122Let jobs
$819,498,291Total low bids
$720,392,659Total estimates
+13.8%Low bids vs estimates
Nov 2022 results
Bid tabs (Excel) ExcelCSV| Let date | CCSJ | County / District | Project | Estimate | Low bid | Low bidder | % vs est. | Bidders |
|---|---|---|---|---|---|---|---|---|
| Nov 29, 2022 | 6420-65-001MMC - 642065001 | Runnels San Angelo |
ASPHALTIC PATCHING MATERIALFM 2887 · | $120,107 | $161,500 | TOUCHSTONE RESOURCES, LLC | +34.5% | 1 |
| Nov 29, 2022 | 6409-55-001BPM - 640955001 | Jasper Beaumont |
BRIDGE PREVENTATIVE MAINTENANCEUS 190 · | $108,980 | $147,768 | TALBRAN ENTERPRISES LLC | +35.6% | 5 |
| Nov 22, 2022 | 6420-59-001MMC - 642059001 | Reagan San Angelo |
FLEXIBLE BASEUS 67 · | $140,266 | $141,859 | CSA MATERIALS, INC. | +1.1% | 3 |
| Nov 22, 2022 | 6420-61-001MMC - 642061001 | Runnels San Angelo |
FLEXIBLE BASEUS 67 · | $89,348 | $90,783 | CSA MATERIALS, INC. | +1.6% | 3 |
| Nov 22, 2022 | 6420-63-001MMC - 642063001 | Kimble San Angelo |
WINTER WEATHER MATERIALUS 83 · | $61,057 | $67,546 | ALLEN KELLER COMPANY | +10.6% | 3 |
| Nov 22, 2022 | 6420-69-001MMC - 642069001 | Crockett San Angelo |
AGGREGATESH 163 · | $57,811 | $65,568 | ALLEN KELLER COMPANY | +13.4% | 2 |
| Nov 22, 2022 | 6420-73-001MMC - 642073001 | Sterling San Angelo |
WINTER WEATHER MATERIALUS 87 · | $60,828 | $59,500 | SOUTHWEST ENVIROTX PARTNERS, LLC | -2.2% | 3 |
| Nov 22, 2022 | 6419-93-001MMC - 641993001 | Tom Green San Angelo |
HYDRAULIC CEMENTSH 208 · | $33,342 | $34,115 | TOUCHSTONE RESOURCES, LLC | +2.3% | 2 |
| Nov 17, 2022 | 6423-11-001MMC - 642311001 | Culberson El Paso |
FLEXIBLE BASEIH 10 · | $166,400 | $212,800 | TOUCHSTONE RESOURCES, LLC | +27.9% | 1 |
| Nov 17, 2022 | 6424-88-001RMC - 642488001 | Hopkins Paris |
TREE REMOVALIH 30 · | $262,250 | $208,800 | BRYDL CONTRACTING, LLC | -20.4% | 6 |
| Nov 16, 2022 | 6424-06-001RMC - 642406001 | Milam Bryan |
TREE REMOVALSH 36 · | $147,875 | $279,000 | GV LANDSCAPE AND CONSTRUCTION LLC | +88.7% | 2 |
| Nov 16, 2022 | 6411-77-001BPM - 641177001 | Jefferson Beaumont |
BRIDGE PREVENTATIVE MAINTENANCEUS 69 · | $263,861 | $277,605 | AMERICAN INFRASTRUCTURE MAINTENANCE MANAGEMENT LLC | +5.2% | 5 |
| Nov 16, 2022 | 6423-99-001RMC - 642399001 | Washington Bryan |
MOWING HIGHWAY RIGHT OF WAYUS 290 · | $223,205 | $239,907 | WELLMANN ENTERPRISES | +7.5% | 1 |
| Nov 16, 2022 | 6422-47-001MMC - 642247001 | Washington Bryan |
