$79.77Avg low bid / TON
$83.67Avg of all bids
$76.07Avg engineer's estimate
22Jobs · 78,600 TON
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2024 | 5 | 20,500 | $94.30 | $98.74 |
| 2023 | 4 | 19,700 | $84.95 | $87.70 |
| 2022 | 5 | 20,000 | $69.69 | $69.69 |
| 2021 | 6 | 13,900 | $65.24 | $69.07 |
| 2020 | 2 | 4,500 | $80.50 | $80.50 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jul 9, 2024 | 6468-55-001 | RobertsonBryan | 500 TON | $81.00 | KNIFE RIVER CORPORATION - SOUTH |
| Jun 5, 2024 | 6466-07-001 | WashingtonBryan | 500 TON | $83.75 | KNIFE RIVER CORPORATION - SOUTH |
| Mar 6, 2024 | 6463-55-001 | LamarParis | 6,500 TON | $97.00 | RK HALL, LLC |
| Mar 6, 2024 | 6463-56-001 | DeltaParis | 6,500 TON | $100.00 | RK HALL, LLC |
| Mar 5, 2024 | 6463-54-001 | Red RiverParis | 6,500 TON | $87.75 | RK HALL, LLC |
| Dec 5, 2023 | 6442-24-001 | WalkerBryan | 200 TON | $80.00 | KNIFE RIVER CORPORATION - SOUTH |
| Mar 8, 2023 | 6431-70-001 | Red RiverParis | 6,500 TON | $85.00 | RK HALL, LLC |
| Mar 8, 2023 | 6431-68-001 | DeltaParis | 6,500 TON | $85.00 | RK HALL, LLC |
| Mar 7, 2023 | 6431-66-001 | LamarParis | 6,500 TON | $85.00 | RK HALL, LLC |
| Aug 10, 2022 | 6414-39-001 | BrazosBryan | 250 TON | $88.00 | KNIFE RIVER CORPORATION - SOUTH |
| Aug 10, 2022 | 6414-57-001 | WalkerBryan | 250 TON | $105.00 | BIG CREEK CONSTRUCTION, LTD. |
| Feb 4, 2022 | 6395-67-001 | DeltaParis | 6,500 TON | $70.00 | RK HALL, LLC |
| Feb 4, 2022 | 6395-68-001 | Red RiverParis | 6,500 TON | $70.00 | RK HALL, LLC |
| Feb 3, 2022 | 6395-66-001 | LamarParis | 6,500 TON | $67.00 | RK HALL, LLC |
| Nov 9, 2021 | 6389-20-001 | WalkerBryan | 400 TON | $71.00 | BIG CREEK CONSTRUCTION, LTD. |
| Oct 13, 2021 | 6389-12-001 | BrazosBryan | 500 TON | $59.00 | KNIFE RIVER CORPORATION - SOUTH |
| Aug 17, 2021 | 6386-53-001 | NavarroDallas | 1,000 TON | $85.00 | TEXAS MATERIALS GROUP, INC. |
| Apr 15, 2021 | 6376-48-001 | DeltaParis | 4,000 TON | $69.00 | RK HALL, LLC |
| Apr 15, 2021 | 6376-45-001 | Red RiverParis | 4,000 TON | $61.00 | RK HALL, LLC |
| Apr 15, 2021 | 6376-46-001 | LamarParis | 4,000 TON | $61.00 | RK HALL, LLC |
| Sep 10, 2020 | 6367-24-001 | NavarroDallas | 1,000 TON | $91.00 | TEXAS MATERIALS GROUP, INC. |
| Jun 5, 2020 | 6361-17-001 | SabineLufkin | 3,500 TON | $77.50 | EAST TEXAS ASPHALT CO., LTD. |