SH 30 NAVASOTA RIVER RELIEF #1 - BR
0212-03-058 · let Nov 4, 2026 · Brazos, Bryan · Bridge Replacement
$30,209,876Low bid: FLUOR ENTERPRISES, INC.-4.8% vs estimate $31,732,117
$2,977,718Left on the table9.9% gap to the second bid
12BiddersSpread 60% low to high
406Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | FLUOR ENTERPRISES, INC. | $30,209,876 | -4.8% | $2,977,718 | 1+$2,496,150 | 2-$860,735 | |
| 2 | BIG CREEK CONSTRUCTION, LTD. | $33,187,594 | +9.9% | 4.6% | $724,204 | 1+$2,476,150 | 2-$774,786 |
| 3 | KNIFE RIVER CORPORATION - SOUTH | $33,911,798 | +12.3% | 6.9% | $950,878 | 1+$1,346,150 | 4-$1,911,311 |
| 4 | R CONSTRUCTION CIVIL, LLC | $34,862,676 | +15.4% | 9.9% | $4,375,152 | 3+$2,842,951 | 2-$1,056,741 |
| 5 | JAMES CONSTRUCTION GROUP, LLC | $39,237,828 | +29.9% | 23.7% | $324,577 | 2+$6,238,538 | 3-$823,978 |
| 6 | TEXAS MATERIALS GROUP, INC. | $39,562,405 | +31.0% | 24.7% | $68,294 | ||
| 7 | A. L. HELMCAMP, INC. | $39,630,699 | +31.2% | 24.9% | $364,296 | ||
| 8 | POSILLICO CIVIL, INC. | $39,994,995 | +32.4% | 26.0% | $2,449,066 | ||
| 9 | ZACHRY CONSTRUCTION CORPORATION | $42,444,061 | +40.5% | 33.8% | $1,264,288 | ||
| 10 | BRIZO CONSTRUCTION, LLC | $43,708,350 | +44.7% | 37.7% | $679,620 | ||
| 11 | GRANITE CONSTRUCTION COMPANY | $44,387,970 | +46.9% | 39.9% | $4,009,002 | ||
| 12 | ISI CONTRACTING, INC. | $48,396,973 | +60.2% | 52.5% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
FLUOR ENTERPRISES, INC. vs BIG CREEK CONSTRUCTION, LTD., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 422-7001 REINF CONC SLAB | 111,370 SF | $20.50 | $28.00 | $24.45 | $835,275 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 283,087 CY | $10.00 | $12.00 | $13.19 | $566,174 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 14,070 LF | $7.00 | $40.00 | $52.29 | $464,310 |
| 425-7005 PRESTR CONC GIRDER (TX54) | 8,779.5 LF | $188.00 | $230.00 | $215.33 | $368,739 |
| 247-7350 FL BS (CMP IN PLC)(TY A GR 1-2) (9") | 123,992 SY | $20.50 | $23.00 | $23.65 | $309,980 |
| 100-7002 PREPARING ROW | 150.5 STA | $4,376.74 | $2,500.00 | $6,072.92 | -$282,449 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 2 EA | $200,000.00 | $100,000.00 | $136,676.66 | -$200,000 |
| 344-7001 SP MIXES SP-B PG64-22 | 33,968 TON | $94.50 | $100.00 | $124.45 | $186,824 |
| 110-7001 EXCAV (ROADWAY) | 33,904 CY | $6.50 | $12.00 | $11.68 | $186,472 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 166,415 SY | $1.95 | $1.00 | $1.43 | -$158,094 |
| 422-7013 APPROACH SLAB | 405 CY | $648.00 | $1,000.00 | $738.51 | $142,560 |
| 416-7007 DRILL SHAFT (42 IN) | 3,649 LF | $281.00 | $320.00 | $318.92 | $142,311 |
| 450-7024 RAIL (TY SSTR) | 2,830 LF | $43.50 | $90.00 | $69.92 | $131,595 |
| 420-7012 CL C CONC (ABUT) | 347.5 CY | $1,047.00 | $1,400.00 | $1,307.98 | $122,668 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 36 MO | $8,381.00 | $5,000.00 | $11,585.04 | -$121,716 |
| 4006-7001 TEMP CONSTRUCTION ACCESS | 1 LS | $450,000.00 | $330,000.00 | $447,206.31 | -$120,000 |
| 505-7001 TMA (STATIONARY) | 392 DAY | $492.00 | $200.00 | $217.57 | -$114,464 |
| 105-7014 RMV (14"-18") TRT/UNTRT BASE & ASPH PAV | 64,084 SY | $6.50 | $5.00 | $9.39 | -$96,126 |
| 420-7022 CL C CONC (CAP) | 421.5 CY | $1,378.00 | $1,600.00 | $1,543.38 | $93,573 |
| 275-7001 CEMENT | 2,113 TON | $185.00 | $220.00 | $224.93 | $73,955 |
Positive: the low bidder was cheaper on that item. These 20 items account for $2,531,586 of the $2,977,718 gap.
FLUOR ENTERPRISES, INC.: unbalanced items
Placed 1BIG CREEK CONSTRUCTION, LTD.: unbalanced items
Placed 2KNIFE RIVER CORPORATION - SOUTH: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $1,870,000.00 | $523,850.32 | 3.57x | $1,346,150 |
| 100-7002 PREPARING ROW | 150.5 STA | $595.72 | $6,072.92 | 0.10x | -$824,319 |
| 105-7014 RMV (14"-18") TRT/UNTRT BASE & ASPH PAV | 64,084 SY | $0.7200 | $9.39 | 0.08x | -$555,454 |
| 275-7028 CEMENT TRT (SUBGRADE)(10") | 128,047 SY | $1.03 | $3.15 | 0.33x | -$272,049 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 36 MO | $4,377.00 | $11,585.04 | 0.38x | -$259,490 |
R CONSTRUCTION CIVIL, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $2,400,000.00 | $523,850.32 | 4.58x | $1,876,150 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 166,415 SY | $4.50 | $1.43 | 3.15x | $511,011 |
| 105-7014 RMV (14"-18") TRT/UNTRT BASE & ASPH PAV | 64,084 SY | $16.50 | $9.39 | 1.76x | $455,791 |
| 100-7002 PREPARING ROW | 150.5 STA | $2,000.00 | $6,072.92 | 0.33x | -$612,975 |
| 4006-7001 TEMP CONSTRUCTION ACCESS | 1 LS | $3,440.00 | $447,206.31 | 0.01x | -$443,766 |
JAMES CONSTRUCTION GROUP, LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $3,880,000.00 | $523,850.32 | 7.41x | $3,356,150 |
| 100-7002 PREPARING ROW | 150.5 STA | $25,225.00 | $6,072.92 | 4.15x | $2,882,388 |
| 105-7014 RMV (14"-18") TRT/UNTRT BASE & ASPH PAV | 64,084 SY | $3.84 | $9.39 | 0.41x | -$355,512 |
| 496-7011 REMOV STR (BRIDGE 500 - 999 FT LENGTH) | 1 EA | $137,598.04 | $378,521.97 | 0.36x | -$240,924 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 36 MO | $5,264.43 | $11,585.04 | 0.45x | -$227,542 |