EMULSIONSH 36 · | $265,320 | $231,720 | ERGON ASPHALT & EMULSIONS, INC. | -12.7% | 3 |
| Nov 16, 2022 | 6418-29-001RMC - 641829001 | Trinity Lufkin |
REPAIR/UPGRADE & MAINTENANCE OF MBGFSH 19 · | $262,350 | $224,750 | GARRET SHIELDS INFRASTRUCTURE | -14.3% | 3 |
| Nov 16, 2022 | 6425-70-001MMC - 642570001 | Walker Bryan |
EMULSIONIH 45 · | $174,480 | $154,200 | MARTIN RESOURCE MANAGEMENT CORPORATION | -11.6% | 3 |
| Nov 16, 2022 | 6422-89-001MMC - 642289001 | Freestone Bryan |
AGGREGATEIH 45 · | $162,000 | $151,600 | ARCOSA LWS, LLC | -6.4% | 1 |
| Nov 15, 2022 | 6406-22-001RMC - 640622001 | Tarrant Fort Worth |
TREE TRIMMING AND BRUSH REMOVALIH 20 · | $313,165 | $364,950 | PATHFIELD INVESTMENTS LLC | +16.5% | 4 |
| Nov 15, 2022 | 6423-09-001MMC - 642309001 | Howard Abilene |
HOT MIXIH 20 · | $267,581 | $299,900 | RK HALL, LLC | +12.1% | 1 |
| Nov 15, 2022 | 6424-38-001MMC - 642438001 | Refugio Corpus Christi |
FLEXIBLE BASEFM 774 · | $292,500 | $286,000 | DIGG COMMERCIAL, LLC | -2.2% | 3 |
| Nov 15, 2022 | 6426-89-001MMC - 642689001 | Aransas Corpus Christi |
FLEXIBLE BASEFM 3036 · | $292,500 | $286,000 | DIGG COMMERCIAL, LLC | -2.2% | 3 |
| Nov 15, 2022 | 6399-75-001MMC - 639975001 | Karnes Corpus Christi |
HOT MIXUS 181 · | $295,800 | $285,600 | BRAUNTEX MATERIALS, INC. | -3.4% | 2 |
| Nov 15, 2022 | 6426-87-001BPM - 642687001 | Goliad Corpus Christi |
BRIDGE SCOUR REPAIRUS 59 · | $284,815 | $282,477 | MB WESTERN INDUSTRIAL CONTRACTING COMPANY | -0.8% | 8 |
| Nov 15, 2022 | 6424-04-001RMC - 642404001 | Brazos Bryan |
TREE REMOVALSH 6 · | $147,875 | $269,400 | GV LANDSCAPE AND CONSTRUCTION LLC | +82.2% | 2 |
| Nov 15, 2022 | 6422-67-001RMC - 642267001 | Dallas Dallas |
STORM SEWER AND DRAIN INLET CLEANINGUS 80 · | $265,250 | $268,980 | SHALOM SERVICES CORPORATION | +1.4% | 3 |
| Nov 15, 2022 | 6422-69-001RMC - 642269001 | Dallas Dallas |
STORM SEWER AND DRAIN INLET CLEANINGIH 30 · | $268,750 | $267,905 | SHALOM SERVICES CORPORATION | -0.3% | 3 |
| Nov 15, 2022 | 6424-20-001MMC - 642420001 | Kaufman Dallas |
AGGREGATEFM 2728 · | $261,000 | $265,000 | ARCOSA LWS, LLC | +1.5% | 1 |
| Nov 15, 2022 | 6406-24-001RMC - 640624001 | Tarrant Fort Worth |
CLEANING AND SEALING CRACKSIH 20 · | $196,736 | $239,921 | D & M CONTRACTORS, LLC | +22.0% | 3 |
| Nov 15, 2022 | 6424-34-001MMC - 642434001 | Bee Corpus Christi |
