HILLSBORO AO - FY27 BASE FAILURE REPAIR
6510-36-001 · let Nov 4, 2026 · Hill, Waco · Routine Maintenance Project
$1,603,275Low bid: BIG CREEK CONSTRUCTION, LTD.-15.6% vs estimate $1,899,845
$141,783Left on the table8.8% gap to the second bid
3BiddersSpread 12% low to high
25Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | BIG CREEK CONSTRUCTION, LTD. | $1,603,275 | -15.6% | $141,783 | 0 | 0 | |
| 2 | TEXAS MATERIALS GROUP, INC. | $1,745,058 | +8.8% | -8.1% | $54,162 | 1+$11,430 | 2-$18,065 |
| 3 | KNIFE RIVER CORPORATION - SOUTH | $1,799,220 | +12.2% | -5.3% | 4+$117,055 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
BIG CREEK CONSTRUCTION, LTD. vs TEXAS MATERIALS GROUP, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 341-7048 D-GR HMA TY-D PG70-22 | 2,750 TON | $120.00 | $148.00 | $126.94 | $77,000 |
| 341-7022 D-GR HMA TY-C PG70-22 | 2,750 TON | $122.00 | $146.00 | $114.77 | $66,000 |
| 351-7003 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") | 4,500 SY | $35.00 | $45.00 | $35.01 | $45,000 |
| 354-7051 PLANE ASPH CONC PAV(2") | 42,000 SY | $2.00 | $1.60 | $1.86 | -$16,800 |
| 500-7033 MOBILIZATION (EMERGENCY) | 2 EA | $50.00 | $6,560.00 | $844.81 | $13,020 |
| 3006-7001 UNDERSEAL COURSE | 6,800 GAL | $5.75 | $4.00 | $3.65 | -$11,900 |
| 341-7082 TACK COAT | 3,000 GAL | $5.50 | $2.90 | $3.93 | -$7,800 |
| 351-7005 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") | 3,900 SY | $55.00 | $53.00 | $49.06 | -$7,800 |
| 351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") | 5,000 SY | $70.00 | $69.20 | $60.19 | -$4,000 |
| 7010-7002 MAINTENANCE SPEED LIMIT SIGNING | 80 DAY | $50.00 | $1.00 | $117.34 | -$3,920 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 40 DAY | $145.00 | $120.00 | $87.82 | -$1,000 |
| 668-7103 PREFAB PM TY C (W)(WORD) | 22 EA | $350.00 | $315.00 | $249.54 | -$770 |
| 505-7002 TMA (MOBILE OPERATION) | 60 HR | $90.00 | $80.00 | $64.00 | -$600 |
| 668-7091 PREFAB PM TY C (W)(ARROW) | 20 EA | $300.00 | $270.00 | $201.69 | -$600 |
| 666-7305 TY I HIGH PERF PM (Y)6"(SLD)(100MIL) | 6,000 LF | $1.20 | $1.10 | $0.5714 | -$600 |
| 672-7002 REFL PAV MRKR TY I-C | 900 EA | $7.15 | $6.50 | $4.04 | -$585 |
| 666-7036 REFL PAV MRK TY I (W)24"(SLD)(100MIL) | 440 LF | $13.50 | $12.25 | $7.19 | -$550 |
| 666-7290 TY I HIGH PERF PM (W)6"(BRK)(100MIL) | 4,000 LF | $1.15 | $1.05 | $0.5652 | -$400 |
| 666-7293 TY I HIGH PERF PM (W)6"(SLD)(100MIL) | 4,000 LF | $1.20 | $1.10 | $0.5533 | -$400 |
| 666-7302 TY I HIGH PERF PM (Y)6"(BRK)(100MIL) | 4,000 LF | $1.15 | $1.05 | $0.5735 | -$400 |
Positive: the low bidder was cheaper on that item. These 20 items account for $142,895 of the $141,783 gap.