161Let jobs
$1,073,051,427Total low bids
$1,089,744,193Total estimates
-1.5%Low bids vs estimates
Jul 2018 results
Bid tabs (Excel) ExcelCSV| Let date | CCSJ | County / District | Project | Estimate | Low bid | Low bidder | % vs est. | Bidders |
|---|---|---|---|---|---|---|---|---|
| Jul 10, 2018 | 0072-07-070NH 1802(387) | Bexar San Antonio |
GRAD, BASE, STRUCTURE, PAVEMENT MARKINGIH 10 · | $36,185,518 | $37,255,989 | J3 COMPANY, LLC | +3.0% | 4 |
| Jul 10, 2018 | 0200-11-095NH 1802(412) | Jefferson Beaumont |
WIDEN FREEWAY FROM 4 TO 6 LANESUS 69 · | $25,665,191 | $31,528,539 | OLDCASTLE MATERIALS TEXAS, INC. | +22.8% | 3 |
| Jul 10, 2018 | 0912-72-075HP 1402(016) | Harris Houston |
RECONSTRUCT CLINTON DRIVECS · | $21,825,975 | $24,159,581 | HARPER BROTHERS CONSTRUCTION LLC | +10.7% | 4 |
| Jul 10, 2018 | 0028-09-116IM 0108(181) | Orange Beaumont |
INSTALL HIGH MAST LIGHTINGIH 10 · | $15,154,924 | $15,083,452 | THIRD COAST SERVICES LLC | -0.5% | 7 |
| Jul 10, 2018 | 0191-03-081STP 2013(215) | Smith Tyler |
GR,FLX BS,ACP,CULV EXT&RPLCMT,SIGNS,PV MKFM 2493 · | $14,297,208 | $14,458,790 | HIGHWAY 19 CONSTRUCTION LLC | +1.1% | 6 |
| Jul 10, 2018 | 0065-05-145C 65-5-145 | Hardin Beaumont |
MILL AND OVERLAY EXISTING ROADWAYUS 96 · | $7,704,753 | $6,772,232 | OLDCASTLE MATERIALS TEXAS, INC. | -12.1% | 3 |
| Jul 10, 2018 | 0393-02-027C 393-2-27 | Rusk Tyler |
PLNG,BS RPR,OCST,SUPERPV SURF,BR RL,MBGF,PV MKSH 149 · | $7,170,336 | $6,294,092 | MADDEN CONTRACTING COMPANY, LLC. | -12.2% | 5 |
| Jul 10, 2018 | 0025-02-216C 25-2-216 | Bexar San Antonio |
UPGRADE ILLUMINATIONIH 10 · | $6,315,723 | $6,167,909 | HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. | -2.3% | 3 |
| Jul 10, 2018 | 0050-03-100C 50-3-100 | Grimes Bryan |
OVERLAYSH 6 · | $6,519,921 | $5,798,126 | KNIFE RIVER CORPORATION - SOUTH | -11.1% | 3 |
| Jul 10, 2018 | 0018-01-097C 18-1-97 | La Salle Laredo |
PLANING, ACP, PAV MRKIH 35 · | $5,025,391 | $5,687,629 | ANDERSON COLUMBIA CO., INC. | +13.2% | 3 |
| Jul 10, 2018 | 1746-01-027STP 1802(377)HESG | Collin Dallas |
WDN, OV, BS REPFM 1827 · | $5,124,198 | $5,440,852 | A. L. HELMCAMP, INC. | +6.2% | 8 |
| Jul 10, 2018 | 0178-02-089C 178-2-89 | Brazoria Houston |
DIAMOND GRINDING & O/L,W/LP DETRSSH 35 · | $3,881,432 | $4,772,338 | DIAMOND SURFACE, INC. | +23.0% | 4 |
| Jul 10, 2018 | 0500-03-588NH 1802(410) | Harris Houston |
RECONSTRUCT FRONTAGE ROADSIH 45 · | $5,105,979 | $4,552,330 | ISI CONTRACTING, INC. | -10.8% | 5 |
| Jul 10, 2018 | 0691-01-035C 691-1-35 | Karnes Corpus Christi |
WIDEN OR REPLACE STRUCTUREFM 81 · | $4,588,436 | $4,236,891 | LISKA CONSTRUCTION COMPANY, INC. | -7.7% | 10 |
| Jul 10, 2018 | 0077-06-099STP 1802(311) | Tom Green San Angelo |