FLEXIBLE BASEUS 59 · | $292,500 | $235,625 | BRAUNTEX MATERIALS, INC. | -19.4% | 3 |
| Nov 15, 2022 | 6424-36-001MMC - 642436001 | Goliad Corpus Christi |
FLEXIBLE BASEUS 59 · | $292,500 | $235,625 | BRAUNTEX MATERIALS, INC. | -19.4% | 4 |
| Nov 15, 2022 | 6424-28-001MMC - 642428001 | Kaufman Dallas |
FLEXIBLE BASEFM 2728 · | $224,000 | $232,000 | FNH CONSTRUCTION, LLC | +3.6% | 4 |
| Nov 15, 2022 | 6422-77-001MMC - 642277001 | Walker Bryan |
ROCK/RIPRAPIH 45 · | $186,000 | $193,900 | TOUCHSTONE RESOURCES, LLC | +4.2% | 3 |
| Nov 15, 2022 | 6422-42-001MMC - 642242001 | Walker Bryan |
CUTBACKIH 45 · | $192,000 | $181,320 | MARTIN RESOURCE MANAGEMENT CORPORATION | -5.6% | 2 |
| Nov 15, 2022 | 6421-77-001MMC - 642177001 | Denton Dallas |
HOT MIXUS 380 · | $224,700 | $181,300 | EUROVIA ATLANTIC COAST LLC | -19.3% | 2 |
| Nov 15, 2022 | 6412-43-001BPM - 641243001 | Goliad Corpus Christi |
BRIDGE PREVENTATIVE MAINTENANCEUS 59 · | $161,440 | $148,260 | AMERICAN INFRASTRUCTURE MAINTENANCE MANAGEMENT LLC | -8.2% | 5 |
| Nov 15, 2022 | 6412-45-001BPM - 641245001 | Goliad Corpus Christi |
BRIDGE PREVENTATIVE MAINTENANCEUS 59 · | $169,045 | $138,880 | AMERICAN INFRASTRUCTURE MAINTENANCE MANAGEMENT LLC | -17.8% | 5 |
| Nov 15, 2022 | 6424-76-001MMC - 642476001 | Scurry Abilene |
WINTER WEATHER MATERIALUS 84 · | $132,915 | $134,009 | NSG LOGISTICS, LLC | +0.8% | 3 |
| Nov 15, 2022 | 6426-71-001MMC - 642671001 | Nueces Corpus Christi |
WINTER WEATHER MATERIALSH 44 · | $100,096 | $104,960 | TOUCHSTONE RESOURCES, LLC | +4.9% | 2 |
| Nov 15, 2022 | 6426-73-001MMC - 642673001 | Karnes Corpus Christi |
WINTER WEATHER MATERIALUS 181 · | $60,576 | $63,360 | SOUTHWEST ENVIROTX PARTNERS, LLC | +4.6% | 2 |
| Nov 9, 2022 | 6422-75-001RMC - 642275001 | San Augustine Lufkin |
TREE & BRUSH REMOVALSH 103 · | $264,275 | $218,700 | K & R CONTRACTORS | -17.2% | 5 |
| Nov 9, 2022 | 6423-01-001MMC - 642301001 | Brazos Bryan |
AGGREGATESH 6 · | $135,000 | $137,500 | TOUCHSTONE RESOURCES, LLC | +1.9% | 3 |
| Nov 9, 2022 | 6422-38-001MMC - 642238001 | Brazos Bryan |
CUTBACKSH 6 · | $144,000 | $135,120 | MARTIN RESOURCE MANAGEMENT CORPORATION | -6.2% | 3 |
| Nov 9, 2022 | 6422-73-001MMC - 642273001 | Walker Bryan |
ASPHALTIC PATCHING MATERIALIH 45 · | $50,000 | $55,445 | WALLER COUNTY ASPHALT INC. | +10.9% | 1 |
| Nov 8, 2022 | 6420-87-001RMC - 642087001 | Smith Tyler |
