Bid Tab X-ray: 0151-02-026

May 6, 2026 · Burnet Sign up free
Set your company to personalize scores

SH 29 from RM 1174 to WILLIAMSON CO LINE

0151-02-026 · let May 6, 2026 · Burnet, Austin · Intersection & Operational Imprv

$10,910,072Low bid: TEXAS MATERIALS GROUP, INC.+0.9% vs estimate $10,815,462
$311,409Left on the table2.9% gap to the second bid
8BiddersSpread 35% low to high
169Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1TEXAS MATERIALS GROUP, INC. $10,910,0720.9% $311,409 4+$387,912 4-$1,465,372
2JOE BLAND CONSTRUCTION LLC $11,221,481+2.9%3.8% $1,160,691 3+$378,351 4-$1,606,278
3HUNTER INDUSTRIES, LTD. $12,382,171+13.5%14.5% $38,247 5+$976,124 2-$1,170,814
4ALLEN KELLER COMPANY $12,420,418+13.8%14.8% $338,715 6+$1,231,044 3-$940,854
5AARON CONCRETE CONTRACTORS, LLC $12,759,133+16.9%18.0% $98,888 6+$1,081,095 3-$1,011,578
6CAPITAL EXCAVATION COMPANY $12,858,021+17.9%18.9% $218,948
7ACME BRIDGE COMPANY, INC. $13,076,970+19.9%20.9% $1,620,382
8ICOS MANAGEMENT, LLC $14,697,351+34.7%35.9%

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.

Where the job was won

TEXAS MATERIALS GROUP, INC. vs JOE BLAND CONSTRUCTION LLC, biggest item swings
ItemQtyLow2ndMarket2nd minus low
500-7001 MOBILIZATION1 LS $665,000.00$225,000.00$523,850.32 -$440,000
432-7002 RIPRAP (CONC)(5 IN)1,392 CY $540.00$395.00$585.15 -$201,840
247-7179 FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS)20,123 CY $45.50$55.00$63.96 $191,169
530-7010 DRIVEWAYS (ACP)5,698 SY $87.00$55.00$54.96 -$182,336
105-7019 RMV (19"-23") TRT/UNTRT BASE & ASPH PAV21,095 SY $8.39$16.00$6.35 $160,533
341-7001 D-GR HMA TY-B PG64-2221,819 TON $93.00$100.00$97.82 $152,733
464-7003 RC PIPE (CL III)(18 IN)2,552 LF $61.00$115.00$83.08 $137,808
467-7308 SET (TY II) (18 IN) (RCP) (6: 1) (P)102 EA $1,050.00$2,250.00$1,176.76 $122,400
160-7002 FURN & PLACE TOPSOIL (4")58,779 SY $3.20$1.50$1.43 -$99,924
464-7005 RC PIPE (CL III)(24 IN)1,710 LF $79.00$135.00$108.34 $95,760
341-7056 D-GR HMA TY-D PG76-228,488 TON $113.00$124.00$123.11 $93,368
168-7001 VEGETATIVE WATERING2,941 TGL $35.00$4.00$8.43 -$91,171
466-7181 WINGWALL (PW - 1) (HW=11 FT)1 EA $154,000.00$65,000.00$55,052.17 -$89,000
347-7002 TOM-C PG76-22 SAC-B9,094 TON $136.00$145.00$130.62 $81,846
467-7328 SET (TY II) (24 IN) (RCP) (6: 1) (P)55 EA $1,390.00$2,750.00$1,883.43 $74,800
5061-7001 SUBSURFACE UTIL LOCATE (NON-PAVED AREA)50 EA $315.00$1,750.00$920.62 $71,750
100-7002 PREPARING ROW210.18 STA $496.00$775.00$6,072.92 $58,640
530-7002 INTERSECTIONS (ACP)1,364 SY $129.00$90.00$50.74 -$53,196
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING8 MO $1,500.00$7,250.00$11,585.04 $46,000
505-7003 TMA (MOBILE OPERATION)75 DAY $600.00$1,100.00$229.60 $37,500

Positive: the low bidder was cheaper on that item. These 20 items account for $166,839 of the $311,409 gap.

