PW within Lake Brownwood SP
0923-06-068 · let Nov 4, 2026 · Brown, Brownwood · Texas Park and Wildlife
$1,561,729Low bid: JAY MILLS CONTRACTING, INCORPORATED-10.3% vs estimate $1,740,230
$122,095Left on the table7.8% gap to the second bid
6BiddersSpread 54% low to high
41Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | JAY MILLS CONTRACTING, INCORPORATED | $1,561,729 | -10.3% | $122,095 | 1+$11,497 | 2-$404,190 | |
| 2 | LONE STAR PAVING COMPANY | $1,683,823 | +7.8% | -3.2% | $75,528 | 6+$137,264 | 2-$638,398 |
| 3 | PRATER DIRT WORK LLC | $1,759,351 | +12.7% | 1.1% | $15,337 | 5+$270,490 | 2-$483,190 |
| 4 | BIG CREEK CONSTRUCTION, LTD. | $1,774,687 | +13.6% | 2.0% | $445,951 | 2+$43,987 | 2-$388,190 |
| 5 | TEXAS MATERIALS GROUP, INC. | $2,220,638 | +42.2% | 27.6% | $178,547 | 3+$77,374 | 3-$340,649 |
| 6 | CK NEWBERRY, LLC | $2,399,186 | +53.6% | 37.9% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
JAY MILLS CONTRACTING, INCORPORATED vs LONE STAR PAVING COMPANY, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 351-7005 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") | 7,156 SY | $35.00 | $10.00 | $49.06 | -$178,900 |
| 316-7277 AGGR(TY-PB GR-4 OR TY-PB GR-4 MOD)SAC-B | 992 CY | $180.00 | $285.00 | $181.53 | $104,160 |
| 666-7542 RE PM TY III (W)6"(SLD)(PU) | 5,602 LF | $1.15 | $11.00 | $1.15 | $55,180 |
| 316-7007 ASPH (AC-20-5TR) | 37,094 GAL | $4.25 | $5.50 | $3.27 | $46,368 |
| 344-7065 SP MIXES SP-D SAC-B PG76-22 | 2,751 TON | $189.00 | $178.00 | $118.07 | -$30,261 |
| 666-7544 RE PM TY III (Y)6"(SLD)(PU) | 24,528 LF | $1.15 | $2.25 | $1.15 | $26,981 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $4,000.00 | $10,100.00 | $11,585.04 | $24,400 |
| 500-7001 MOBILIZATION | 1 LS | $150,000.00 | $165,000.00 | $523,850.32 | $15,000 |
| 506-7039 TEMP SEDMT CONT FENCE (INSTALL) | 4,600 LF | $3.95 | $7.00 | $3.92 | $14,030 |
| 506-7041 TEMP SEDMT CONT FENCE (REMOVE) | 4,600 LF | $0.4200 | $3.00 | $1.02 | $11,868 |
| 132-7005 EMBANK (FNL)(OC)(TY C) | 187.6 CY | $80.00 | $135.00 | $18.71 | $10,318 |
| 310-7004 PRIME COAT (MC-30) | 2,147 GAL | $7.00 | $10.00 | $5.35 | $6,441 |
| 420-7067 CL C CONC (MISC) | 161.6 CY | $865.00 | $900.00 | $1,569.38 | $5,656 |
| 644-7001 IN SM RD SN SUP&AM TY10BWG(1)SA(P) | 11 EA | $840.00 | $1,200.00 | $696.14 | $3,960 |
| 110-7002 EXCAV (CHANNEL) | 60 CY | $60.00 | $105.00 | $16.69 | $2,700 |
| 420-7148 CLASS K CONCRETE (MISC) | 2.7 CY | $2,500.00 | $1,600.00 | $1,507.23 | -$2,430 |
| 216-7001 PROOF ROLLING | 8 HR | $180.00 | $480.00 | $127.71 | $2,400 |
| 194-7008 RDSIDE AMENITY (WHEEL STOP REMOV&RESET) | 48 EA | $75.00 | $115.00 | $134.22 | $1,920 |
| 401-7001 FLOWABLE BACKFILL | 10.5 CY | $220.00 | $400.00 | $298.77 | $1,890 |
| 110-7003 EXCAV (SPECIAL) | 10.5 CY | $250.00 | $105.00 | $18.78 | -$1,523 |
Positive: the low bidder was cheaper on that item. These 20 items account for $120,158 of the $122,095 gap.