ILLUMINATION MAINTENANCESH 64 · | $258,935 | $336,850 | STRIPING TECHNOLOGY, L.P. | +30.1% | 2 |
| Nov 8, 2022 | 6424-08-001RMC - 642408001 | Robertson Bryan |
TREE REMOVALSH 6 · | $147,875 | $306,467 | ROAD SOLUTIONS L.L.C. | +107.2% | 1 |
| Nov 8, 2022 | 6425-72-001MMC - 642572001 | Freestone Bryan |
ROCK/RIPRAPIH 45 · | $186,000 | $174,800 | A. L. HELMCAMP, INC. | -6.0% | 3 |
| Nov 8, 2022 | 6422-51-001MMC - 642251001 | Freestone Bryan |
EMULSIONIH 45 · | $174,480 | $159,520 | MARTIN RESOURCE MANAGEMENT CORPORATION | -8.6% | 4 |
| Nov 8, 2022 | 6422-32-001MMC - 642232001 | Washington Bryan |
CUTBACKSH 36 · | $144,000 | $135,240 | MARTIN RESOURCE MANAGEMENT CORPORATION | -6.1% | 3 |
| Nov 8, 2022 | 6425-24-001MMC - 642524001 | Pecos Odessa |
EMULSIONIH 10 · | $128,700 | $121,380 | ERGON ASPHALT & EMULSIONS, INC. | -5.7% | 3 |
| Nov 8, 2022 | 6423-36-001RMC - 642336001 | Freestone Bryan |
CLEANING AND SWEEPING HIGHWAYSUS 84 · | $123,231 | $89,129 | TEXAS TMA RENTAL | -27.7% | 4 |
| Nov 3, 2022 | 0141-02-033C 141-2-33 | Sutton San Angelo |
ACP OVERLAYIH 10 · | $21,507,910 | $21,298,154 | DELHUR INDUSTRIES, INC. | -1.0% | 4 |
| Nov 3, 2022 | 0052-03-030F 2023(192) | Bailey Lubbock |
SEAL COATUS 84 · | $19,691,968 | $19,522,385 | LIPHAM ASPHALT AND PAVING COMPANY, LLC | -0.9% | 2 |
| Nov 3, 2022 | 0025-05-024F 2023(225) | Gonzales Yoakum |
SEAL COATUA 90 · | $21,059,259 | $18,739,125 | BRANNAN PAVING CO., LTD. | -11.0% | 4 |
| Nov 3, 2022 | 2707-01-011F 2023(209) | Houston Lufkin |
HIGHWAY IMPROVEMENTFM 2781 · | $12,769,655 | $12,103,921 | A. L. HELMCAMP, INC. | -5.2% | 4 |
| Nov 3, 2022 | 0249-03-055F 2023(183) | Archer Wichita Falls |
SEAL COAT, STRIPING & RPM'SUS 281 · | $9,172,582 | $10,600,584 | NORTHEASTERN PAVERS, LLC | +15.6% | 3 |
| Nov 3, 2022 | 1315-01-028F 2023(171) | Denton Dallas |
REHABILITATION OF EXISTING ROADFM 1385 · | $7,415,034 | $7,569,743 | STATELINE CONSTRUCTION, LLC | +2.1% | 7 |
| Nov 3, 2022 | 0581-01-156F 2023(169) | Dallas Dallas |
PLANING, CONCRETE FULL DEPTH REPAIR,OV & SIDEWALKSSL 12 · | $6,665,555 | $7,277,370 | RAGLE CONSTRUCTION, INC. | +9.2% | 4 |
| Nov 3, 2022 | 1912-01-022C 1912-1-22 | Montgomery Houston |
SURFACING/ROADWAY RESTORATIONFM 2090 · | $7,973,999 | $7,041,940 | TEXAS MATERIALS GROUP, INC. | -11.7% | 2 |
| Nov 3, 2022 | 0233-05-038BR 2023(245) | Culberson El Paso |
