SH 29 from RM 1174 to WILLIAMSON CO LINE
0151-02-026 · let May 6, 2026 · Burnet, Austin · Intersection & Operational Imprv
$10,910,072Low bid: TEXAS MATERIALS GROUP, INC.+0.9% vs estimate $10,815,462
$311,409Left on the table2.9% gap to the second bid
8BiddersSpread 35% low to high
169Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | TEXAS MATERIALS GROUP, INC. | $10,910,072 | 0.9% | $311,409 | 4+$387,912 | 4-$1,465,372 | |
| 2 | JOE BLAND CONSTRUCTION LLC | $11,221,481 | +2.9% | 3.8% | $1,160,691 | 3+$378,351 | 4-$1,606,278 |
| 3 | HUNTER INDUSTRIES, LTD. | $12,382,171 | +13.5% | 14.5% | $38,247 | 5+$976,124 | 2-$1,170,814 |
| 4 | ALLEN KELLER COMPANY | $12,420,418 | +13.8% | 14.8% | $338,715 | 6+$1,231,044 | 3-$940,854 |
| 5 | AARON CONCRETE CONTRACTORS, LLC | $12,759,133 | +16.9% | 18.0% | $98,888 | 6+$1,081,095 | 3-$1,011,578 |
| 6 | CAPITAL EXCAVATION COMPANY | $12,858,021 | +17.9% | 18.9% | $218,948 | ||
| 7 | ACME BRIDGE COMPANY, INC. | $13,076,970 | +19.9% | 20.9% | $1,620,382 | ||
| 8 | ICOS MANAGEMENT, LLC | $14,697,351 | +34.7% | 35.9% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
TEXAS MATERIALS GROUP, INC. vs JOE BLAND CONSTRUCTION LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $665,000.00 | $225,000.00 | $523,850.32 | -$440,000 |
| 432-7002 RIPRAP (CONC)(5 IN) | 1,392 CY | $540.00 | $395.00 | $585.15 | -$201,840 |
| 247-7179 FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS) | 20,123 CY | $45.50 | $55.00 | $63.96 | $191,169 |
| 530-7010 DRIVEWAYS (ACP) | 5,698 SY | $87.00 | $55.00 | $54.96 | -$182,336 |
| 105-7019 RMV (19"-23") TRT/UNTRT BASE & ASPH PAV | 21,095 SY | $8.39 | $16.00 | $6.35 | $160,533 |
| 341-7001 D-GR HMA TY-B PG64-22 | 21,819 TON | $93.00 | $100.00 | $97.82 | $152,733 |
| 464-7003 RC PIPE (CL III)(18 IN) | 2,552 LF | $61.00 | $115.00 | $83.08 | $137,808 |
| 467-7308 SET (TY II) (18 IN) (RCP) (6: 1) (P) | 102 EA | $1,050.00 | $2,250.00 | $1,176.76 | $122,400 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 58,779 SY | $3.20 | $1.50 | $1.43 | -$99,924 |
| 464-7005 RC PIPE (CL III)(24 IN) | 1,710 LF | $79.00 | $135.00 | $108.34 | $95,760 |
| 341-7056 D-GR HMA TY-D PG76-22 | 8,488 TON | $113.00 | $124.00 | $123.11 | $93,368 |
| 168-7001 VEGETATIVE WATERING | 2,941 TGL | $35.00 | $4.00 | $8.43 | -$91,171 |
| 466-7181 WINGWALL (PW - 1) (HW=11 FT) | 1 EA | $154,000.00 | $65,000.00 | $55,052.17 | -$89,000 |
| 347-7002 TOM-C PG76-22 SAC-B | 9,094 TON | $136.00 | $145.00 | $130.62 | $81,846 |
| 467-7328 SET (TY II) (24 IN) (RCP) (6: 1) (P) | 55 EA | $1,390.00 | $2,750.00 | $1,883.43 | $74,800 |
| 5061-7001 SUBSURFACE UTIL LOCATE (NON-PAVED AREA) | 50 EA | $315.00 | $1,750.00 | $920.62 | $71,750 |
| 100-7002 PREPARING ROW | 210.18 STA | $496.00 | $775.00 | $6,072.92 | $58,640 |
| 530-7002 INTERSECTIONS (ACP) | 1,364 SY | $129.00 | $90.00 | $50.74 | -$53,196 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $1,500.00 | $7,250.00 | $11,585.04 | $46,000 |
| 505-7003 TMA (MOBILE OPERATION) | 75 DAY | $600.00 | $1,100.00 | $229.60 | $37,500 |
Positive: the low bidder was cheaper on that item. These 20 items account for $166,839 of the $311,409 gap.
