FY26 Plainview LRA
6499-11-001 · let Apr 21, 2026 · Hale, Lubbock · Material Maintenance Project
$826,770Low bid: VULCAN CONSTRUCTION MATERIALS, LLC+6.7% vs estimate $775,000
$8,740Left on the table1.1% gap to the second bid
2BiddersSpread 1% low to high
10Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | VULCAN CONSTRUCTION MATERIALS, LLC | $826,770 | 6.7% | $8,740 | 0 | 0 | |
| 2 | MARTIN MARIETTA MATERIALS, INC. | $835,510 | +1.1% | 7.8% | 0 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
VULCAN CONSTRUCTION MATERIALS, LLC vs MARTIN MARIETTA MATERIALS, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 8001-7012 LRA (TY I GR AA) (DEL) (ST4) | 500 TON | $158.37 | $162.29 | $124.59 | $1,960 |
| 8001-7013 LRA (TY I GR AA) (DEL) (ST5) | 500 TON | $153.42 | $156.47 | $119.67 | $1,525 |
| 8001-7110 LRA (TY II GR DS) (DEL) (ST4) | 500 TON | $162.37 | $165.09 | $127.32 | $1,360 |
| 8001-7011 LRA (TY I GR AA) (DEL) (ST3) | 500 TON | $162.88 | $165.30 | $127.41 | $1,210 |
| 8001-7111 LRA (TY II GR DS) (DEL) (ST5) | 500 TON | $157.42 | $159.27 | $127.02 | $925 |
| 8001-7010 LRA (TY I GR AA) (DEL) (ST2) | 500 TON | $169.76 | $171.52 | $124.75 | $880 |
| 8001-7109 LRA (TY II GR DS) (DEL) (ST3) | 500 TON | $166.88 | $168.10 | $132.08 | $610 |
| 8001-7107 LRA (TY II GR DS) (DEL) (ST1) | 500 TON | $176.34 | $175.73 | $125.06 | -$305 |
| 8001-7009 LRA (TY I GR AA) (DEL) (ST1) | 500 TON | $172.34 | $172.93 | $112.79 | $295 |
| 8001-7108 LRA (TY II GR DS) (DEL) (ST2) | 500 TON | $173.76 | $174.32 | $141.87 | $280 |
Positive: the low bidder was cheaper on that item. These 10 items account for $8,740 of the $8,740 gap.