 Seal Coat Striping RetraceVarious · Seal Coat | $3,967,494 | $3,520,879 | STRIPING TECHNOLOGY, L.P. | -11.3% | 4 |
| Nov 3, 2026 | 0045-09-113F 2027(050) | Lamar Paris |
BU 82 H Overlay/ONYXBU 82H · Overlay | $3,685,991 | $3,510,998 | DRAKE COMPANIES LLC | -4.7% | 5 |
| Nov 3, 2026 | 0054-05-027C 54-5-27 | Coleman Brownwood |
SH153 SAN SABA ST TO US84 FY27 MILL&SEALSH 153 · Seal Coat | $2,448,783 | $2,929,127 | RONALD R. WAGNER & CO., LP | +19.6% | 4 |
| Nov 3, 2026 | 0022-03-032BR 2026(514) | Terrell Odessa |
NBI_06-222-0-0022-03-011_BMIPUS 90 · Bridge Maintenance | $3,246,904 | $2,888,888 | THE TRUESDELL CORPORATION | -11.0% | 7 |
| Nov 3, 2026 | 6510-76-001RMC - A00224308 | Bexar San Antonio |
NORTH TRAFFIC CONTROL FY 27IH0010 · Routine Maintenance Project - Sealed | $2,531,500 | $2,716,850 | AUSTIN BARRICADE COMPANY, L.L.C. | +7.3% | 4 |
| Nov 3, 2026 | 6496-55-001MMC - A00219446 | Bastrop Austin |
FY 27 Districtwide Seal Coat AggregateFM0535 · Material Maintenance Project | $2,672,500 | $2,525,950 | TOUCHSTONE RESOURCES, LLC | -5.5% | 4 |
| Nov 3, 2026 | 6510-37-001RMC - A00224202 | McLennan Waco |
MCLENNAN - FY27 BASE FAILURE REPAIRFM3476 · Routine Maintenance Project | $2,486,802 | $2,172,910 | TEXAS MATERIALS GROUP, INC. | -12.6% | 4 |
| Nov 3, 2026 | 6504-89-001RMC - A00222928 | Harris Houston |
FY2026 - Maintenance of Traffic SignalsIH0610 · Routine Maintenance Project - Sealed | $1,322,895 | $2,035,047 | TRAF-TEX, INC. | +53.8% | 7 |
| Nov 3, 2026 | 0914-00-506C 914-00-506 | Travis Austin |
FY 27 - Striping BTAOVarious · Traffic Control Devices | $2,218,786 | $1,574,735 | TRP INFRASTRUCTURE SERVICES, LLC | -29.0% | 4 |
| Nov 3, 2026 | 0619-03-068STP 2027(201)VRU | Collin Dallas |
FM 544 at McCeary Rd in City of WylieFM 544 · Traffic Control Devices | $1,735,135 | $1,528,909 | RCR TELECON LLC | -11.9% | 13 |
| Nov 3, 2026 | 0038-01-107STP 2027(078)HES | Webb Laredo |
US 83, 0038-01-107 Cable BarrierUS 83 · Safety Improvement Projects | $1,590,609 | $1,490,944 | HJC FARMS, INC. | -6.3% | 4 |
| Nov 3, 2026 | 6508-86-001RMC - A00223921 | Gregg Tyler |
FY 27 Gregg/Rusk Co Traffic ControlUS0080 · Routine Maintenance Project - Sealed | $1,405,700 | $1,372,080 | HIGHWAY 19 CONSTRUCTION LLC | -2.4% | 4 |
| Nov 3, 2026 | 6508-84-001RMC - A00223911 | Midland Odessa |
6508-84-001 Mill & InlayIH0020 · Routine Maintenance Project - Sealed | $1,540,045 | $1,285,507 | RAGLE CONSTRUCTION, INC. | -16.5% | 4 |
| Nov 3, 2026 | 0271-06-141C 271-6-141 | Harris Houston |
IH 10: SH 99 to SH 6, LandscapeIH 10 · Landscape & Scenic Enhancement | $1,692,724 | $1,151,035 | YELLOWSTONE LANDSCAPE - CENTRAL, INC. | -32.0% | 5 |
| Nov 3, 2026 | 6510-38-001RMC - A00224203 | Coryell Waco |
GATESVILLE AO - FY27 BASE FAILURE REPAIRUS0084 · Routine Maintenance Project | $1,203,177 | $1,146,275 | BIG CREEK CONSTRUCTION, LTD. | -4.7% | 4 |
