BELL - FY27 BASE FAILURE REPAIR
6510-39-001 · let Nov 4, 2026 · Bell, Waco · Routine Maintenance Project
$1,470,225Low bid: TEXAS MATERIALS GROUP, INC.-15.9% vs estimate $1,748,410
$299,200Left on the table20.4% gap to the second bid
3BiddersSpread 28% low to high
26Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | TEXAS MATERIALS GROUP, INC. | $1,470,225 | -15.9% | $299,200 | 1+$8,416 | 0 | |
| 2 | BIG CREEK CONSTRUCTION, LTD. | $1,769,425 | +20.4% | 1.2% | $107,275 | 0 | 0 |
| 3 | LONE STAR PAVING COMPANY | $1,876,700 | +27.6% | 7.3% | 3+$111,167 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
TEXAS MATERIALS GROUP, INC. vs BIG CREEK CONSTRUCTION, LTD., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 341-7048 D-GR HMA TY-D PG70-22 | 4,000 TON | $119.00 | $145.00 | $126.94 | $104,000 |
| 341-7022 D-GR HMA TY-C PG70-22 | 2,500 TON | $122.00 | $140.00 | $114.77 | $45,000 |
| 344-7019 SP MIXES SP-C PG70-22 | 2,500 TON | $122.10 | $140.00 | $142.22 | $44,750 |
| 354-7051 PLANE ASPH CONC PAV(2") | 40,000 SY | $1.45 | $2.50 | $1.86 | $42,000 |
| 351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") | 2,000 SY | $68.00 | $85.00 | $60.19 | $34,000 |
| 351-7003 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") | 1,600 SY | $38.00 | $45.00 | $35.01 | $11,200 |
| 500-7033 MOBILIZATION (EMERGENCY) | 3 EA | $3,650.00 | $50.00 | $844.81 | -$10,800 |
| 341-7082 TACK COAT | 4,000 GAL | $2.90 | $5.00 | $3.93 | $8,400 |
| 505-7001 TMA (STATIONARY) | 50 DAY | $105.00 | $250.00 | $217.57 | $7,250 |
| 3006-7001 UNDERSEAL COURSE | 3,000 GAL | $4.00 | $5.00 | $3.65 | $3,000 |
| 666-7293 TY I HIGH PERF PM (W)6"(SLD)(100MIL) | 12,000 LF | $0.7000 | $0.9500 | $0.5533 | $3,000 |
| 666-7305 TY I HIGH PERF PM (Y)6"(SLD)(100MIL) | 12,000 LF | $0.7000 | $0.9500 | $0.5714 | $3,000 |
| 7010-7002 MAINTENANCE SPEED LIMIT SIGNING | 25 DAY | $1.00 | $50.00 | $117.34 | $1,225 |
| 662-7112 WK ZN PAV MRK SHT TERM (TAB)TY W | 1,000 EA | $1.00 | $2.00 | $1.03 | $1,000 |
| 662-7114 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 | 1,000 EA | $1.00 | $2.00 | $0.5715 | $1,000 |
| 351-7005 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") | 750 SY | $66.00 | $65.00 | $49.06 | -$750 |
| 505-7002 TMA (MOBILE OPERATION) | 25 HR | $20.00 | $50.00 | $64.00 | $750 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 25 DAY | $120.00 | $100.00 | $87.82 | -$500 |
| 668-7103 PREFAB PM TY C (W)(WORD) | 10 EA | $300.00 | $350.00 | $249.54 | $500 |
| 672-7004 REFL PAV MRKR TY II-A-A | 1,000 EA | $5.50 | $6.00 | $3.97 | $500 |
Positive: the low bidder was cheaper on that item. These 20 items account for $298,525 of the $299,200 gap.
TEXAS MATERIALS GROUP, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7033 MOBILIZATION (EMERGENCY) | 3 EA | $3,650.00 | $844.81 | 4.32x | $8,416 |