REPLACE BRIDGE AND APPROACHES
- Let date
- Thursday, March 3, 2022
- CCSJ
- 0919-22-034
- District
- Atlanta
- County
- Marion
- Highway
- CR
- Limits
- ON CR 3306 AT MILL CREEK
- Classification
- Construction
- Project number
- BR 2020(063)
- Working days
- 64
Bidders 9
| # | Contractor | Total bid | vs estimate | vs low |
| EE | Engineer's estimate | $373,737 | | |
| 1 |
THK CONSTRUCTION LLC Low bidder |
$324,589 |
-13.2% |
|
| 2 |
H. H. HOWARD & SONS, INC. |
$346,147 |
-7.4% |
+6.6% |
| 3 |
HIGHWAY 19 CONSTRUCTION LLC |
$365,579 |
-2.2% |
+12.6% |
| 4 |
EAST TEXAS BRIDGE, INC. |
$388,582 |
+4.0% |
+19.7% |
| 5 |
PIERCE R & B LLC |
$389,000 |
+4.1% |
+19.8% |
| 6 |
HODGES AND SON CONSTRUCTION COMPANY, INC. |
$419,667 |
+12.3% |
+29.3% |
| 7 |
LONGVIEW BRIDGE AND ROAD, LTD. |
$447,732 |
+19.8% |
+37.9% |
| 8 |
ENCINO LANDSCAPE, INC. |
$461,749 |
+23.5% |
+42.3% |
| 9 |
CDM HOLDINGS, LLC |
$470,738 |
+26.0% |
+45.0% |
Bid tab: unit prices 32 items
ExcelCSV
| Seq | Bid code | Description | Qty | Unit | Estimate |
#1 THK CONSTRUCTIO… | #2 H. H. HOWARD & … | #3 HIGHWAY 19 CONS… | #4 EAST TEXAS BRID… | #5 PIERCE R & B LLC | #6 HODGES AND SON … | #7 LONGVIEW BRIDGE… | #8 ENCINO LANDSCAP… |
| 1 | 100-6001 |
PREPARING ROW | 0.28 | AC |
$8,000.00 |
$25,000.00 |
$20,000.00 |
$5,000.00 |
$40,000.00 |
$18,000.00 |
$50,000.00 |
$43,000.00 |
$100,000.00 |
| 2 | 110-6001 |
EXCAVATION (ROADWAY) | 542 | CY |
$15.00 |
$18.00 |
$20.00 |
$25.00 |
$20.00 |
$18.00 |
$15.00 |
$35.00 |
$20.00 |
| 3 | 110-6002 |
EXCAVATION (CHANNEL) | 80 | CY |
$30.00 |
$18.00 |
$20.00 |
$25.00 |
$25.00 |
$25.00 |
$20.00 |
$55.00 |
$20.00 |
| 4 | 132-6005 |
EMBANKMENT (FINAL)(ORD COMP)(TY C) | 827 | CY |
$30.00 |
$17.00 |
$20.00 |
$30.00 |
$30.00 |
$22.00 |
$20.00 |
$40.00 |
$40.00 |
| 5 | 160-6003 |
FURNISHING AND PLACING TOPSOIL (4") | 5,200 | SY |
$2.50 |
$2.30 |
$2.00 |
$3.00 |
$3.00 |
$3.00 |
$5.00 |
$4.00 |
$1.00 |
| 6 | 164-6054 |
BOND FBR MTRX SEED (PERM)(RURAL)(SAND) | 2,600 | SY |
$1.00 |
$0.5700 |
$0.6000 |
$1.00 |
$1.00 |
$0.6200 |
$2.00 |
$0.7500 |
$0.1500 |
| 7 | 164-6055 |
BONDED FBR MTRX SEED (TEMP)(WARM) | 1,300 | SY |
$1.00 |
$0.5700 |
$0.6000 |
$1.00 |
$0.6500 |
$0.6500 |
$1.00 |
$0.7500 |
$0.1500 |
| 8 | 164-6056 |
BONDED FBR MTRX SEED (TEMP)(COOL) | 1,300 | SY |
$1.00 |
$0.5700 |
$0.6000 |
$1.00 |
$0.6500 |
$0.6500 |
$1.00 |
$0.7500 |
$0.1500 |
| 9 | 168-6001 |
VEGETATIVE WATERING | 83 | MG |
$7.00 |
$10.00 |
$20.00 |
$10.00 |
$10.00 |
$25.00 |
$1.00 |
$21.00 |
$1.00 |
| 10 | 169-6002 |
SOIL RETENTION BLANKETS (CL 1) (TY B) | 400 | SY |
$1.35 |
$1.58 |
$2.00 |
$5.00 |
$2.00 |
$2.00 |
$4.00 |
$2.00 |
$4.00 |
| 11 | 275-6001 |
CEMENT | 15 | TON |
$200.00 |
$300.00 |
$250.00 |
$250.00 |
$250.00 |
$275.00 |
$300.00 |
$275.00 |
$300.00 |
| 12 | 275-6019 |
CEMENT TREAT (SUBGRADE)(6") | 918 | SY |
$4.00 |
$21.00 |
$8.00 |
$25.00 |
$8.00 |
$12.50 |
$12.00 |
$8.00 |
$4.00 |
| 13 | 310-6009 |
PRIME COAT (MC-30) | 231 | GAL |
$4.50 |
$20.00 |
$10.00 |
$25.00 |
$12.00 |
$16.00 |
$15.00 |
$8.00 |