| Nov 3, 2026 | 6497-19-001BPM - A00219553 | Travis Austin |
FY 27 Districtwide BPMRM2222 · Bridge Preventative Maintenance - Sealed | $1,289,420 | $1,080,402 | ROAD DOCTORS LLC | -16.2% | 13 |
| Nov 3, 2026 | 6484-51-001RMC - A00215476 | Williamson Austin |
CTTS Small Signs Set 4 FY 27SH0045 · Routine Maintenance Project - Sealed | $1,160,586 | $962,812 | RHINO EQUITY, LLC | -17.0% | 7 |
| Nov 3, 2026 | 0919-00-108STP 2027(069)HES | Cass Atlanta |
2023_ATL_Various_BackplateVarious · Safety Improvement Projects | $947,552 | $877,015 | NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION | -7.4% | 10 |
| Nov 3, 2026 | 6508-47-001BPM - A00223831 | Childress Childress |
FY27 Supplemental BPM 1US0287 · Bridge Preventative Maintenance - Sealed | $1,143,630 | $792,433 | ICOS MANAGEMENT, LLC | -30.7% | 15 |
| Nov 3, 2026 | 0917-30-068BR 2025(062) | Burleson Bryan |
CR 244 (FCR 344) @ DEEP CREEK - BR FY 26COUNTY ROAD 244 · Bridge Replacement | $712,231 | $721,844 | C & W SOUTHERN LLC | +1.3% | 15 |
| Nov 3, 2026 | 0008-02-078STP 2027(100)HES | Parker Fort Worth |
US 180: AT COOL JCTUS 180 · Intersection & Operational Imprv | $632,887 | $494,986 | JAY MILLS CONTRACTING, INCORPORATED | -21.8% | 8 |
| Nov 3, 2026 | 0616-01-020C 616-1-20 | San Patricio Corpus Christi |
TPWD Lake Corpus ChristiPR 25A · Texas Park and Wildlife | $489,256 | $470,959 | LCR TOTAL TRANSPORT LLC | -3.7% | 7 |
| Nov 3, 2026 | 3330-01-011STP 2027(018)HES | McLennan Waco |
IOI | FM 3223 @ Jewell Dr | Install SigFM 3223 · Intersection & Operational Imprv | $304,689 | $291,481 | THE LEVY COMPANY, LLC | -4.3% | 9 |
| Nov 3, 2026 | 6512-91-001SUP - A00225178 | Stephens Brownwood |
STATE USE LITTER REMOVAL STEPHENS 26US0180 · State Use Project | $72,324 | — | 0 | ||
| Nov 2, 2026 | 6494-86-001RMC - A00218659 | Brown Brownwood |
HYDROBLASTING VARIOUS 2027US0377 · Routine Maintenance Project | $938,640 | $561,742 | TRP INFRASTRUCTURE SERVICES, LLC | -40.2% | 5 |
| Nov 2, 2026 | 6511-20-001EMC - A00224429 | Tarrant Fort Worth |
EMC - Bridge 287 & Erath - S. TarrantUS0287 · Emergency Maintenance Project - Sealed | $2,028,910 | — | 0 | ||
| Nov 1, 2026 | 6512-64-001SUP - A00225030 | Ellis Dallas |
Ellis Litter Removal FY27IH0045 · State Use Project | $425,428 | — | 0 | ||
| Nov 1, 2026 | 6512-69-001SUP - A00225054 | Dallas Dallas |
West Dallas Litter FY27IH0035E · State Use Project | $171,016 | — | 0 | ||
| Oct 30, 2026 | 6512-26-001SUP - A00224829 | Nacogdoches Lufkin |
2026-10 Nacogdoches Grounds and PicnicFM0343 · State Use Project | $50,300 | — | 0 | ||
| Oct 30, 2026 | 6512-30-001SUP - A00224834 | Nacogdoches Lufkin |
2026-10 Nacogdoches Mailbox/C&GFM0343 · State Use Project | $118,083 | — | 0 | ||
| Oct 30, 2026 | 6512-31-001SUP - A00224835 | Shelby Lufkin |