JAY MILLS CONTRACTING, INCORPORATED: unbalanced items
Placed 1LONE STAR PAVING COMPANY: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 666-7542 RE PM TY III (W)6"(SLD)(PU) | 5,602 LF | $11.00 | $1.15 | 9.57x | $55,180 |
| 666-7544 RE PM TY III (Y)6"(SLD)(PU) | 24,528 LF | $2.25 | $1.15 | 1.96x | $26,981 |
| 132-7005 EMBANK (FNL)(OC)(TY C) | 187.6 CY | $135.00 | $18.71 | 7.21x | $21,815 |
| 506-7039 TEMP SEDMT CONT FENCE (INSTALL) | 4,600 LF | $7.00 | $3.92 | 1.79x | $14,187 |
| 310-7004 PRIME COAT (MC-30) | 2,147 GAL | $10.00 | $5.35 | 1.87x | $9,990 |
| 506-7041 TEMP SEDMT CONT FENCE (REMOVE) | 4,600 LF | $3.00 | $1.02 | 2.94x | $9,111 |
| 500-7001 MOBILIZATION | 1 LS | $165,000.00 | $523,850.32 | 0.31x | -$358,850 |
| 351-7005 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") | 7,156 SY | $10.00 | $49.06 | 0.20x | -$279,548 |
PRATER DIRT WORK LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 316-7007 ASPH (AC-20-5TR) | 37,094 GAL | $7.90 | $3.27 | 2.42x | $171,793 |
| 666-7542 RE PM TY III (W)6"(SLD)(PU) | 5,602 LF | $10.10 | $1.15 | 8.78x | $50,138 |
| 666-7544 RE PM TY III (Y)6"(SLD)(PU) | 24,528 LF | $2.20 | $1.15 | 1.91x | $25,754 |
| 132-7005 EMBANK (FNL)(OC)(TY C) | 187.6 CY | $90.00 | $18.71 | 4.81x | $13,373 |
| 420-7148 CLASS K CONCRETE (MISC) | 2.7 CY | $5,000.00 | $1,507.23 | 3.32x | $9,430 |
| 500-7001 MOBILIZATION | 1 LS | $75,000.00 | $523,850.32 | 0.14x | -$448,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $3,000.00 | $11,585.04 | 0.26x | -$34,340 |
BIG CREEK CONSTRUCTION, LTD.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 132-7005 EMBANK (FNL)(OC)(TY C) | 187.6 CY | $200.00 | $18.71 | 10.69x | $34,009 |
| 529-7029 CONC CURB (TY I) (MOD) | 120 LF | $95.00 | $11.85 | 8.01x | $9,978 |
| 500-7001 MOBILIZATION | 1 LS | $170,000.00 | $523,850.32 | 0.32x | -$353,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $3,000.00 | $11,585.04 | 0.26x | -$34,340 |
TEXAS MATERIALS GROUP, INC.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 666-7542 RE PM TY III (W)6"(SLD)(PU) | 5,602 LF | $10.00 | $1.15 | 8.70x | $49,578 |
| 506-7039 TEMP SEDMT CONT FENCE (INSTALL) | 4,600 LF | $7.50 | $3.92 | 1.92x | $16,487 |
| 132-7005 EMBANK (FNL)(OC)(TY C) | 187.6 CY | $79.00 | $18.71 | 4.22x | $11,310 |
| 500-7001 MOBILIZATION | 1 LS | $221,000.00 | $523,850.32 | 0.42x | -$302,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $5,000.00 | $11,585.04 | 0.43x | -$26,340 |
| 310-7004 PRIME COAT (MC-30) | 2,147 GAL | $0.0100 | $5.35 | 0.00x | -$11,459 |