$512.83Avg low bid / CY
$548.67Avg of all bids
$791.66Avg engineer's estimate
10Jobs · 467 CY
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2024 | 3 | 361 | $539.58 | $577.24 |
| 2022 | 1 | 22 | $500.00 | $515.56 |
| 2020 | 3 | 23 | $573.91 | $762.58 |
| 2019 | 1 | 10 | $450.00 | $444.00 |
| 2017 | 2 | 51 | $313.73 | $359.96 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Aug 1, 2024 | 0046-03-038 | BowieAtlanta | 308 CY | $550.00 | DRAKE COMPANIES LLC |
| Jun 5, 2024 | 0919-30-061 | TitusAtlanta | 37 CY | $470.00 | THK CONSTRUCTION LLC |
| Apr 5, 2024 | 1574-01-018 | MorrisAtlanta | 16 CY | $500.00 | A. K. GILLIS & SONS, LLC |
| Mar 3, 2022 | 0919-22-034 | MarionAtlanta | 22 CY | $500.00 | THK CONSTRUCTION LLC |
| May 8, 2020 | 0610-07-113 | BowieAtlanta | 11 CY | $400.00 | LONGVIEW BRIDGE AND ROAD, LTD. |
| Apr 9, 2020 | 6352-28-001 | CoryellWaco | 8 CY | $500.00 | CROSS PLUS CONSTRUCTION, LLC |
| Mar 4, 2020 | 0063-01-094 | HarrisonAtlanta | 4 CY | $1,200.00 | LONGVIEW BRIDGE AND ROAD, LTD. |
| Mar 5, 2019 | 0632-04-032 | HarrisonAtlanta | 10 CY | $450.00 | H. V. CAVER, INC. |
| Jun 7, 2017 | 0221-05-064 | TitusAtlanta | 50 CY | $300.00 | LONGVIEW BRIDGE AND ROAD, LTD. |
| Jan 4, 2017 | 0429-01-023 | WoodTyler | 1 CY | $1,000.00 | HIGHWAY 19 CONSTRUCTION LLC |