2026-10 Shelby Grounds and PicnicSH0007 · State Use Project | $151,591 | — | 0 | ||
| Oct 30, 2026 | 6512-32-001SUP - A00224836 | Polk Lufkin |
2026-10 Polk JanitorialUS0059 · State Use Project | $35,632 | — | 0 | ||
| Oct 29, 2026 | 6505-56-001RMC - A00223099 | Howard Abilene |
Callout Cable Barrier West FY26IH0020 · Routine Maintenance Project - Sealed | $961,136 | $1,017,742 | T&L CLEANING SERVICES LLC | +5.9% | 4 |
| Oct 29, 2026 | 6505-54-001RMC - A00223097 | Taylor Abilene |
Callout Cable Barrier East FY26IH0020 · Routine Maintenance Project - Sealed | $625,967 | $696,554 | ROSS SA ENTERPRISE LLC | +11.3% | 3 |
| Oct 29, 2026 | 6505-07-001RMC - A00222999 | Howard Abilene |
BSAO MBGF FY 27IH0020 · Routine Maintenance Project - Sealed | $994,160 | $672,620 | ROSS SA ENTERPRISE LLC | -32.3% | 4 |
| Oct 29, 2026 | 6505-06-001RMC - A00222998 | Taylor Abilene |
AAO MBGF FY 27IH0020 · Routine Maintenance Project - Sealed | $983,600 | $640,990 | ROSS SA ENTERPRISE LLC | -34.8% | 3 |
| Oct 29, 2026 | 6505-08-001RMC - A00223000 | Scurry Abilene |
SAO MBGF FY 27US0084 · Routine Maintenance Project - Sealed | $283,622 | $201,973 | ROSS SA ENTERPRISE LLC | -28.8% | 3 |
| Oct 29, 2026 | 6510-81-001SUP - A00224319 | Tarrant Fort Worth |
District Grounds MaintenanceIH0020 · State Use Project | $88,915 | — | 0 | ||
| Oct 29, 2026 | 6511-77-001SUP - A00224571 | Wise Fort Worth |
Janitorial & Grounds for Decatur OfficesUS0380 · State Use Project | $77,336 | — | 0 | ||
| Oct 29, 2026 | 6512-72-001SUP - A00225075 | Carson Amarillo |
Picnic Area Carson, Moore & Randall FY27IH0040 · State Use Project | $275,502 | — | 0 | ||
| Oct 28, 2026 | 6507-80-001BPM - A00223651 | Angelina Lufkin |
BPM - Bridge Rail UpgradesUS0059 · Bridge Preventative Maintenance | $999,970 | $681,151 | BLACKSMITH VENTURES LLC | -31.9% | 8 |
| Oct 28, 2026 | 6510-42-001RMC - A00224208 | Angelina Lufkin |
10-26 Angelina Ditch CleaningUS0059 · Routine Maintenance Project | $385,050 | $283,926 | TEXAS DRAINAGE INC. | -26.3% | 4 |
| Oct 28, 2026 | 6510-51-001RMC - A00224238 | San Augustine Lufkin |
10-27 San Augustine TreeSH0103 · Routine Maintenance Project - Sealed | $193,065 | $161,059 | ACE CONTRACTORS, INC. | -16.6% | 4 |
| Oct 28, 2026 | 6511-46-001SUP - A00224482 | Nueces Maritime Division |
6511-46-001 Port Aransas JanitorialSH0361 · State Use Project | $268,952 | — | 0 | ||
| Oct 22, 2026 | 6510-58-001MMC - A00224260 | Cass Atlanta |
District Wide Salt FY 27US0059 · Material Maintenance Project | $940,500 | $943,337 | CLEMENTS FLUIDS HENDERSON, LTD. | +0.3% | 2 |
| Oct 22, 2026 | 6510-97-001MMC - A00224391 | Comanche Brownwood |
HMA COMANCHE 2026SH0016 · Material Maintenance Project | $450,120 | $410,000 | BIG CREEK CONSTRUCTION, LTD. | -8.9% | 3 |
| Oct 22, 2026 | 6509-81-001MMC - A00224074 | Panola Atlanta |