ACP OVERLAYUS 67 · | $3,383,898 | $3,463,807 | REECE ALBERT, INC. | +2.4% | 3 |
| Jul 10, 2018 | 0383-04-061STP 1802(405) | Kleberg Corpus Christi |
MISCELLANEOUS CONSTRUCTIONSH 141 · | $3,390,740 | $3,087,011 | TI-ZACK CONCRETE, INC. | -9.0% | 5 |
| Jul 10, 2018 | 2590-01-020STP 2013(518) | Nacogdoches Lufkin |
WIDEN FROM 2 TO 4 LANESFM 2609 · | $2,711,569 | $2,896,894 | DREWERY CONSTRUCTION COMPANY, INCORPORATED | +6.8% | 4 |
| Jul 10, 2018 | 3005-02-006STP 2013(635) | Burnet Austin |
PROVIDE ADDITIONAL PAVED SURFACERM 690 · | $2,430,395 | $2,692,129 | AARON CONCRETE CONTRACTORS, L.P. | +10.8% | 6 |
| Jul 10, 2018 | 6330-97-001RMC - 633097001 | Lamar Paris |
ON CALL TRAFFIC CONTROL SERVICESUS 82 · | $3,240,274 | $2,626,187 | AREA WIDE PROTECTIVE, INC. | -19.0% | 4 |
| Jul 10, 2018 | 0184-04-050C 184-4-50 | Bell Waco |
MISC SPOT PAVEMENT REPAIRSSH 36 · | $2,831,808 | $2,282,822 | LONE STAR PAVING COMPANY | -19.4% | 5 |
| Jul 10, 2018 | 0912-00-531C 912-0-531 | Harris Houston |
INSTALL NEW TRAFFIC SIGNALSVA · | $1,999,880 | $1,999,535 | TRAF-TEX, INC. | 0.0% | 4 |
| Jul 10, 2018 | 2417-02-016STP 1802(382) | Johnson Fort Worth |
BS REPR, MILL, OV, PAV MK, MBGFFM 2331 · | $1,640,815 | $1,839,668 | PEACHTREE CONSTRUCTION, LTD. | +12.1% | 4 |
| Jul 10, 2018 | 0906-32-054STP 2017(228)HES | Midland Odessa |
IMPROVE TRAFFIC SIGNALS,ADD RT LANECS · | $1,298,056 | $1,801,684 | REECE ALBERT, INC. | +38.8% | 2 |
| Jul 10, 2018 | 0167-02-051C 167-2-51 | El Paso El Paso |
OVERLAYBU 54-A · | $2,295,063 | $1,723,480 | J. A. R. CONCRETE, INC. | -24.9% | 6 |
| Jul 10, 2018 | 6331-75-001RMC - 633175001 | Bexar San Antonio |
PAV MARKINGS & MRKRS CENTERLINE TEXTUREIH 35 · | $1,648,130 | $1,529,779 | INTERSTATE BARRICADES & MARKINGS, INC. | -7.2% | 4 |
| Jul 10, 2018 | 0089-18-003C 89-18-3 | Fort Bend Houston |
BASE REPAIR, PLANING, ACP OL, SIGNING & PVMT MARKSL 540 · | $1,724,083 | $1,518,767 | DURWOOD GREENE CONSTRUCTION CO. | -11.9% | 5 |
| Jul 10, 2018 | 6327-40-001RMC - 632740001 | Kaufman Dallas |
REFLECTORIZED PAVEMENT MARKINGS & MARKERSIH 20 · | $1,732,670 | $1,372,598 | TOTAL HIGHWAY MAINTENANCE, LLC | -20.8% | 5 |
| Jul 10, 2018 | 0921-02-305BR 2015(640) | Hidalgo Pharr |
REPLACE BRIDGE & RECONSTRUCT APPROACHESCS · | $1,368,414 | $1,276,034 | TEXAS CORDIA CONSTRUCTION, LLC | -6.8% | 5 |
| Jul 10, 2018 | 6329-52-001RMC - 632952001 | Wood Tyler |
TRAFFIC CONTROLUS 80 · | $1,363,950 | $1,263,544 | TOTAL HIGHWAY MAINTENANCE, LLC | -7.4% | 6 |
| Jul 10, 2018 | 0269-02-065STP 1802(397)HES | Lavaca Yoakum |
SAFETY TREAT FIXED OBJECTSUS 77 · | $1,015,370 | $1,147,696 | CONSTAR CONSTRUCTION | +13.0% | 4 |
| Jul 10, 2018 | 6330-40-001RMC - 633040001 | Collin Dallas |