CONSTRUCT BRIDGESH 54 · | $3,940,229 | $6,330,874 | DAN WILLIAMS COMPANY | +60.7% | 1 |
| Nov 3, 2022 | 0110-03-085F 2023(184) | Montgomery Houston |
SURFACING/ROADWAY RESTORATIONSH 75 · | $4,005,728 | $3,455,794 | VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC | -13.7% | 3 |
| Nov 3, 2022 | 0909-00-062C 909-00-62 | McLennan Waco |
BRIDGE MAINTENANCEVA · | $3,831,954 | $3,216,349 | SCR CIVIL CONSTRUCTION, LLC | -16.1% | 2 |
| Nov 3, 2022 | 6420-99-001RMC - 642099001 | Bosque Waco |
TRAFFIC CONTROL SERVICESFM 56 · | $2,990,050 | $2,857,805 | STATEWIDE SAFETY SYSTEMS | -4.4% | 3 |
| Nov 3, 2022 | 0169-02-068STP 2023(181)HES | Potter Amarillo |
INTERSECTION IMPROVEMENTS WITH RIGHT AND/OR LEFT TUS 60 · | $2,221,786 | $2,207,755 | L A FULLER & SONS CONSTRUCTION, LTD. | -0.6% | 3 |
| Nov 3, 2022 | 0135-02-069STP 2023(168)HES | Collin Dallas |
INSTALL ILLUMINATIONUS 380 · | $2,304,266 | $2,000,000 | HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, LLC | -13.2% | 3 |
| Nov 3, 2022 | 6422-44-001RMC - 642244001 | Wood Tyler |
TRAFFIC CONTROL SERVICESUS 80 · | $2,242,950 | $1,979,845 | SOUTH TEXAS ILLUMINATION, LLC | -11.7% | 4 |
| Nov 3, 2022 | 0862-01-057BR 2023(199) | Hidalgo Pharr |
BRIDGE REPLACEMENTFM 492 · | $2,066,857 | $1,917,664 | TEXAS CORDIA CONSTRUCTION, LLC | -7.2% | 5 |
| Nov 3, 2022 | 6404-72-001MMC - 640472001 | Bastrop Austin |
SEAL COAT AGGREGATE (MATERIAL ONLY)FM 535 · | $1,642,258 | $1,759,340 | TOUCHSTONE RESOURCES, LLC | +7.1% | 2 |
| Nov 3, 2022 | 0901-19-207F 2023(141) | Grayson Paris |
PREVENTIVE MAINTENANCEVA · | $1,498,975 | $1,694,730 | GHB EQUIPMENT COMPANY, L.L.C. | +13.1% | 2 |
| Nov 3, 2022 | 0052-02-038F 2023(189) | Bailey Lubbock |
SEAL COATUS 70 · | $1,088,697 | $1,422,922 | COX PAVING OF TEXAS, INC. | +30.7% | 2 |
| Nov 3, 2022 | 0913-28-082BR 2021(266) | Fayette Yoakum |
BRIDGE REPLACEMENTCR · | $1,244,567 | $1,338,297 | HODGES AND SON CONSTRUCTION COMPANY, INC. | +7.5% | 8 |
| Nov 3, 2022 | 0065-01-062F 2023(186) | Jasper Beaumont |
SURFACING/ROADWAY RESTORATIONUS 96 · | $1,948,567 | $1,199,254 | INTERSTATE IMPROVEMENT, INC. | -38.5% | 3 |
| Nov 3, 2022 | 6413-69-001RMC - 641369001 | Hidalgo Pharr |
INSTALLATION OF TRAFFIC SIGNALSIH 69C · | $1,320,629 | $1,120,664 | TRAF-TEX, INC. | -15.1% | 3 |
| Nov 3, 2022 | 0902-00-337F 2023(240) | Tarrant Fort Worth |