TEXAS MATERIALS GROUP, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 530-7002 INTERSECTIONS (ACP) | 1,364 SY | $129.00 | $50.74 | 2.54x | $106,753 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 58,779 SY | $3.20 | $1.43 | 2.24x | $104,080 |
| 466-7181 WINGWALL (PW - 1) (HW=11 FT) | 1 EA | $154,000.00 | $55,052.17 | 2.80x | $98,948 |
| 168-7001 VEGETATIVE WATERING | 2,941 TGL | $35.00 | $8.43 | 4.15x | $78,131 |
| 100-7002 PREPARING ROW | 210.18 STA | $496.00 | $6,072.92 | 0.08x | -$1,172,157 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 11,383 CY | $5.05 | $16.96 | 0.30x | -$135,609 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $1,500.00 | $11,585.04 | 0.13x | -$80,680 |
| 668-7137 PRFB RUMBLE STRIP (BLK)(1')(EDGELINE) | 41,108 LF | $0.8100 | $2.68 | 0.30x | -$76,925 |
JOE BLAND CONSTRUCTION LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 105-7019 RMV (19"-23") TRT/UNTRT BASE & ASPH PAV | 21,095 SY | $16.00 | $6.35 | 2.52x | $203,601 |
| 467-7308 SET (TY II) (18 IN) (RCP) (6: 1) (P) | 102 EA | $2,250.00 | $1,176.76 | 1.91x | $109,470 |
| 505-7003 TMA (MOBILE OPERATION) | 75 DAY | $1,100.00 | $229.60 | 4.79x | $65,280 |
| 100-7002 PREPARING ROW | 210.18 STA | $775.00 | $6,072.92 | 0.13x | -$1,113,517 |
| 500-7001 MOBILIZATION | 1 LS | $225,000.00 | $523,850.32 | 0.43x | -$298,850 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 11,383 CY | $6.00 | $16.96 | 0.35x | -$124,795 |
| 668-7137 PRFB RUMBLE STRIP (BLK)(1')(EDGELINE) | 41,108 LF | $1.00 | $2.68 | 0.37x | -$69,115 |
HUNTER INDUSTRIES, LTD.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $953,038.64 | $523,850.32 | 1.82x | $429,188 |
| 105-7019 RMV (19"-23") TRT/UNTRT BASE & ASPH PAV | 21,095 SY | $15.25 | $6.35 | 2.40x | $187,779 |
| 110-7001 EXCAV (ROADWAY) | 19,011 CY | $20.90 | $11.68 | 1.79x | $175,240 |
| 466-7181 WINGWALL (PW - 1) (HW=11 FT) | 1 EA | $160,000.00 | $55,052.17 | 2.91x | $104,948 |
| 5061-7001 SUBSURFACE UTIL LOCATE (NON-PAVED AREA) | 50 EA | $2,500.00 | $920.62 | 2.72x | $78,969 |
| 100-7002 PREPARING ROW | 210.18 STA | $854.70 | $6,072.92 | 0.14x | -$1,096,766 |
| 668-7137 PRFB RUMBLE STRIP (BLK)(1')(EDGELINE) | 41,108 LF | $0.8800 | $2.68 | 0.33x | -$74,048 |
ALLEN KELLER COMPANY: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $1,180,000.00 | $523,850.32 | 2.25x | $656,150 |
| 110-7001 EXCAV (ROADWAY) | 19,011 CY | $25.60 | $11.68 | 2.19x | $264,591 |
| 662-7114 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 | 28,376 EA | $3.64 | $0.5715 | 6.37x | $87,072 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 58,779 SY | $2.78 | $1.43 | 1.95x | $79,393 |
| 168-7001 VEGETATIVE WATERING | 2,941 TGL | $33.00 | $8.43 | 3.91x | $72,249 |
| 530-7002 INTERSECTIONS (ACP) | 1,364 SY | $103.22 | $50.74 | 2.03x | $71,589 |
| 100-7002 PREPARING ROW | 210.18 STA | $2,273.83 | $6,072.92 | 0.37x | -$798,493 |
| 668-7137 PRFB RUMBLE STRIP (BLK)(1')(EDGELINE) | 41,108 LF | $0.8100 | $2.68 | 0.30x | -$76,925 |
| 466-7176 WINGWALL (PW - 1) (HW=6 FT) | 4 EA | $13,159.28 | $29,518.27 | 0.45x | -$65,436 |
AARON CONCRETE CONTRACTORS, LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 105-7019 RMV (19"-23") TRT/UNTRT BASE & ASPH PAV | 21,095 SY | $23.00 | $6.35 | 3.62x | $351,266 |
| 110-7001 EXCAV (ROADWAY) | 19,011 CY | $28.00 | $11.68 | 2.40x | $310,218 |
| 168-7001 VEGETATIVE WATERING | 2,941 TGL | $55.00 | $8.43 | 6.52x | $136,951 |
| 467-7308 SET (TY II) (18 IN) (RCP) (6: 1) (P) | 102 EA | $2,405.00 | $1,176.76 | 2.04x | $125,280 |
| 466-7181 WINGWALL (PW - 1) (HW=11 FT) | 1 EA | $141,143.00 | $55,052.17 | 2.56x | $86,091 |
| 530-7002 INTERSECTIONS (ACP) | 1,364 SY | $103.00 | $50.74 | 2.03x | $71,289 |
| 100-7002 PREPARING ROW | 210.18 STA | $1,919.00 | $6,072.92 | 0.32x | -$873,071 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $2,911.00 | $11,585.04 | 0.25x | -$69,392 |
| 668-7137 PRFB RUMBLE STRIP (BLK)(1')(EDGELINE) | 41,108 LF | $1.00 | $2.68 | 0.37x | -$69,115 |