SWEEPING AND DEBRIS REMOVALUS 75 · | $1,309,811 | $1,043,710 | PANNELL INDUSTRIES, INC. | -20.3% | 2 |
| Jul 10, 2018 | 0910-00-111C 910-00-111 | Smith Tyler |
THERMOPLASTIC PAVEMENT MARKINGSVA · | $1,037,301 | $958,013 | TOTAL HIGHWAY MAINTENANCE, LLC | -7.6% | 5 |
| Jul 10, 2018 | 6329-51-001RMC - 632951001 | Henderson Tyler |
TRAFFIC CONTROLSH 31 · | $1,003,200 | $940,201 | TOTAL HIGHWAY MAINTENANCE, LLC | -6.3% | 5 |
| Jul 10, 2018 | 0014-08-084C 14-8-84 | McLennan Waco |
MISC SPOT PAVEMENT REPAIRSIH 35 · | $854,053 | $810,416 | OLDCASTLE MATERIALS TEXAS, INC. | -5.1% | 3 |
| Jul 10, 2018 | 0072-10-006STP 1802(388)HES | Kendall San Antonio |
PROVIDE ADDITIONAL PAVED SURFACE WIDTHFM 289 · | $843,747 | $783,135 | Curran Contracting Company | -7.2% | 8 |
| Jul 10, 2018 | 1656-03-012STP 1702(303)HES | Falls Waco |
SAFETY TREAT FIXED OBJECTSFM 413 · | $881,744 | $777,557 | TALBRAN ENTERPRISES LLC | -11.8% | 6 |
| Jul 10, 2018 | 6330-41-001RMC - 633041001 | Fort Bend Houston |
CLEANNING AND SWEEPING OF HIGHWAYSUS 59 · | $1,013,546 | $775,542 | SWEEPING SERVICES OF TEXAS - OPERATING, L.P. | -23.5% | 4 |
| Jul 10, 2018 | 6318-57-001RMC - 631857001 | Parker Fort Worth |
CLEANING AND SEALING JOINTS AND CRACKSIH 20 · | $740,392 | $715,003 | TALBRAN ENTERPRISES LLC | -3.4% | 5 |
| Jul 10, 2018 | 6330-70-001RMC - 633070001 | Bell Waco |
MBGF, CABLE BARRIER & BRIDGE RAILUS 190 · | $670,851 | $604,623 | T&L CLEANING SERVICES LLC | -9.9% | 4 |
| Jul 10, 2018 | 0924-06-578NH 1802(477) | El Paso El Paso |
VEGETATION LANDSCAPEVA · | $503,337 | $585,214 | ZTEX CONSTRUCTION, INC. | +16.3% | 5 |
| Jul 10, 2018 | 2121-02-159BR 1802(327) | El Paso El Paso |
UPGRADE BRIDGE AND APPROACH RAILINGIH 10 · | $473,458 | $549,262 | DAN WILLIAMS COMPANY | +16.0% | 4 |
| Jul 10, 2018 | 0176-08-024STP 1802(328)HES | Angelina Lufkin |
IMPROVE GUARDRAIL AND SAFETY TREATFM 324 · | $563,358 | $533,772 | A R BROTHERS CONSTRUCTION SERVICES, INC. | -5.3% | 8 |
| Jul 10, 2018 | 0043-07-111STP 1802(315)HES | Wilbarger Wichita Falls |
IMPROVE GUARDRAIL TO DESIGN STANDARDSUS 287 · | $528,706 | $524,560 | IIPL USA LLC | -0.8% | 4 |
| Jul 10, 2018 | 6327-18-001RMC - 632718001 | Delta Paris |
CROSS DRAINAGE STRUCTURE REPAIRFM 3132 · | $488,458 | $519,837 | TALBRAN ENTERPRISES LLC | +6.4% | 9 |
| Jul 10, 2018 | 6329-67-001RMC - 632967001 | Cooke Wichita Falls |
CULVERT REPLACEMENTIH 35 · | $499,633 | $515,404 | TALBRAN ENTERPRISES LLC | +3.2% | 7 |
| Jul 10, 2018 | 6332-57-001RMC - 633257001 | Bowie Atlanta |
CALLOUT PREFABRICATED PAVEMENT MARKINGSUS 59 · | $516,315 | $503,830 | STRIPING TECHNOLOGY, L.P. | -2.4% | 4 |
| Jul 10, 2018 | 6333-57-001RMC - 633357001 | Lubbock Lubbock |