REHABILITATE BRIDGEVA · | $1,140,179 | $996,995 | 3LW CIVIL LLC | -12.6% | 6 |
| Nov 3, 2022 | 6420-81-001RMC - 642081001 | Smith Tyler |
TRAFFIC SIGNAL MAINTENANCEUS 69 · | $608,050 | $832,600 | TEXAS TRAFFIC CONTROL SYSTEMS, INC. | +36.9% | 2 |
| Nov 3, 2022 | 6424-10-001MMC - 642410001 | Taylor Abilene |
HOT-MIX COLD-LAIDIH 20 · | $778,050 | $802,100 | ZACK BURKETT CO. | +3.1% | 2 |
| Nov 3, 2022 | 6424-16-001MMC - 642416001 | Taylor Abilene |
EMULSIONIH 20 · | $782,340 | $769,260 | WRIGHT ASPHALT PRODUCTS COMPANY LLC | -1.7% | 3 |
| Nov 3, 2022 | 6362-25-001RMC - 636225001 | Eastland Brownwood |
MILLING/ HYDROBLASTING (CALL-OUT)SH 206 · | $847,496 | $726,536 | TRP CONSTRUCTION GROUP, LLC | -14.3% | 4 |
| Nov 3, 2022 | 6414-25-001RMC - 641425001 | Wise Fort Worth |
TREE REMOVALUS 380 · | $622,154 | $698,790 | SHALOM SERVICES CORPORATION | +12.3% | 5 |
| Nov 3, 2022 | 6424-00-001RMC - 642400001 | Brazos Bryan |
MOWING HIGHWAY RIGHT OF WAYSH 6 · | $377,555 | $528,699 | R&M INCORPORATED | +40.0% | 1 |
| Nov 3, 2022 | 6418-41-001RMC - 641841001 | Harris Houston |
TRAFFIC CONTROL SERVICESSL 8 · | $560,405 | $504,220 | REPUBLIC TRAFFIC SAFETY, INC. | -10.0% | 7 |
| Nov 3, 2022 | 6420-21-001RMC - 642021001 | Carson Amarillo |
CABLE MEDIAN BARRIER SYSTEM REPAIRIH 40 · | $339,820 | $355,464 | BK FIELD OPERATIONS LLC | +4.6% | 3 |
| Nov 3, 2022 | 6409-53-001RMC - 640953001 | Navarro Dallas |
REPAIR/REPLACE CONCRETE BARRIERIH 45 · | $309,430 | $305,600 | IBCTX, LLC | -1.2% | 7 |
| Nov 3, 2022 | 6424-92-001RMC - 642492001 | Polk Lufkin |
DEBRIS REMOVALUS 59 · | $347,600 | $220,008 | AMERICAN INFRASTRUCTURE MAINTENANCE MANAGEMENT LLC | -36.7% | 2 |
| Nov 2, 2022 | 0009-12-219F 2023(166) | Rockwall Dallas |
GRADING,ACP,STRS,SIGNING,PAVEMENTIH 30 · | $413,700,705 | $510,166,222 | AUSTIN BRIDGE & ROAD SERVICES, LP | +23.3% | 3 |
| Nov 2, 2022 | 0030-06-066F 2023(179) | Hemphill Amarillo |
SEAL COATUS 60 · | $19,917,148 | $21,819,571 | MISSOURI PETROLEUM PRODUCTS COMPANY LLC | +9.6% | 1 |
| Nov 2, 2022 | 2906-01-006C 2906-1-6 | Midland Odessa |
ROADWAY REHABILITATIONRM 1492 · | $16,647,090 | $16,251,844 | JONES BROS. DIRT & PAVING CONTRACTORS, INC. | -2.4% | 2 |
| Nov 2, 2022 | 0064-01-069F 2023(196) | Shelby Lufkin |
RESURFACE ROADWAYSH 87 · | $13,550,044 | $15,659,342 | CLARK CONSTRUCTION OF TEXAS, INC. | +15.6% | 2 |
| Nov 2, 2022 | 0011-09-075F 2023(156) | Stephens Brownwood |
