$143.66Avg low bid / TON
$146.50Avg of all bids
$138.31Avg engineer's estimate
16Jobs · 9,330 TON
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2026 | 15 | 8,830 | $143.96 | $146.77 |
| 2025 | 1 | 500 | $138.27 | $141.74 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Nov 18, 2026 | 6511-39-001 | BrazosBryan | 750 TON | $145.17 | VULCAN CONSTRUCTION MATERIALS, LLC |
| Nov 17, 2026 | 6511-40-001 | WalkerBryan | 750 TON | $146.24 | MARTIN MARIETTA MATERIALS, INC. |
| Sep 9, 2026 | 6502-44-001 | KaufmanDallas | 130 TON | $171.41 | MARTIN MARIETTA MATERIALS, INC. |
| Jul 7, 2026 | 6503-58-001 | AngelinaLufkin | 1,000 TON | $150.76 | VULCAN CONSTRUCTION MATERIALS, LLC |
| Jun 10, 2026 | 6502-39-001 | FreestoneBryan | 600 TON | $145.21 | MARTIN MARIETTA MATERIALS, INC. |
| Apr 28, 2026 | 6501-36-001 | PecosOdessa | 100 TON | $142.21 | VULCAN CONSTRUCTION MATERIALS, LLC |
| Apr 28, 2026 | 6501-37-001 | MidlandOdessa | 100 TON | $133.39 | VULCAN CONSTRUCTION MATERIALS, LLC |
| Apr 22, 2026 | 6494-95-001 | VictoriaYoakum | 1,000 TON | $131.15 | MARTIN MARIETTA MATERIALS, INC. |
| Apr 21, 2026 | 6499-13-001 | LubbockLubbock | 500 TON | $160.85 | VULCAN CONSTRUCTION MATERIALS, LLC |
| Apr 21, 2026 | 6499-10-001 | TerryLubbock | 500 TON | $153.55 | VULCAN CONSTRUCTION MATERIALS, LLC |
| Apr 21, 2026 | 6499-11-001 | HaleLubbock | 500 TON | $173.76 | VULCAN CONSTRUCTION MATERIALS, LLC |
| Apr 21, 2026 | 6499-12-001 | LambLubbock | 500 TON | $173.47 | VULCAN CONSTRUCTION MATERIALS, LLC |
| Mar 24, 2026 | 6498-44-001 | RunnelsSan Angelo | 300 TON | $110.35 | VULCAN CONSTRUCTION MATERIALS, LLC |
| Feb 17, 2026 | 6494-32-001 | WhartonYoakum | 2,000 TON | $126.21 | VULCAN CONSTRUCTION MATERIALS, LLC |
| Jan 28, 2026 | 6496-10-001 | PotterAmarillo | 100 TON | $174.00 | MARTIN MARIETTA MATERIALS, INC. |
| Nov 5, 2025 | 6459-69-001 | HidalgoPharr | 500 TON | $138.27 | MARTIN MARIETTA MATERIALS, INC. |
| Sep 17, 2025 | 6491-12-001 | JeffersonBeaumont | 500 TON | $147.82 | MARTIN MARIETTA MATERIALS, INC. |
| Aug 13, 2025 | 6485-97-001 | KaufmanDallas | 250 TON | $163.46 | MARTIN MARIETTA MATERIALS, INC. |
| Jun 24, 2025 | 6485-22-001 | PecosOdessa | 100 TON | $136.21 | VULCAN CONSTRUCTION MATERIALS, LLC |
| Jun 12, 2025 | 6483-73-001 | WalkerBryan | 1,000 TON | $137.62 | MARTIN MARIETTA MATERIALS, INC. |
| Jun 10, 2025 | 6483-74-001 | BrazosBryan | 750 TON | $134.34 | VULCAN CONSTRUCTION MATERIALS, LLC |
| May 15, 2025 | 6482-56-001 | TerryLubbock | 500 TON | $145.40 | VULCAN CONSTRUCTION MATERIALS, LLC |
| May 15, 2025 | 6482-58-001 | HaleLubbock | 500 TON | $163.40 | VULCAN CONSTRUCTION MATERIALS, LLC |
| May 15, 2025 | 6482-59-001 | LubbockLubbock | 500 TON | $148.60 | VULCAN CONSTRUCTION MATERIALS, LLC |
| May 14, 2025 | 6483-99-001 | ChildressChildress | 500 TON | $164.95 | MARTIN MARIETTA MATERIALS, INC. |
| Apr 21, 2025 | 6477-07-001 | VictoriaYoakum | 1,000 TON | $123.73 | MARTIN MARIETTA MATERIALS, INC. |
| Feb 18, 2025 | 6476-56-001 | WhartonYoakum | 2,000 TON | $128.37 | MARTIN MARIETTA MATERIALS, INC. |
| Jan 21, 2025 | 6478-12-001 | FreestoneBryan | 600 TON | $147.20 | MARTIN MARIETTA MATERIALS, INC. |
| Nov 22, 2024 | 6476-94-001 | JonesAbilene | 25 TON | $139.42 | VULCAN CONSTRUCTION MATERIALS, LLC |