GUARDRAIL REPAIRIH 27 · | $543,750 | $470,045 | BARRICADES UNLIMITED | -13.6% | 3 |
| Jul 10, 2018 | 6331-03-001RMC - 633103001 | Bell Waco |
CLEANING AND SWEEPING HIGHWAYSUS 190 · | $470,077 | $439,828 | EXPERT MAINTENANCE & CONSTRUCTION SERVICES LLC | -6.4% | 4 |
| Jul 10, 2018 | 6317-17-001RMC - 631717001 | Ellis Dallas |
REMOVAL AND DISPOSAL OF DRIFTWOODFM 813 · | $337,000 | $420,100 | CROSS PLUS CONSTRUCTION, LLC | +24.7% | 1 |
| Jul 10, 2018 | 0033-06-114NH 1802(319) | Taylor Abilene |
ILLUMINATION UPGRADEUS 83 · | $442,501 | $412,647 | WILLIS ELECTRIC CO., LP | -6.7% | 4 |
| Jul 10, 2018 | 0913-20-090BR 2018(207) | Austin Yoakum |
REPLACE BRIDGE AND APPROACHESCR · | $416,354 | $410,493 | FUQUA CONSTRUCTION CO., INC. | -1.4% | 9 |
| Jul 10, 2018 | 0009-03-047STP 1802(305)HES | Dallas Dallas |
TRAFFIC SIGNAL IMPROVEMENTSSH 66 · | $461,954 | $399,626 | HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. | -13.5% | 7 |
| Jul 10, 2018 | 0081-02-069NH 1802(380) | Tarrant Fort Worth |
LANDSCAPINGUS 377 · | $428,449 | $393,162 | CENTRAL NORTH CONSTRUCTION, LLC | -8.2% | 5 |
| Jul 10, 2018 | 3417-03-024NH 1802(402) | Travis Austin |
ADDING 2ND LEFT TURN LANE TO 2 INTERESECTIONSFM 734 · | $436,660 | $388,447 | AARON CONCRETE CONTRACTORS, L.P. | -11.0% | 5 |
| Jul 10, 2018 | 0919-00-078STP 1802(324) | Cass Atlanta |
PAVEMENT MARKINGSVA · | $350,000 | $378,300 | STRIPING TECHNOLOGY, L.P. | +8.1% | 4 |
| Jul 10, 2018 | 6328-05-001RMC - 632805001 | Wichita Wichita Falls |
GUARDRAIL UPGRADEFM 367 · | $358,975 | $344,346 | IIPL USA LLC | -4.1% | 6 |
| Jul 10, 2018 | 6328-09-001RMC - 632809001 | Dallas Dallas |
MISCELLANEOUS CONCRETE REPAIRUS 80 · | $364,605 | $335,413 | DBI SERVICES, LLC | -8.0% | 5 |
| Jul 10, 2018 | 0920-00-121NH 1802(409) | Jefferson Beaumont |
INSTALL LANDSCAPINGVA · | $262,910 | $259,712 | TIGHT LINE CONSTRUCTION, LLC | -1.2% | 3 |
| Jul 10, 2018 | 0901-28-085BR 2016(211) | Hopkins Paris |
BRIDGE REPLACEMENTCR · | $269,981 | $253,519 | HIGHWAY 19 CONSTRUCTION LLC | -6.1% | 9 |
| Jul 10, 2018 | 1186-01-098STP 1802(400)HES | Travis Austin |
SAFETY LIGHTINGFM 969 · | $234,642 | $199,994 | THE LEVY COMPANY, INC. | -14.8% | 4 |
| Jul 10, 2018 | 0265-02-035CC 265-2-35 | Travis Austin |
EXTEND WESTBOUND LEFT TURN LANESH 71 · | $181,548 | $184,201 | AARON CONCRETE CONTRACTORS, L.P. | +1.5% | 4 |
101–161 of 161‹ Prev
Source: TxDOT Bid Tabulations (data.texas.gov), which covers state and local lettings from the previous 24 months. Bid Potato keeps every month it has loaded, so history grows past that window. Totals are as read at the letting; on packaged proposals the low bid can be the whole package total. Confirm against TxDOT's official tabulations.