‹ Mar 2018 results
SAFETY TREAT FIXED OBJECTS
- Let date
- Tuesday, March 6, 2018
- CCSJ
- 0010-19-012
- District
- Atlanta
- County
- Bowie
- Highway
- FM 991
- Limits
- US 67 W to US 67 E
- Classification
- Construction
- Project number
- STP 2018(645)HES
- Working days
- 395
Bidders 11
| # | Contractor | Total bid | vs estimate | vs low |
| EE | Engineer's estimate | $1,965,619 | | |
| 1 |
CDM HOLDINGS, LLC Low bidder |
$1,463,551 |
-25.5% |
|
| 2 |
STATELINE CONSTRUCTION, LLC |
$1,555,278 |
-20.9% |
+6.3% |
| 3 |
EAST TEXAS BRIDGE, INC. |
$1,604,779 |
-18.4% |
+9.6% |
| 4 |
LONGVIEW BRIDGE AND ROAD, LTD. |
$1,646,279 |
-16.2% |
+12.5% |
| 5 |
H. V. CAVER, INC. |
$1,657,787 |
-15.7% |
+13.3% |
| 6 |
L.C. JORDAN & SON |
$1,708,445 |
-13.1% |
+16.7% |
| 7 |
PIERCE R & B LLC |
$1,864,882 |
-5.1% |
+27.4% |
| 8 |
HIGHWAY 19 CONSTRUCTION LLC |
$1,924,576 |
-2.1% |
+31.5% |
| 9 |
FNH CONSTRUCTION, LLC |
$2,602,549 |
+32.4% |
+77.8% |
| 10 |
HODGES AND SON CONSTRUCTION COMPANY, INC. |
$2,635,098 |
+34.1% |
+80.0% |
| 11 |
CHAMPION INFRASTRUCTURE, LLC |
$3,191,236 |
+62.4% |
+118.0% |
Bid tab: unit prices 22 items
ExcelCSV
| Seq | Bid code | Description | Qty | Unit | Estimate |
#1 CDM HOLDINGS, L… | #2 STATELINE CONST… | #3 EAST TEXAS BRID… | #4 LONGVIEW BRIDGE… | #5 H. V. CAVER, IN… | #6 L.C. JORDAN & S… | #7 PIERCE R & B LLC | #8 HIGHWAY 19 CONS… |
| 1 | 150-6001 |
BLADING | 430 | STA |
$325.00 |
$75.00 |
$245.00 |
$135.00 |
$200.00 |
$300.00 |
$150.00 |
$270.00 |
$450.00 |
| 2 | 162-6002 |
BLOCK SODDING | 2,994 | SY |
$5.00 |
$5.00 |
$5.00 |
$5.30 |
$5.25 |
$10.00 |
$6.00 |
$5.00 |
$5.00 |
| 3 | 164-6001 |
BROADCAST SEED (PERM) (RURAL) (SANDY) | 11,963 | SY |
$0.2500 |
$0.3500 |
$0.2500 |
$0.2500 |
$0.2200 |
$0.2000 |
$0.2500 |
$0.2200 |
$0.1900 |
| 4 | 168-6001 |
VEGETATIVE WATERING | 195 | MG |
$10.00 |
$35.00 |
$15.00 |
$11.00 |
$15.00 |
$30.00 |
$100.00 |
$25.00 |
$50.00 |
| 5 | 400-6007 |
CUT & RESTORE CONC PAVING | 37 | SY |
$250.00 |
$180.00 |
$75.00 |
$250.00 |
$150.00 |
$175.00 |
$210.00 |
$175.00 |
$125.00 |
| 6 | 400-6008 |
CUT & RESTORE ASPH PAVING | 300 | SY |
$75.00 |
$115.00 |
$55.00 |
$75.00 |
$100.00 |
$90.00 |
$100.00 |
$105.00 |
$75.00 |
| 7 | 400-6012 |
CUT AND RESTORE PAV (FLEX BASE) | 1,349 | SY |
$25.00 |
$50.00 |
$35.00 |
$25.00 |
$75.00 |
$30.00 |
$40.00 |
$60.00 |
$25.00 |
