Subcontracts on active jobs 32
| CCSJ | Prime contractor | Where | Work | Share | Value (est.) |
|---|---|---|---|---|---|
| 0315-06-047Let Nov 5, 2025 | LARRY YOUNG PAVING, INC. | WashingtonBryan | BRIDGE REPLACEMENT | 0.42% | $12,174 |
| 0382-03-038Let Oct 9, 2025 | BIG CREEK CONSTRUCTION, LTD. | LimestoneWaco | REHABILITATION OF EXISTING ROAD | 0.31% | $43,397 |
| 0048-06-037Let Oct 8, 2025 | KNIFE RIVER CORPORATION - SOUTH | HillWaco | REHABILITATION OF EXISTING ROAD | 0.21% | $7,120 |
| 0639-02-026Let Sep 4, 2025 | KNIFE RIVER CORPORATION - SOUTH | MadisonBryan | REHABILITATION OF EXISTING ROAD | 1.34% | $249,488 |
| 0408-02-048Let Aug 7, 2025 | BIG CREEK CONSTRUCTION, LTD. | AustinYoakum | REHABILITATION OF EXISTING ROAD | 0.51% | $65,013 |
| 0540-03-037Let Aug 7, 2025 | LARRY YOUNG PAVING, INC. | BrazosBryan | HAZARD ELIMINATION & SAFETY | 2.1% | $60,381 |
| 2134-01-031Let Jul 2, 2025 | KNIFE RIVER CORPORATION - SOUTH | RobertsonBryan | REHABILITATION OF EXISTING ROAD | 2.34% | $437,965 |
| 2399-01-085Let Jun 5, 2025 | LARRY YOUNG PAVING, INC. | BrazosBryan | HAZARD ELIMINATION & SAFETY | 1.94% | $36,681 |
| 0187-02-073Let May 2, 2025 | TEXAS MATERIALS GROUP, INC. | AustinYoakum | REHABILITATION OF EXISTING ROAD | 0.36% | $23,330 |
| 0909-38-095Let May 2, 2025 | A. L. HELMCAMP, INC. | FallsWaco | BRIDGE REPLACEMENT | 2.35% | $54,243 |
| 0049-09-102Let May 1, 2025 | LARRY YOUNG PAVING, INC. | BrazosBryan | HAZARD ELIMINATION & SAFETY | 0.22% | $9,834 |
| 0540-05-054Let Apr 4, 2025 | BRAZOS PAVING, INC. | BrazosBryan | REHABILITATION OF EXISTING ROAD | 0.86% | $55,149 |
| 0205-05-051Let Apr 3, 2025 | LARRY YOUNG PAVING, INC. | LeonBryan | HAZARD ELIMINATION & SAFETY | 2.14% | $66,178 |
| 0176-08-026Let Apr 3, 2025 | A. L. HELMCAMP, INC. | AngelinaLufkin | BRIDGE REPLACEMENT | 0.53% | $145,505 |
| 0212-04-049Let Mar 4, 2025 | BRAZOS PAVING, INC. | GrimesBryan | HAZARD ELIMINATION & SAFETY | 6.99% | $72,696 |
| 0204-09-045Let Nov 7, 2024 | LARRY YOUNG PAVING, INC. | RobertsonBryan | BRIDGE REPLACEMENT | 1.33% | $254,240 |
| 1564-01-036Let Oct 1, 2024 | KNIFE RIVER CORPORATION - SOUTH | WashingtonBryan | REHABILITATION OF EXISTING ROAD | 1.26% | $222,010 |
| 0116-04-111Let Jul 10, 2024 | LARRY YOUNG PAVING, INC. | BrazosBryan | HAZARD ELIMINATION & SAFETY | 0.6% | $42,466 |
| 0212-04-039Let Jun 6, 2024 | BIG CREEK CONSTRUCTION, LTD. | GrimesBryan | BRIDGE REPLACEMENT | 0.99% | $124,427 |
| 0162-01-100Let May 2, 2024 | BIG CREEK CONSTRUCTION, LTD. | MclennanWaco | INTERCHANGE (NEW OR RECONSTRUCTED) | 0.56% | $165,500 |
| 1191-05-009Let Aug 3, 2023 | BIG CREEK CONSTRUCTION, LTD. | RobertsonBryan | REHABILITATION OF EXISTING ROAD | 3.39% | $290,231 |
| 1129-01-028Let Aug 3, 2023 | TEXAS MATERIALS GROUP, INC. | BurlesonBryan | REHABILITATION OF EXISTING ROAD | 1.95% | $117,872 |
| 1316-01-081Let Jun 27, 2023 | LARRY YOUNG PAVING, INC. | BrazosBryan | HAZARD ELIMINATION & SAFETY | 1.26% | $54,405 |
| 0675-01-069Let Dec 1, 2022 | A. L. HELMCAMP, INC. | FreestoneBryan | CONVERT NON-FREEWAY TO FREEWAY | 0.74% | $286,446 |
| 0338-04-060Let Aug 4, 2022 | JAMES CONSTRUCTION GROUP, LLC | MontgomeryHouston | WIDEN NON-FREEWAY | 0.34% | $181,120 |
| 0049-09-089Let Aug 4, 2022 | CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. | BrazosBryan | HAZARD ELIMINATION & SAFETY | 0.93% | $115,916 |
| 2502-01-021Let Aug 5, 2021 | JAMES CONSTRUCTION GROUP, LLC | BellWaco | WIDEN NON-FREEWAY | 1.21% | $428,304 |
| 0523-09-009Let Aug 5, 2021 | JAMES CONSTRUCTION GROUP, LLC | MontgomeryHouston | WIDEN NON-FREEWAY | 1.66% | $816,413 |
| 1259-01-044Let Aug 4, 2021 | JAMES CONSTRUCTION GROUP, LLC | MontgomeryHouston | WIDEN NON-FREEWAY | 0.38% | $86,198 |
| 0648-03-049Let Jul 2, 2021 | BIG CREEK CONSTRUCTION, LTD. | BurlesonBryan | WIDEN NON-FREEWAY | 0.33% | $116,670 |
| 2399-01-074Let Sep 4, 2020 | KNIFE RIVER CORPORATION - SOUTH | BrazosBryan | WIDEN NON-FREEWAY | 0.41% | $221,483 |
| 1685-03-058Let Jul 8, 2020 | TEXAS MATERIALS GROUP, INC. | HarrisHouston | WIDEN NON-FREEWAY | 1.36% | $892,371 |