Carthage Hot Mix FY 27US0079 · Material Maintenance Project | $396,480 | $405,480 | LONGVIEW ASPHALT, INC. | +2.3% | 2 |
| Oct 22, 2026 | 6509-83-001MMC - A00224076 | Upshur Atlanta |
Gilmer Hot Mix FY 27US0271 · Material Maintenance Project | $390,400 | $405,480 | LONGVIEW ASPHALT, INC. | +3.9% | 1 |
| Oct 22, 2026 | 6509-84-001MMC - A00224077 | Marion Atlanta |
Jefferson Hot Mix FY 27US0059 · Material Maintenance Project | $396,480 | $405,480 | LONGVIEW ASPHALT, INC. | +2.3% | 1 |
| Oct 22, 2026 | 6509-86-001MMC - A00224079 | Harrison Atlanta |
Marshall Hot Mix FY 27US0059 · Material Maintenance Project | $396,480 | $405,480 | LONGVIEW ASPHALT, INC. | +2.3% | 1 |
| Oct 22, 2026 | 6510-55-001MMC - A00224256 | Brown Brownwood |
GRADE 4 MODIFIED UNCOATED ROCK (DW)US0183 · Material Maintenance Project | $388,250 | $341,288 | VULCAN CONSTRUCTION MATERIALS, LLC | -12.1% | 2 |
| Oct 22, 2026 | 6509-82-001MMC - A00224075 | Morris Atlanta |
Hot Mix Daingerfield FY 27US0259 · Material Maintenance Project | $382,800 | $311,000 | C-RAE MATERIALS LLC | -18.8% | 2 |
| Oct 22, 2026 | 6509-85-001MMC - A00224078 | Cass Atlanta |
Linden Hot Mix FY 27US0059 · Material Maintenance Project | $406,700 | $311,000 | C-RAE MATERIALS LLC | -23.5% | 2 |
| Oct 22, 2026 | 6509-87-001MMC - A00224080 | Titus Atlanta |
Mt. Pleasant Hot Mix FY 27US0271 · Material Maintenance Project | $381,700 | $310,000 | C-RAE MATERIALS LLC | -18.8% | 2 |
| Oct 22, 2026 | 6509-88-001MMC - A00224081 | Bowie Atlanta |
New Boston Hot Mix FY 27US0082 · Material Maintenance Project | $399,500 | $306,000 | C-RAE MATERIALS LLC | -23.4% | 2 |
| Oct 22, 2026 | 6509-89-001MMC - A00224082 | Bowie Atlanta |
Texarkana Hot Mix FY 27US0059 · Material Maintenance Project | $399,000 | $306,000 | C-RAE MATERIALS LLC | -23.3% | 2 |
| Oct 22, 2026 | 6509-70-001RMC - A00224062 | Harrison Atlanta |
Debris Removal (South) FY 2027IH0020 · Routine Maintenance Project | $242,535 | $297,000 | HOLMES AND HOLMES CONTRACTING | +22.5% | 3 |
| Oct 22, 2026 | 6509-69-001RMC - A00224061 | Bowie Atlanta |
Debris Removal (North) FY 2027IH0030 · Routine Maintenance Project | $223,850 | $204,500 | HOLMES AND HOLMES CONTRACTING | -8.6% | 3 |
| Oct 22, 2026 | 6510-63-001MMC - A00224267 | Brown Brownwood |
FLEXIBLE BASE DISTRICT WIDE (MAT ONLY)US0183 · Material Maintenance Project | $112,800 | $81,399 | SOUTHERN SOURCING SOLUTIONS, LLC | -27.8% | 3 |
| Oct 22, 2026 | 6504-33-001SUP - A00222698 | Waller Houston |
SUP 6504-33-001 Waller LandscapeFM1488 · State Use Project | $19,825 | — | 0 | ||
| Oct 22, 2026 | 6506-97-001SUP - A00223459 | La Salle Laredo |
Metal Beam Guard Fence Repair - Lower CoIH0035 · State Use Project - Sealed | $1,802,118 | — | 0 | ||
| Oct 21, 2026 | 6506-35-001RMC - A00223240 | Angelina Lufkin |