| 8 | 432-6001 |
RIPRAP (CONC)(4 IN) | 110 | CY |
$410.00 |
$325.00 |
$420.00 |
$450.00 |
$500.00 |
$500.00 |
$450.00 |
$450.00 |
$600.00 |
| 9 | 464-6003 |
RC PIPE (CL III)(18 IN) | 3,802 | LF |
$40.00 |
$42.00 |
$31.00 |
$40.00 |
$36.00 |
$34.30 |
$39.00 |
$40.00 |
$31.00 |
| 10 | 464-6004 |
RC PIPE (CL III)(21 IN) | 8 | LF |
$65.00 |
$50.00 |
$56.00 |
$55.00 |
$55.00 |
$49.00 |
$50.00 |
$60.00 |
$45.00 |
| 11 | 464-6005 |
RC PIPE (CL III)(24 IN) | 352 | LF |
$62.00 |
$50.00 |
$68.00 |
$55.00 |
$48.00 |
$49.50 |
$45.00 |
$60.00 |
$45.00 |
| 12 | 464-6007 |
RC PIPE (CL III)(30 IN) | 52 | LF |
$85.00 |
$67.50 |
$106.00 |
$75.00 |
$64.00 |
$80.00 |
$80.00 |
$105.00 |
$80.00 |
| 13 | 464-6008 |
RC PIPE (CL III)(36 IN) | 36 | LF |
$100.00 |
$100.00 |
$135.00 |
$100.00 |
$85.00 |
$100.00 |
$110.00 |
$175.00 |
$150.00 |
| 14 | 467-6363 |
SET (TY II) (18 IN) (RCP) (6: 1) (P) | 1,429 | EA |
$675.00 |
$505.00 |
$510.00 |
$550.00 |
$540.00 |
$585.00 |
$640.00 |
$550.00 |
$555.00 |
| 15 | 467-6374 |
SET (TY II) (21 IN) (RCP) (6: 1) (P) | 8 | EA |
$1,120.00 |
$875.00 |
$895.00 |
$850.00 |
$900.00 |
$800.00 |
$850.00 |
$2,175.00 |
$952.00 |
| 16 | 467-6395 |
SET (TY II) (24 IN) (RCP) (6: 1) (P) | 136 | EA |
$1,175.00 |
$835.00 |
$795.00 |
$850.00 |
$865.00 |
$800.00 |
$900.00 |
$1,100.00 |
$940.00 |
| 17 | 467-6423 |
SET (TY II) (30 IN) (RCP) (6: 1) (P) | 16 | EA |
$1,600.00 |
$1,550.00 |
$2,010.00 |
$3,000.00 |
$1,500.00 |
$1,500.00 |
$1,500.00 |
$3,000.00 |
$2,060.00 |
| 18 | 467-6454 |
SET (TY II) (36 IN) (RCP) (6: 1) (P) | 6 | EA |
$3,800.00 |
$3,300.00 |
$4,100.00 |
$4,500.00 |
$3,000.00 |
$2,625.00 |
$4,000.00 |
$4,750.00 |
$3,500.00 |
| 19 | 496-6007 |
REMOV STR (PIPE) | 292 | LF |
$12.00 |
$17.50 |
$12.00 |
$10.00 |
$24.00 |
$10.00 |
$10.00 |
$25.00 |
$25.00 |
| 20 | 496-6016 |
REMOV STR (PIPE) | 149 | EA |
$300.00 |
$350.00 |
$200.00 |
$300.00 |
$475.00 |
$160.00 |
$100.00 |
$300.00 |
$200.00 |
| 21 | 500-6001 |
MOBILIZATION | 1 | LS |
$178,000.00 |
$100,600.00 |
$154,000.00 |
$150,000.00 |
$120,000.00 |
$125,000.00 |
$180,000.00 |
$186,000.00 |
$330,000.00 |
| 22 | 502-6001 |
BARRICADES, SIGNS AND TRAFFIC HANDLING | 42 | MO |
$2,500.00 |
$750.00 |
$1,800.00 |
$1,200.00 |
$1,200.00 |
$1,500.00 |
$1.00 |
$2,500.00 |
$2,000.00 |
Showing the first 8 bidders. The Excel and CSV downloads include all 11.