$54.99Avg low bid / CY
$55.88Avg of all bids
$57.46Avg engineer's estimate
13Jobs · 203,739 CY
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2022 | 2 | 7,676 | $68.90 | $67.75 |
| 2021 | 3 | 76,897 | $56.01 | $53.42 |
| 2020 | 1 | 9,863 | $40.00 | $53.26 |
| 2019 | 1 | 70,624 | $49.00 | $52.58 |
| 2018 | 4 | 33,072 | $64.07 | $61.58 |
| 2017 | 2 | 5,607 | $70.39 | $81.18 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Oct 6, 2022 | 2678-02-008 | DentonDallas | 5,894 CY | $76.12 | A. K. GILLIS & SONS, LLC |
| Sep 7, 2022 | 0831-01-019 | McLennanWaco | 1,782 CY | $45.00 | KNIFE RIVER CORPORATION - SOUTH |
| Nov 3, 2021 | 0610-04-033 | MorrisAtlanta | 8,582 CY | $92.00 | LONGVIEW BRIDGE AND ROAD, LTD. |
| Jul 2, 2021 | 0648-03-049 | BurlesonBryan | 63,118 CY | $52.00 | BIG CREEK CONSTRUCTION, LTD. |
| Feb 5, 2021 | 3236-02-012 | CollinDallas | 5,197 CY | $45.23 | A. K. GILLIS & SONS, LLC |
| Feb 7, 2020 | 0120-05-026 | HamiltonWaco | 9,863 CY | $40.00 | BIG CREEK CONSTRUCTION, LTD. |
| Jun 4, 2019 | 0475-01-056 | BrazosBryan | 70,624 CY | $49.00 | BIG CREEK CONSTRUCTION, LTD. |
| May 1, 2018 | 1024-01-074 | ChambersBeaumont | 3,816 CY | $74.00 | OLDCASTLE MATERIALS TEXAS, INC. |
| May 1, 2018 | 0877-03-025 | TylerBeaumont | 299 CY | $67.00 | DREWERY CONSTRUCTION COMPANY, INCORPORATED |
| Apr 4, 2018 | 1420-02-012 | ChambersBeaumont | 662 CY | $94.00 | CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. |
| Apr 3, 2018 | 0508-04-162 | JeffersonBeaumont | 28,295 CY | $62.00 | STERLING DELAWARE HOLDING COMPANY, INC. |
| Jul 12, 2017 | 3092-01-009 | TylerBeaumont | 4,518 CY | $70.00 | OLDCASTLE MATERIALS TEXAS, INC. |
| Jul 11, 2017 | 1109-01-021 | JasperBeaumont | 1,089 CY | $72.00 | DREWERY CONSTRUCTION COMPANY, INCORPORATED |