2026-Spot Paint & Bead StripingUS0059 · Routine Maintenance Project - Sealed | $702,450 | $645,000 | STRIPING TECHNOLOGY, L.P. | -8.2% | 1 |
| Oct 21, 2026 | 6506-54-001RMC - A00223379 | Tarrant Fort Worth |
Long Line Striping - S. TarrantIH0030 · Routine Maintenance Project - Sealed | $640,890 | $439,494 | TRP INFRASTRUCTURE SERVICES, LLC | -31.4% | 2 |
| Oct 21, 2026 | 6510-35-001RMC - A00224200 | Angelina Lufkin |
2026-Raised Pavement MarkersUS0059 · Routine Maintenance Project - Sealed | $348,125 | $338,454 | ANTHONY SERVICES | -2.8% | 2 |
| Oct 21, 2026 | 6510-25-001SUP - A00224147 | Williamson Austin |
Georgetown Maintenance Litter FY27SH0195 · State Use Project | $595,284 | — | 0 | ||
| Oct 20, 2026 | 6510-89-001RMC - A00224379 | Midland Odessa |
6510-89-001 Street SweepingIH0020 · Routine Maintenance Project | $756,650 | $719,661 | SWEEPING CORPORATION OF AMERICA, LLC | -4.9% | 2 |
| Oct 20, 2026 | 6509-98-001MMC - A00224110 | Bexar San Antonio |
Districtwide Flexible BaseIH0010 · Material Maintenance Project | $115,983 | $136,073 | DIGG COMMERCIAL, LLC | +17.3% | 4 |
| Oct 20, 2026 | 6511-04-001SUP - A00224401 | Delta Paris |
LANDSCAPE - DELTA FY 27SH0024 · State Use Project | $6,400 | — | 0 | ||
| Oct 20, 2026 | 6511-11-001SUP - A00224417 | Red River Paris |
Picnic Area Maint - Red River 27US0082 · State Use Project | $33,408 | — | 0 | ||
| Oct 20, 2026 | 6511-15-001SUP - A00224422 | Rains Paris |
Rains - Janitorial 27US0069 · State Use Project | $21,553 | — | 0 | ||
| Oct 19, 2026 | 6508-91-001SUP - A00223944 | Harris Houston |
SUP 6508-91-001 WH LandscapeUS0290 · State Use Project | $13,800 | — | 0 | ||
| Oct 19, 2026 | 6512-16-001SUP - A00224642 | Nueces Corpus Christi |
6512-16-001 District GroundsSH0286 · State Use Project | $132,662 | — | 0 | ||
| Oct 19, 2026 | 6512-33-001SUP - A00224837 | Tyler Beaumont |
WOODVILLE PICNIC MAINT. FY27US0287 · State Use Project | $109,422 | — | 0 | ||
| Oct 15, 2026 | 6507-51-001RMC - A00223573 | Grayson Paris |
Debris Removal - Grayson Co FY27US0075 · Routine Maintenance Project - Sealed | $631,000 | $553,846 | SWEEPING CORPORATION OF AMERICA, LLC | -12.2% | 7 |
| Oct 15, 2026 | 6506-36-001RMC - A00223243 | McLennan Waco |
FY 2027 Culvert Cleaning - DistrictwideFM3047 · Routine Maintenance Project | $561,816 | $472,690 | KriMatt Services LLC | -15.9% | 2 |
| Oct 15, 2026 | 6510-64-001MMC - A00224270 | Hunt Paris |
Rock-Rip Rap - Paris District 27IH0030 · Material Maintenance Project - Sealed | $455,500 | $402,428 | RK HALL, LLC | -11.7% | 3 |
| Oct 15, 2026 | 6510-65-001MMC - A00224272 | Hunt Paris |
Asphalt Concrete Patch - Hunt/ DW FY27IH0030 · Material Maintenance Project - Sealed | $311,460 | $293,106 | HALL BROTHERS, INC. | -5.9% | 2 |
| Oct 15, 2026 | 6503-97-001RMC - A00222534 | McLennan Waco |
Large Green Signs FY27SH0006 · Routine Maintenance Project | $343,344 | $277,100 | RHINO EQUITY, LLC | -19.3% | 7 |