PREVENTIVE MAINTENANCEUS 180 · | $14,695,410 | $14,954,533 | BRANNAN PAVING CO., LTD. | +1.8% | 4 |
| Nov 2, 2022 | 0114-11-086C 114-11-86 | Waller Houston |
CONSTRUCT FRONTAGE ROADSUS 290 · | $10,755,429 | $10,942,905 | ISI CONTRACTING, INC. | +1.7% | 8 |
| Nov 2, 2022 | 0053-18-048CR 2023(042) | Lubbock Lubbock |
INFRASTRUCTURE IMPROVEMENTSUS 84 · | $8,534,908 | $9,876,827 | GILVIN-TERRILL, LTD. | +15.7% | 2 |
| Nov 2, 2022 | 0141-08-050F 2023(137) | Kimble San Angelo |
PREVENTIVE MAINTENANCEIH 10 · | $10,955,919 | $9,718,660 | ALLEN KELLER COMPANY | -11.3% | 4 |
| Nov 2, 2022 | 0065-05-156BR 2023(188) | Hardin Beaumont |
BRIDGE MAINTENANCEUS 96 · | $7,925,258 | $8,587,147 | RAGLE CONSTRUCTION, INC. | +8.4% | 3 |
| Nov 2, 2022 | 0045-18-046STP 2023(138)HES | Grayson Paris |
HAZARD ELIMINATION & SAFETYUS 82 · | $6,383,895 | $5,981,039 | STATELINE CONSTRUCTION, LLC | -6.3% | 7 |
| Nov 2, 2022 | 0528-01-121C 528-1-121 | Hidalgo Pharr |
PREVENTIVE MAINTENANCESH 107 · | $6,258,578 | $5,739,476 | IOC COMPANY LLC | -8.3% | 3 |
| Nov 2, 2022 | 0030-07-022F 2023(180) | Hemphill Amarillo |
SURFACING/ROADWAY RESTORATIONUS 83 · | $5,574,894 | $5,382,630 | DUININCK, INC. | -3.4% | 4 |
| Nov 2, 2022 | 0255-01-090C 255-1-90 | Jim Wells Corpus Christi |
SURFACING/ROADWAY RESTORATIONUS 281 · | $5,229,054 | $4,570,095 | HUNTER INDUSTRIES, LTD. | -12.6% | 4 |
| Nov 2, 2022 | 0471-02-079F 2023(175) | Hays Austin |
PREVENTIVE MAINTENANCESH 21 · | $3,022,331 | $2,808,196 | LONE STAR PAVING COMPANY | -7.1% | 4 |
| Nov 2, 2022 | 0288-01-040BR 2023(159) | Comanche Brownwood |
BRIDGE MAINTENANCESH 16 · | $2,493,957 | $2,724,265 | STRUCTURAL INTEGRITY GROUP LLC | +9.2% | 7 |
| Nov 2, 2022 | 6423-19-001MMC - 642319001 | Taylor Abilene |
LIMESTONE ROCK ASPHALTIH 20 · | $1,725,000 | $1,838,980 | VULCAN CONSTRUCTION MATERIALS, LLC | +6.6% | 2 |
| Nov 2, 2022 | 6392-03-001RMC - 639203001 | Taylor Abilene |
ILLUMINATION MAINTENANCEIH 20 · | $1,104,405 | $1,743,650 | WILLIS ELECTRIC CO., LP | +57.9% | 3 |
1–100 of 122Next ›
Source: TxDOT Bid Tabulations (data.texas.gov), which covers state and local lettings from the previous 24 months. Bid Potato keeps every month it has loaded, so history grows past that window. Totals are as read at the letting; on packaged proposals the low bid can be the whole package total. Confirm against TxDOT's official tabulations.