Bid Tab X-ray: 6510-39-001

Nov 4, 2026 · Bell Sign up free
Set your company to personalize scores

BELL - FY27 BASE FAILURE REPAIR

6510-39-001 · let Nov 4, 2026 · Bell, Waco · Routine Maintenance Project

$1,470,225Low bid: TEXAS MATERIALS GROUP, INC.-15.9% vs estimate $1,748,410
$299,200Left on the table20.4% gap to the second bid
3BiddersSpread 28% low to high
26Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1TEXAS MATERIALS GROUP, INC. $1,470,225-15.9% $299,200 1+$8,416 0
2BIG CREEK CONSTRUCTION, LTD. $1,769,425+20.4%1.2% $107,275 0 0
3LONE STAR PAVING COMPANY $1,876,700+27.6%7.3% 3+$111,167 0

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.

Where the job was won

TEXAS MATERIALS GROUP, INC. vs BIG CREEK CONSTRUCTION, LTD., biggest item swings
ItemQtyLow2ndMarket2nd minus low
341-7048 D-GR HMA TY-D PG70-224,000 TON $119.00$145.00$126.94 $104,000
341-7022 D-GR HMA TY-C PG70-222,500 TON $122.00$140.00$114.77 $45,000
344-7019 SP MIXES SP-C PG70-222,500 TON $122.10$140.00$142.22 $44,750
354-7051 PLANE ASPH CONC PAV(2")40,000 SY $1.45$2.50$1.86 $42,000
351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")2,000 SY $68.00$85.00$60.19 $34,000
351-7003 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4")1,600 SY $38.00$45.00$35.01 $11,200
500-7033 MOBILIZATION (EMERGENCY)3 EA $3,650.00$50.00$844.81 -$10,800
341-7082 TACK COAT4,000 GAL $2.90$5.00$3.93 $8,400
505-7001 TMA (STATIONARY)50 DAY $105.00$250.00$217.57 $7,250
3006-7001 UNDERSEAL COURSE3,000 GAL $4.00$5.00$3.65 $3,000
666-7293 TY I HIGH PERF PM (W)6"(SLD)(100MIL)12,000 LF $0.7000$0.9500$0.5533 $3,000
666-7305 TY I HIGH PERF PM (Y)6"(SLD)(100MIL)12,000 LF $0.7000$0.9500$0.5714 $3,000
7010-7002 MAINTENANCE SPEED LIMIT SIGNING25 DAY $1.00$50.00$117.34 $1,225
662-7112 WK ZN PAV MRK SHT TERM (TAB)TY W1,000 EA $1.00$2.00$1.03 $1,000
662-7114 WK ZN PAV MRK SHT TERM (TAB)TY Y-21,000 EA $1.00$2.00$0.5715 $1,000
351-7005 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")750 SY $66.00$65.00$49.06 -$750
505-7002 TMA (MOBILE OPERATION)25 HR $20.00$50.00$64.00 $750
503-7001 PORTABLE CHANGEABLE MESSAGE SIGN25 DAY $120.00$100.00$87.82 -$500
668-7103 PREFAB PM TY C (W)(WORD)10 EA $300.00$350.00$249.54 $500
672-7004 REFL PAV MRKR TY II-A-A1,000 EA $5.50$6.00$3.97 $500

Positive: the low bidder was cheaper on that item. These 20 items account for $298,525 of the $299,200 gap.

TEXAS MATERIALS GROUP, INC.: unbalanced items

Placed 1
ItemQtyTheir priceMarketx market$ vs market
500-7033 MOBILIZATION (EMERGENCY)3 EA $3,650.00$844.814.32x$8,416

LONE STAR PAVING COMPANY: unbalanced items

Placed 3
ItemQtyTheir priceMarketx market$ vs market
354-7051 PLANE ASPH CONC PAV(2")40,000 SY $3.40$1.861.83x$61,720
351-7005 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")750 SY $99.00$49.062.02x$37,451
500-7002 MOBILIZATION (CALLOUT)5 EA $3,000.00$600.854.99x$11,996