$119.67Avg low bid / TON
$121.39Avg of all bids
$122.11Avg engineer's estimate
14Jobs · 10,900 TON
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2026 | 7 | 5,650 | $122.30 | $123.52 |
| 2025 | 7 | 5,250 | $116.84 | $119.09 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Nov 17, 2026 | 6506-96-001 | HillWaco | 200 TON | $139.58 | VULCAN CONSTRUCTION MATERIALS, LLC |
| Apr 28, 2026 | 6501-36-001 | PecosOdessa | 200 TON | $115.95 | VULCAN CONSTRUCTION MATERIALS, LLC |
| Apr 21, 2026 | 6499-10-001 | TerryLubbock | 250 TON | $148.91 | VULCAN CONSTRUCTION MATERIALS, LLC |
| Apr 21, 2026 | 6499-11-001 | HaleLubbock | 500 TON | $153.42 | VULCAN CONSTRUCTION MATERIALS, LLC |
| Apr 21, 2026 | 6499-12-001 | LambLubbock | 500 TON | $157.43 | VULCAN CONSTRUCTION MATERIALS, LLC |
| Mar 11, 2026 | 6483-16-001 | BurnetAustin | 2,500 TON | $111.21 | MARTIN MARIETTA MATERIALS, INC. |
| Jan 14, 2026 | 6483-14-001 | BastropAustin | 1,500 TON | $112.82 | VULCAN CONSTRUCTION MATERIALS, LLC |
| Nov 13, 2025 | 6487-07-001 | HillWaco | 200 TON | $130.80 | VULCAN CONSTRUCTION MATERIALS, LLC |
| Jun 24, 2025 | 6485-22-001 | PecosOdessa | 50 TON | $111.95 | VULCAN CONSTRUCTION MATERIALS, LLC |
| May 15, 2025 | 6482-58-001 | HaleLubbock | 500 TON | $145.20 | VULCAN CONSTRUCTION MATERIALS, LLC |
| May 15, 2025 | 6482-56-001 | TerryLubbock | 250 TON | $142.00 | VULCAN CONSTRUCTION MATERIALS, LLC |
| May 14, 2025 | 6483-99-001 | ChildressChildress | 250 TON | $140.30 | MARTIN MARIETTA MATERIALS, INC. |
| Mar 12, 2025 | 6468-16-001 | BurnetAustin | 2,500 TON | $108.10 | MARTIN MARIETTA MATERIALS, INC. |
| Jan 15, 2025 | 6468-11-001 | BastropAustin | 1,500 TON | $112.15 | MARTIN MARIETTA MATERIALS, INC. |