McLennan - Base Repair
6491-79-001 · let Jan 14, 2026 · McLennan, Waco · Routine Maintenance Project - Sealed
$669,246Low bid: TEXAS MATERIALS GROUP, INC.+1.1% vs estimate $661,759
$6,780Left on the table1.0% gap to the second bid
3BiddersSpread 25% low to high
24Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | TEXAS MATERIALS GROUP, INC. | $669,246 | 1.1% | $6,780 | 2+$38,626 | 3-$19,582 | |
| 2 | BIG CREEK CONSTRUCTION, LTD. | $676,025 | +1.0% | 2.2% | $161,570 | 7+$51,925 | 1-$3,508 |
| 3 | KNIFE RIVER CORPORATION - SOUTH | $837,595 | +25.2% | 26.6% | 7+$137,304 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
TEXAS MATERIALS GROUP, INC. vs BIG CREEK CONSTRUCTION, LTD., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7033 MOBILIZATION (EMERGENCY) | 5 EA | $5,700.00 | $250.00 | $844.81 | -$27,250 |
| 505-7001 TMA (STATIONARY) | 55 DAY | $85.30 | $400.00 | $217.57 | $17,309 |
| 351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") | 1,250 SY | $83.00 | $70.00 | $60.19 | -$16,250 |
| 341-7048 D-GR HMA TY-D PG70-22 | 2,000 TON | $113.50 | $120.00 | $126.94 | $13,000 |
| 351-7003 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") | 1,000 SY | $47.45 | $35.00 | $35.01 | -$12,450 |
| 341-7082 TACK COAT | 1,500 GAL | $2.75 | $8.00 | $3.93 | $7,875 |
| 505-7002 TMA (MOBILE OPERATION) | 55 HR | $35.00 | $175.00 | $64.00 | $7,700 |
| 344-7019 SP MIXES SP-C PG70-22 | 1,500 TON | $123.50 | $119.00 | $142.22 | -$6,750 |
| 7010-7002 MAINTENANCE SPEED LIMIT SIGNING | 55 DAY | $1.00 | $120.00 | $117.34 | $6,545 |
| 3006-7001 UNDERSEAL COURSE | 1,500 GAL | $4.15 | $7.00 | $3.65 | $4,275 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 55 DAY | $62.80 | $125.00 | $87.82 | $3,421 |
| 500-7002 MOBILIZATION (CALLOUT) | 10 EA | $10.00 | $250.00 | $600.85 | $2,400 |
| 666-7293 TY I HIGH PERF PM (W)6"(SLD)(100MIL) | 5,000 LF | $1.15 | $1.50 | $0.5533 | $1,750 |
| 666-7305 TY I HIGH PERF PM (Y)6"(SLD)(100MIL) | 5,000 LF | $1.15 | $1.50 | $0.5714 | $1,750 |
| 354-7051 PLANE ASPH CONC PAV(2") | 9,300 SY | $3.40 | $3.50 | $1.86 | $930 |
| 666-7036 REFL PAV MRK TY I (W)24"(SLD)(100MIL) | 100 LF | $14.00 | $20.00 | $7.19 | $600 |
| 666-7290 TY I HIGH PERF PM (W)6"(BRK)(100MIL) | 1,000 LF | $1.15 | $1.50 | $0.5652 | $350 |
| 666-7302 TY I HIGH PERF PM (Y)6"(BRK)(100MIL) | 1,000 LF | $1.15 | $1.50 | $0.5735 | $350 |
| 668-7091 PREFAB PM TY C (W)(ARROW) | 5 EA | $300.00 | $350.00 | $201.69 | $250 |
| 672-7004 REFL PAV MRKR TY II-A-A | 500 EA | $6.00 | $6.50 | $3.97 | $250 |
Positive: the low bidder was cheaper on that item. These 20 items account for $6,055 of the $6,780 gap.
TEXAS MATERIALS GROUP, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7033 MOBILIZATION (EMERGENCY) | 5 EA | $5,700.00 | $844.81 | 6.75x | $24,276 |
| 354-7051 PLANE ASPH CONC PAV(2") | 9,300 SY | $3.40 | $1.86 | 1.83x | $14,350 |
| 505-7001 TMA (STATIONARY) | 55 DAY | $85.30 | $217.57 | 0.39x | -$7,275 |
| 7010-7002 MAINTENANCE SPEED LIMIT SIGNING | 55 DAY | $1.00 | $117.34 | 0.01x | -$6,399 |
| 500-7002 MOBILIZATION (CALLOUT) | 10 EA | $10.00 | $600.85 | 0.02x | -$5,908 |
BIG CREEK CONSTRUCTION, LTD.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 354-7051 PLANE ASPH CONC PAV(2") | 9,300 SY | $3.50 | $1.86 | 1.88x | $15,280 |
| 505-7001 TMA (STATIONARY) | 55 DAY | $400.00 | $217.57 | 1.84x | $10,034 |
| 505-7002 TMA (MOBILE OPERATION) | 55 HR | $175.00 | $64.00 | 2.73x | $6,105 |
| 341-7082 TACK COAT | 1,500 GAL | $8.00 | $3.93 | 2.03x | $6,098 |
| 3006-7001 UNDERSEAL COURSE | 1,500 GAL | $7.00 | $3.65 | 1.92x | $5,031 |
| 666-7293 TY I HIGH PERF PM (W)6"(SLD)(100MIL) | 5,000 LF | $1.50 | $0.5533 | 2.71x | $4,734 |
| 666-7305 TY I HIGH PERF PM (Y)6"(SLD)(100MIL) | 5,000 LF | $1.50 | $0.5714 | 2.63x | $4,643 |
| 500-7002 MOBILIZATION (CALLOUT) | 10 EA | $250.00 | $600.85 | 0.42x | -$3,508 |
KNIFE RIVER CORPORATION - SOUTH: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 351-7003 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") | 1,000 SY | $71.70 | $35.01 | 2.05x | $36,685 |
| 500-7002 MOBILIZATION (CALLOUT) | 10 EA | $3,375.00 | $600.85 | 5.62x | $27,742 |
| 505-7001 TMA (STATIONARY) | 55 DAY | $679.00 | $217.57 | 3.12x | $25,379 |
| 354-7051 PLANE ASPH CONC PAV(2") | 9,300 SY | $4.35 | $1.86 | 2.34x | $23,185 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 55 DAY | $288.00 | $87.82 | 3.28x | $11,010 |
| 341-7082 TACK COAT | 1,500 GAL | $8.50 | $3.93 | 2.16x | $6,848 |
| 3006-7001 UNDERSEAL COURSE | 1,500 GAL | $7.95 | $3.65 | 2.18x | $6,456 |