Bid Tab X-ray: 0114-10-108

Apr 8, 2026 · Washington Sign up free
Set your company to personalize scores

US 290 F: FM 577 T: FM 1155 - FY 26

0114-10-108 · let Apr 8, 2026 · Washington, Bryan · Overlay

$6,537,278Low bid: DURWOOD GREENE CONSTRUCTION CO.+6.8% vs estimate $6,122,429
$178,347Left on the table2.7% gap to the second bid
7BiddersSpread 22% low to high
27Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1DURWOOD GREENE CONSTRUCTION CO. $6,537,2786.8% $178,347 0 3-$541,053
2BIG CREEK CONSTRUCTION, LTD. $6,715,625+2.7%9.7% $270,335 0 3-$437,441
3TEXAS MATERIALS GROUP, INC. $6,985,960+6.9%14.1% $75,452 0 3-$493,381
4KNIFE RIVER CORPORATION - SOUTH $7,061,412+8.0%15.3% $132,489 0 3-$557,707
5ENVIRONMENTAL ALLIES, INC. $7,193,900+10.0%17.5% $462,143 0 0
6LARRY YOUNG PAVING, INC. $7,656,043+17.1%25.0% $334,269
7BRAZOS PAVING, INC. $7,990,313+22.2%30.5%

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.

Where the job was won

DURWOOD GREENE CONSTRUCTION CO. vs BIG CREEK CONSTRUCTION, LTD., biggest item swings
ItemQtyLow2ndMarket2nd minus low
354-7076 PLANE ASPH CONC PAV (1" TO 2")293,899 SY $1.75$2.00$1.92 $73,475
500-7001 MOBILIZATION1 LS $130,000.00$200,000.00$523,850.32 $70,000
134-7004 BACKFILL (TY A OR B)657.6 STA $100.00$200.00$211.21 $65,760
342-7015 TACK COAT29,390 GAL $2.75$2.00$3.37 -$22,043
347-7011 TACK COAT29,390 GAL $2.75$2.00$3.24 -$22,043
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING7 MO $7,000.00$5,000.00$11,585.04 -$14,000
662-7008 WK ZN PAV MRK NON-REMOV (W)6"(SLD)130,176 LF $0.2200$0.2800$0.2750 $7,811
662-7038 WK ZN PAV MRK NON-REMOV (Y)6"(SLD)128,564 LF $0.2200$0.2800$0.2770 $7,714
150-7001 BLADING657.6 STA $40.00$50.00$152.64 $6,576
505-7003 TMA (MOBILE OPERATION)18 DAY $250.00$550.00$229.60 $5,400
662-7112 WK ZN PAV MRK SHT TERM (TAB)TY W6,150 EA $2.25$1.50$1.03 -$4,613
505-7001 TMA (STATIONARY)79 DAY $300.00$250.00$217.57 -$3,950
666-7410 REFL PAV MRK TY I (W)6"(SLD)(090MIL)65,088 LF $0.5600$0.6000$0.4886 $2,604
666-7065 REFL PAV MRK TY I (W)(WORD)(090MIL)37 EA $220.00$150.00$203.99 -$2,590
666-7422 REFL PAV MRK TY I (Y)6"(SLD)(090MIL)64,282 LF $0.5600$0.6000$0.5014 $2,571
533-7001 MILL RUMBLE STRIPS (ASPHALT) (SHLDR)118,320 LF $0.1800$0.2000$0.2040 $2,366
662-7012 WK ZN PAV MRK NON-REMOV (W)8"(SLD)9,128 LF $0.3000$0.5500$0.6092 $2,282
662-7005 WK ZN PAV MRK NON-REMOV (W)6"(BRK)32,544 LF $0.2200$0.2800$0.3316 $1,953
666-7041 REFL PAV MRK TY I (W)(ARROW)(090MIL)38 EA $190.00$150.00$164.35 -$1,520
666-7017 REFL PAV MRK TY I (W)8"(DOT)(090MIL)3,149 LF $1.35$1.00$1.25 -$1,102

Positive: the low bidder was cheaper on that item. These 20 items account for $176,651 of the $178,347 gap.

DURWOOD GREENE CONSTRUCTION CO.: unbalanced items

Placed 1
ItemQtyTheir priceMarketx market$ vs market
500-7001 MOBILIZATION1 LS $130,000.00$523,850.320.25x-$393,850
150-7001 BLADING657.6 STA $40.00$152.640.26x-$74,071
134-7004 BACKFILL (TY A OR B)657.6 STA $100.00$211.210.47x-$73,132

BIG CREEK CONSTRUCTION, LTD.: unbalanced items

Placed 2
ItemQtyTheir priceMarketx market$ vs market
500-7001 MOBILIZATION1 LS $200,000.00$523,850.320.38x-$323,850
150-7001 BLADING657.6 STA $50.00$152.640.33x-$67,495
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING7 MO $5,000.00$11,585.040.43x-$46,095

TEXAS MATERIALS GROUP, INC.: unbalanced items

Placed 3
ItemQtyTheir priceMarketx market$ vs market
500-7001 MOBILIZATION1 LS $178,000.00$523,850.320.34x-$345,850
150-7001 BLADING657.6 STA $25.00$152.640.16x-$83,935
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING7 MO $2,500.00$11,585.040.22x-$63,595

KNIFE RIVER CORPORATION - SOUTH: unbalanced items

Placed 4
ItemQtyTheir priceMarketx market$ vs market
500-7001 MOBILIZATION1 LS $153,000.00$523,850.320.29x-$370,850
150-7001 BLADING657.6 STA $9.90$152.640.06x-$93,865
134-7004 BACKFILL (TY A OR B)657.6 STA $69.80$211.210.33x-$92,991