| 1 | 134-6008 |
BACKFILL (TY A OR B) | 100 | CY |
$20.00 |
$17.50 |
$50.00 |
$35.00 |
|
| 2 | 351-6004 |
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") | 6,667 | SY |
$45.00 |
$40.65 |
$44.50 |
$53.00 |
|
| 3 | 351-6013 |
FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") | 26,668 | SY |
$25.00 |
$21.55 |
$23.00 |
$26.35 |
|
| 4 | 500-6033 |
MOBILIZATION (CALLOUT) | 3 | EA |
$28,246.40 |
$250.00 |
$500.00 |
$410.00 |
|
| 5 | 662-6109 |
WK ZN PAV MRK SHT TERM (TAB)TY W | 2,500 | EA |
$1.00 |
$0.9000 |
$1.00 |
$1.00 |
|
| 6 | 662-6111 |
WK ZN PAV MRK SHT TERM (TAB)TY Y-2 | 2,500 | EA |
$1.00 |
$0.9000 |
$1.00 |
$1.00 |
|
| 7 | 666-6048 |
REFL PAV MRK TY I (W)24"(SLD)(100MIL) | 100 | LF |
$6.00 |
$18.00 |
$12.00 |
$19.00 |
|
| 8 | 666-6300 |
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL) | 6,250 | LF |
$1.00 |
$0.5000 |
$0.5000 |
$0.5300 |
|
| 9 | 666-6303 |
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL) | 25,000 | LF |
$1.00 |
$0.4800 |
$0.4500 |
$0.5100 |
|
| 10 | 666-6312 |
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL) | 6,250 | LF |
$1.00 |
$0.5000 |
$0.5000 |
$0.5300 |
|
| 11 | 666-6315 |
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL) | 25,000 | LF |
$1.00 |
$0.4900 |
$0.4500 |
$0.5200 |
|
| 12 | 672-6007 |
REFL PAV MRKR TY I-C | 200 | EA |
$10.00 |
$3.00 |
$6.00 |
$3.15 |
|
| 13 | 672-6009 |
REFL PAV MRKR TY II-A-A | 313 | EA |
$10.00 |
$6.50 |
$6.00 |
$6.85 |
|
| 14 | 6001-6001 |
PORTABLE CHANGEABLE MESSAGE SIGN | 80 | DAY |
$80.00 |
$0.0100 |
$25.00 |
$1.00 |
|
| 15 | 6185-6002 |
TMA (STATIONARY) | 40 | DAY |
$160.00 |
$0.0100 |
$35.00 |
$1.00 |
|
| 16 | 6185-6003 |
TMA (MOBILE OPERATION) | 100 | HR |
$45.00 |
$1.00 |
$25.00 |
$72.00 |
|