TEXAS MATERIALS GROUP, INC.: unbalanced items

Placed 1
ItemQtyTheir priceMarketx market$ vs market
530-7002 INTERSECTIONS (ACP)1,364 SY $129.00$50.742.54x$106,753
160-7002 FURN & PLACE TOPSOIL (4")58,779 SY $3.20$1.432.24x$104,080
466-7181 WINGWALL (PW - 1) (HW=11 FT)1 EA $154,000.00$55,052.172.80x$98,948
168-7001 VEGETATIVE WATERING2,941 TGL $35.00$8.434.15x$78,131
100-7002 PREPARING ROW210.18 STA $496.00$6,072.920.08x-$1,172,157
132-7003 EMBANK (FNL)(OC)(TY B)11,383 CY $5.05$16.960.30x-$135,609
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING8 MO $1,500.00$11,585.040.13x-$80,680
668-7137 PRFB RUMBLE STRIP (BLK)(1')(EDGELINE)41,108 LF $0.8100$2.680.30x-$76,925

JOE BLAND CONSTRUCTION LLC: unbalanced items

Placed 2
ItemQtyTheir priceMarketx market$ vs market
105-7019 RMV (19"-23") TRT/UNTRT BASE & ASPH PAV21,095 SY $16.00$6.352.52x$203,601
467-7308 SET (TY II) (18 IN) (RCP) (6: 1) (P)102 EA $2,250.00$1,176.761.91x$109,470
505-7003 TMA (MOBILE OPERATION)75 DAY $1,100.00$229.604.79x$65,280
100-7002 PREPARING ROW210.18 STA $775.00$6,072.920.13x-$1,113,517
500-7001 MOBILIZATION1 LS $225,000.00$523,850.320.43x-$298,850
132-7003 EMBANK (FNL)(OC)(TY B)11,383 CY $6.00$16.960.35x-$124,795
668-7137 PRFB RUMBLE STRIP (BLK)(1')(EDGELINE)41,108 LF $1.00$2.680.37x-$69,115

HUNTER INDUSTRIES, LTD.: unbalanced items

Placed 3
ItemQtyTheir priceMarketx market$ vs market
500-7001 MOBILIZATION1 LS $953,038.64$523,850.321.82x$429,188
105-7019 RMV (19"-23") TRT/UNTRT BASE & ASPH PAV21,095 SY $15.25$6.352.40x$187,779
110-7001 EXCAV (ROADWAY)19,011 CY $20.90$11.681.79x$175,240
466-7181 WINGWALL (PW - 1) (HW=11 FT)1 EA $160,000.00$55,052.172.91x$104,948
5061-7001 SUBSURFACE UTIL LOCATE (NON-PAVED AREA)50 EA $2,500.00$920.622.72x$78,969
100-7002 PREPARING ROW210.18 STA $854.70$6,072.920.14x-$1,096,766
668-7137 PRFB RUMBLE STRIP (BLK)(1')(EDGELINE)41,108 LF $0.8800$2.680.33x-$74,048

ALLEN KELLER COMPANY: unbalanced items

Placed 4
ItemQtyTheir priceMarketx market$ vs market
500-7001 MOBILIZATION1 LS $1,180,000.00$523,850.322.25x$656,150
110-7001 EXCAV (ROADWAY)19,011 CY $25.60$11.682.19x$264,591
662-7114 WK ZN PAV MRK SHT TERM (TAB)TY Y-228,376 EA $3.64$0.57156.37x$87,072
160-7002 FURN & PLACE TOPSOIL (4")58,779 SY $2.78$1.431.95x$79,393
168-7001 VEGETATIVE WATERING2,941 TGL $33.00$8.433.91x$72,249
530-7002 INTERSECTIONS (ACP)1,364 SY $103.22$50.742.03x$71,589
100-7002 PREPARING ROW210.18 STA $2,273.83$6,072.920.37x-$798,493
668-7137 PRFB RUMBLE STRIP (BLK)(1')(EDGELINE)41,108 LF $0.8100$2.680.30x-$76,925
466-7176 WINGWALL (PW - 1) (HW=6 FT)4 EA $13,159.28$29,518.270.45x-$65,436

AARON CONCRETE CONTRACTORS, LLC: unbalanced items

Placed 5
ItemQtyTheir priceMarketx market$ vs market
105-7019 RMV (19"-23") TRT/UNTRT BASE & ASPH PAV21,095 SY $23.00$6.353.62x$351,266
110-7001 EXCAV (ROADWAY)19,011 CY $28.00$11.682.40x$310,218
168-7001 VEGETATIVE WATERING2,941 TGL $55.00$8.436.52x$136,951
467-7308 SET (TY II) (18 IN) (RCP) (6: 1) (P)102 EA $2,405.00$1,176.762.04x$125,280
466-7181 WINGWALL (PW - 1) (HW=11 FT)1 EA $141,143.00$55,052.172.56x$86,091
530-7002 INTERSECTIONS (ACP)1,364 SY $103.00$50.742.03x$71,289
100-7002 PREPARING ROW210.18 STA $1,919.00$6,072.920.32x-$873,071
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING8 MO $2,911.00$11,585.040.25x-$69,392
668-7137 PRFB RUMBLE STRIP (BLK)(1')(EDGELINE)41,108 LF $1.00$2.680.37x-$69,115