$10.00 |
| 14 | 420-6001 |
CL A CONC (SEAL) | 22 | CY |
$400.00 |
$500.00 |
$400.00 |
$350.00 |
$600.00 |
$450.00 |
$400.00 |
$415.00 |
$1,000.00 |
| 15 | 432-6033 |
RIPRAP (STONE PROTECTION)(18 IN) | 137.32 | CY |
$120.00 |
$173.00 |
$180.00 |
$180.00 |
$175.00 |
$180.00 |
$150.00 |
$200.00 |
$200.00 |
| 16 | 432-6039 |
BEDDING MATERIAL (6 IN) | 29 | CY |
$140.00 |
$200.00 |
$180.00 |
$180.00 |
$175.00 |
$180.00 |
$125.00 |
$210.00 |
$200.00 |
| 17 | 450-6019 |
RAIL (TY T631LS) | 125 | LF |
$60.00 |
$68.25 |
$70.00 |
$52.00 |
$75.00 |
$70.00 |
$65.00 |
$86.00 |
$100.00 |
| 18 | 462-6017 |
CONC BOX CULV (7 FT X 6 FT) | 78 | LF |
$730.00 |
$675.00 |
$790.00 |
$1,172.00 |
$850.00 |
$875.00 |
$1,000.00 |
$960.00 |
$700.00 |
| 19 | 466-6184 |
WINGWALL (PW - 1) (HW=9 FT) | 2 | EA |
$35,000.00 |
$18,000.00 |
$25,000.00 |
$10,000.00 |
$22,000.00 |
$32,000.00 |
$38,000.00 |
$23,500.00 |
$36,000.00 |
| 20 | 496-6009 |
REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 1 | EA |
$9,000.00 |
$4,000.00 |
$10,000.00 |
$10,000.00 |
$10,000.00 |
$10,000.00 |
$10,000.00 |
$25,200.00 |
$30,000.00 |
| 21 | 500-6001 |
MOBILIZATION | 1 | LS |
$37,000.00 |
$30,000.00 |
$30,000.00 |
$30,000.00 |
$37,000.00 |
$37,000.00 |
$38,000.00 |
$43,000.00 |
$40,000.00 |
| 22 | 502-6001 |
BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 | MO |
$7,000.00 |
$1,200.00 |
$1,500.00 |
$1,300.00 |
$4,000.00 |
$2,500.00 |
$5,000.00 |
$2,100.00 |
$5,000.00 |
| 23 | 506-6002 |
ROCK FILTER DAMS (INSTALL) (TY 2) | 200 | LF |
$25.00 |
$35.00 |
$35.00 |
$35.00 |
$36.00 |
$40.00 |
$5.00 |
$45.50 |
$50.00 |
| 24 | 506-6011 |
ROCK FILTER DAMS (REMOVE) | 200 | LF |
$13.00 |
$1.00 |
$15.00 |
$10.00 |
$11.00 |
$9.00 |
$5.00 |
$12.00 |
$10.00 |
| 25 | 506-6038 |
TEMP SEDMT CONT FENCE (INSTALL) | 1,500 | LF |
$3.00 |
$3.00 |
$3.50 |
$3.00 |
$3.50 |
$3.20 |
$1.00 |
$3.50 |
$5.00 |
| 26 | 506-6039 |
TEMP SEDMT CONT FENCE (REMOVE) | 1,500 | LF |
$1.10 |
$1.00 |
$1.00 |
$1.00 |
$1.00 |
$1.00 |
$1.00 |
$1.00 |
$1.00 |
| 27 | 540-6001 |
MTL W-BEAM GD FEN (TIM POST) | 50 | LF |
$21.50 |
$34.00 |
$35.00 |
$30.00 |
$35.00 |
$32.50 |
$30.00 |
$36.00 |
$30.00 |
| 28 | 540-6016 |
DOWNSTREAM ANCHOR TERMINAL SECTION | 2 | EA |
$1,250.00 |
$1,575.00 |
$1,600.00 |
$1,500.00 |
$1,700.00 |
$1,450.00 |
$1,500.00 |
$1,650.00 |
$1,500.00 |
| 29 | 544-6004 |
GDRAIL END TRT(INST)(WOOD POST)(TY I) | 2 | EA |
$2,500.00 |
$3,334.00 |
$3,200.00 |
$3,000.00 |
$3,500.00 |
$3,275.00 |
$3,000.00 |
$1,980.00 |
$2,600.00 |
| 30 | 658-6062 |
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) | 8 | EA |
$32.00 |
$47.25 |
$50.00 |
$45.00 |
$50.00 |
$50.00 |
$50.00 |
$66.00 |
$40.00 |
| 31 | 2014-6002 |
ASPHALT-STABILIZED FLEXIBLE BASE | 269 | TON |
$180.00 |
$164.00 |
$175.00 |
$150.00 |
$185.00 |
$175.00 |
$165.00 |
$215.00 |
$200.00 |
| 32 | 6185-6002 |
TMA (STATIONARY) | 3 | DAY |
$115.00 |
$600.00 |
$500.00 |
$250.00 |
$300.00 |
$149.80 |
$500.00 |
$365.00 |
$300.00 |
Showing the first 8 bidders. The Excel and CSV downloads include all 9.