$16,532.30Avg low bid / EA
$17,142.69Avg of all bids
$14,818.93Avg engineer's estimate
14Jobs · 101 EA
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2023 | 1 | 1 | $32,000.00 | $27,556.78 |
| 2022 | 1 | 2 | $34,000.00 | $27,418.32 |
| 2021 | 1 | 1 | $31,411.80 | $17,001.31 |
| 2020 | 1 | 4 | $7,900.00 | $12,966.67 |
| 2019 | 2 | 24 | $16,400.00 | $16,763.12 |
| 2018 | 3 | 20 | $16,162.50 | $18,357.37 |
| 2017 | 5 | 49 | $16,120.41 | $16,525.93 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| May 4, 2023 | 0231-03-154 | BellWaco | 1 EA | $32,000.00 | SCR CIVIL CONSTRUCTION, LLC |
| Sep 8, 2022 | 0027-12-158 | Fort BendHouston | 2 EA | $34,000.00 | NBG CONSTRUCTORS, INC. |
| Feb 4, 2021 | 0113-07-075 | HaysAustin | 1 EA | $31,411.80 | SALINAS CONSTRUCTION TECHNOLOGIES, LTD. |
| Jul 9, 2020 | 0231-03-147 | BellWaco | 4 EA | $7,900.00 | J.D. ABRAMS, L.P. |
| Aug 7, 2019 | 0025-02-219 | BexarSan Antonio | 18 EA | $15,700.00 | JORDAN FOSTER CONSTRUCTION, LLC |
| May 8, 2019 | 0090-09-006 | OldhamAmarillo | 6 EA | $18,500.00 | GILVIN-TERRILL, LTD. |
| Aug 8, 2018 | 0101-03-088 | San PatricioCorpus Christi | 2 EA | $19,500.00 | HAAS-ANDERSON CONSTRUCTION, LTD. |
| Jun 5, 2018 | 0231-03-146 | BellWaco | 3 EA | $2,250.00 | CAPITAL EXCAVATION COMPANY |
| Apr 3, 2018 | 0090-01-032 | Deaf SmithAmarillo | 15 EA | $18,500.00 | GILVIN-TERRILL, LTD. |
| Oct 4, 2017 | 0101-04-115 | San PatricioCorpus Christi | 4 EA | $23,200.00 | BAY LTD. |
| Aug 9, 2017 | 0675-07-101 | WalkerBryan | 18 EA | $15,000.00 | JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY |
| Aug 9, 2017 | 0675-03-081 | LeonBryan | 5 EA | $18,000.00 | BIG CREEK CONSTRUCTION, LTD. |
| Jan 4, 2017 | 0675-07-096 | WalkerBryan | 21 EA | $15,100.00 | WEBBER, LLC |
| Jan 4, 2017 | 0118-01-019 | HoustonLufkin | 1 EA | $20,000.00 | L.C. JORDAN & SON |