Hill AO - Base Repair
6491-80-001 · let Jan 14, 2026 · Hill, Waco · Routine Maintenance Project
$734,700Low bid: BIG CREEK CONSTRUCTION, LTD.-10.5% vs estimate $820,761
$105,075Left on the table14.3% gap to the second bid
3BiddersSpread 31% low to high
21Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | BIG CREEK CONSTRUCTION, LTD. | $734,700 | -10.5% | $105,075 | 3+$53,774 | 0 | |
| 2 | TEXAS MATERIALS GROUP, INC. | $839,775 | +14.3% | 2.3% | $123,752 | 1+$18,586 | 2-$16,758 |
| 3 | KNIFE RIVER CORPORATION - SOUTH | $963,527 | +31.1% | 17.4% | 6+$206,050 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
BIG CREEK CONSTRUCTION, LTD. vs TEXAS MATERIALS GROUP, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 341-7022 D-GR HMA TY-C PG70-22 | 1,050 TON | $130.00 | $169.80 | $114.77 | $41,790 |
| 351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") | 1,500 SY | $70.00 | $96.60 | $60.19 | $39,900 |
| 351-7003 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") | 3,000 SY | $35.00 | $47.50 | $35.01 | $37,500 |
| 341-7048 D-GR HMA TY-D PG70-22 | 1,500 TON | $125.00 | $149.10 | $126.94 | $36,150 |
| 505-7001 TMA (STATIONARY) | 75 DAY | $400.00 | $87.20 | $217.57 | -$23,460 |
| 500-7033 MOBILIZATION (EMERGENCY) | 3 EA | $250.00 | $7,040.00 | $844.81 | $20,370 |
| 354-7051 PLANE ASPH CONC PAV(2") | 24,000 SY | $3.25 | $2.70 | $1.86 | -$13,200 |
| 505-7002 TMA (MOBILE OPERATION) | 60 HR | $175.00 | $30.00 | $64.00 | -$8,700 |
| 341-7082 TACK COAT | 3,000 GAL | $5.00 | $2.65 | $3.93 | -$7,050 |
| 7010-7002 MAINTENANCE SPEED LIMIT SIGNING | 60 DAY | $115.00 | $1.00 | $117.34 | -$6,840 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 60 DAY | $150.00 | $64.00 | $87.82 | -$5,160 |
| 3006-7001 UNDERSEAL COURSE | 5,100 GAL | $5.00 | $4.15 | $3.65 | -$4,335 |
| 500-7002 MOBILIZATION (CALLOUT) | 6 EA | $250.00 | $10.00 | $600.85 | -$1,440 |
| 662-7112 WK ZN PAV MRK SHT TERM (TAB)TY W | 450 EA | $1.50 | $1.00 | $1.03 | -$225 |
| 662-7114 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 | 450 EA | $1.50 | $1.00 | $0.5715 | -$225 |
| 666-7036 REFL PAV MRK TY I (W)24"(SLD)(100MIL) | 150 LF | $12.00 | $12.00 | $7.19 | $0 |
| 666-7290 TY I HIGH PERF PM (W)6"(BRK)(100MIL) | 3,000 LF | $1.35 | $1.35 | $0.5652 | $0 |
| 666-7293 TY I HIGH PERF PM (W)6"(SLD)(100MIL) | 3,000 LF | $1.35 | $1.35 | $0.5533 | $0 |
| 666-7302 TY I HIGH PERF PM (Y)6"(BRK)(100MIL) | 3,000 LF | $1.35 | $1.35 | $0.5735 | $0 |
| 666-7305 TY I HIGH PERF PM (Y)6"(SLD)(100MIL) | 3,000 LF | $1.35 | $1.35 | $0.5714 | $0 |
Positive: the low bidder was cheaper on that item. These 20 items account for $105,075 of the $105,075 gap.
BIG CREEK CONSTRUCTION, LTD.: unbalanced items
Placed 1TEXAS MATERIALS GROUP, INC.: unbalanced items
Placed 2KNIFE RIVER CORPORATION - SOUTH: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") | 1,500 SY | $110.50 | $60.19 | 1.84x | $75,463 |
| 354-7051 PLANE ASPH CONC PAV(2") | 24,000 SY | $4.25 | $1.86 | 2.29x | $57,432 |
| 505-7001 TMA (STATIONARY) | 75 DAY | $545.00 | $217.57 | 2.50x | $24,557 |
| 500-7002 MOBILIZATION (CALLOUT) | 6 EA | $4,000.00 | $600.85 | 6.66x | $20,395 |
| 3006-7001 UNDERSEAL COURSE | 5,100 GAL | $6.95 | $3.65 | 1.91x | $16,851 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 60 DAY | $277.00 | $87.82 | 3.15x | $11,351 |