| Oct 15, 2026 | 6508-04-001RMC - A00223685 | Hopkins Paris |
Bridge Maintenance - Hopkins Co. FY27IH0030 · Routine Maintenance Project - Sealed | $381,350 | $252,821 | 12TWELVE ROAD AND BRIDGE LLC | -33.7% | 11 |
| Oct 15, 2026 | 6510-62-001MMC - A00224266 | Lamar Paris |
Sheet Pilings - Paris HQUS0271 · Material Maintenance Project - Sealed | $100,100 | $91,000 | TOUCHSTONE RESOURCES, LLC | -9.1% | 3 |
| Oct 14, 2026 | 6507-39-001RMC - A00223543 | El Paso El Paso |
EAO - Miscellaneous ConcreteIH0010 · Routine Maintenance Project | $809,850 | $845,627 | SYNERGY PROJECT CONTRACTORS, INC. | +4.4% | 6 |
| Oct 14, 2026 | 6502-60-001RMC - A00221875 | Denton Dallas |
On Call Traffic Control FY 27 Denton COIH0035E · Routine Maintenance Project - Sealed | $827,358 | $757,316 | ROAD SOLUTIONS L.L.C. | -8.5% | 3 |
| Oct 14, 2026 | 6507-02-001MMC - A00223482 | Hemphill Amarillo |
FY 27 Pampa Area HMAC Pickup & DeliveryUS0083 · Material Maintenance Project | $614,500 | $700,000 | BIG CREEK SAND & GRAVEL, INC. | +13.9% | 1 |
| Oct 14, 2026 | 6493-19-001RMC - A00218279 | Dallas Dallas |
Flexible Pavement Str Repair 771 26-27SH0183 · Routine Maintenance Project - Sealed | $688,540 | $622,508 | TEXAS MATERIALS GROUP, INC. | -9.6% | 7 |
| Oct 14, 2026 | 6502-76-001RMC - A00221977 | Ellis Dallas |
Reflectorized Pavement Markings 09 10/26IH0035E · Routine Maintenance Project - Sealed | $370,456 | $453,554 | STRIPE-A-ZONE, LLC | +22.4% | 2 |
| Oct 14, 2026 | 6502-95-001MMC - A00222098 | Ellis Dallas |
Winter Weather Material 09 0926FM0876 · Material Maintenance Project | $411,000 | $446,751 | NSG LOGISTICS, LLC | +8.7% | 1 |
| Oct 14, 2026 | 6508-81-001MMC - A00223899 | Palo Pinto Fort Worth |
FY '27 Palo Pinto MMC Hydraulic CementIH0020 · Material Maintenance Project | $465,000 | $390,000 | TOUCHSTONE RESOURCES, LLC | -16.1% | 5 |
| Oct 14, 2026 | 6495-90-001BPM - A00218976 | Kaufman Dallas |
FY 27 BPM KaufmanSH0034 · Bridge Preventative Maintenance - Sealed | $244,120 | $341,942 | GIBSON & ASSOCIATES, INC. | +40.1% | 3 |
| Oct 14, 2026 | 6504-79-001RMC - A00222907 | Kaufman Dallas |
Concrete Structure Repair KRAO FY'27IH0020 · Routine Maintenance Project - Sealed | $270,825 | $203,140 | JACKSON EXCAVATION, LLC | -25.0% | 4 |
| Oct 14, 2026 | 6503-01-001MMC - A00222133 | Ellis Dallas |
Limestone Rock Asphalt 09 1026FM0876 · Material Maintenance Project | $182,400 | $197,064 | VULCAN CONSTRUCTION MATERIALS, LLC | +8.0% | 2 |
Source: TxDOT Bid Tabulations (data.texas.gov), which covers state and local lettings from the previous 24 months. Bid Potato keeps every month it has loaded, so history grows past that window. Totals are as read at the letting; on packaged proposals the low bid can be the whole package total. Confirm against TxDOT's official tabulations.