Coryell,etc. - Base Repair
6492-20-001 · let Jan 14, 2026 · Coryell, Waco · Routine Maintenance Project
$555,360Low bid: BIG CREEK CONSTRUCTION, LTD.-24.6% vs estimate $736,525
$266,777Left on the table48.0% gap to the second bid
3BiddersSpread 48% low to high
25Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | BIG CREEK CONSTRUCTION, LTD. | $555,360 | -24.6% | $266,777 | 2+$14,101 | 0 | |
| 2 | KNIFE RIVER CORPORATION - SOUTH | $822,137 | +48.0% | 11.6% | $363 | 7+$202,129 | 0 |
| 3 | TEXAS MATERIALS GROUP, INC. | $822,499 | +48.1% | 11.7% | 4+$185,123 | 1-$7,714 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
BIG CREEK CONSTRUCTION, LTD. vs KNIFE RIVER CORPORATION - SOUTH, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 351-7003 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") | 1,550 SY | $35.00 | $68.55 | $35.01 | $52,003 |
| 351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") | 900 SY | $70.00 | $126.35 | $60.19 | $50,715 |
| 341-7022 D-GR HMA TY-C PG70-22 | 1,405 TON | $127.00 | $154.70 | $114.77 | $38,919 |
| 344-7019 SP MIXES SP-C PG70-22 | 500 TON | $127.00 | $181.75 | $142.22 | $27,375 |
| 505-7001 TMA (STATIONARY) | 60 DAY | $210.00 | $660.00 | $217.57 | $27,000 |
| 500-7002 MOBILIZATION (CALLOUT) | 6 EA | $250.00 | $4,150.00 | $600.85 | $23,400 |
| 354-7051 PLANE ASPH CONC PAV(2") | 7,500 SY | $3.25 | $6.15 | $1.86 | $21,750 |
| 341-7048 D-GR HMA TY-D PG70-22 | 800 TON | $132.00 | $149.50 | $126.94 | $14,000 |
| 3006-7001 UNDERSEAL COURSE | 1,800 GAL | $4.00 | $7.20 | $3.65 | $5,760 |
| 500-7033 MOBILIZATION (EMERGENCY) | 3 EA | $400.00 | $2,235.00 | $844.81 | $5,505 |
| 7010-7002 MAINTENANCE SPEED LIMIT SIGNING | 20 DAY | $300.00 | $65.00 | $117.34 | -$4,700 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 20 DAY | $105.00 | $278.00 | $87.82 | $3,460 |
| 341-7082 TACK COAT | 500 GAL | $4.00 | $8.20 | $3.93 | $2,100 |
| 505-7002 TMA (MOBILE OPERATION) | 60 HR | $100.00 | $96.00 | $64.00 | -$240 |
| 662-7112 WK ZN PAV MRK SHT TERM (TAB)TY W | 150 EA | $2.00 | $1.00 | $1.03 | -$150 |
| 662-7114 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 | 150 EA | $2.00 | $1.00 | $0.5715 | -$150 |
| 668-7091 PREFAB PM TY C (W)(ARROW) | 9 EA | $325.00 | $339.00 | $201.69 | $126 |
| 668-7103 PREFAB PM TY C (W)(WORD) | 9 EA | $450.00 | $458.00 | $249.54 | $72 |
| 672-7004 REFL PAV MRKR TY II-A-A | 1,200 EA | $6.50 | $6.45 | $3.97 | -$60 |
| 666-7290 TY I HIGH PERF PM (W)6"(BRK)(100MIL) | 1,000 LF | $2.50 | $2.45 | $0.5652 | -$50 |
Positive: the low bidder was cheaper on that item. These 20 items account for $266,834 of the $266,777 gap.
BIG CREEK CONSTRUCTION, LTD.: unbalanced items
Placed 1KNIFE RIVER CORPORATION - SOUTH: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") | 900 SY | $126.35 | $60.19 | 2.10x | $59,543 |
| 351-7003 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") | 1,550 SY | $68.55 | $35.01 | 1.96x | $51,979 |
| 354-7051 PLANE ASPH CONC PAV(2") | 7,500 SY | $6.15 | $1.86 | 3.31x | $32,198 |
| 505-7001 TMA (STATIONARY) | 60 DAY | $660.00 | $217.57 | 3.03x | $26,546 |
| 500-7002 MOBILIZATION (CALLOUT) | 6 EA | $4,150.00 | $600.85 | 6.91x | $21,295 |
| 3006-7001 UNDERSEAL COURSE | 1,800 GAL | $7.20 | $3.65 | 1.97x | $6,398 |
| 500-7033 MOBILIZATION (EMERGENCY) | 3 EA | $2,235.00 | $844.81 | 2.65x | $4,171 |
TEXAS MATERIALS GROUP, INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") | 900 SY | $139.00 | $60.19 | 2.31x | $70,928 |
| 351-7003 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") | 1,550 SY | $77.00 | $35.01 | 2.20x | $65,077 |
| 354-7051 PLANE ASPH CONC PAV(2") | 7,500 SY | $6.60 | $1.86 | 3.55x | $35,573 |
| 500-7033 MOBILIZATION (EMERGENCY) | 3 EA | $5,360.00 | $844.81 | 6.34x | $13,546 |
| 505-7001 TMA (STATIONARY) | 60 DAY | $89.00 | $217.57 | 0.41x | -$7,714 |