FM 974 F: FM 2776 T: south - FY 27
0540-03-039 · let Jul 1, 2026 · Brazos, Bryan · Safety Improvement Projects
$3,771,592Low bid: BIG CREEK CONSTRUCTION, LTD.-12.6% vs estimate $4,315,846
$500,884Left on the table13.3% gap to the second bid
8BiddersSpread 67% low to high
77Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | BIG CREEK CONSTRUCTION, LTD. | $3,771,592 | -12.6% | $500,884 | 0 | 4-$1,099,157 | |
| 2 | KNIFE RIVER CORPORATION - SOUTH | $4,272,476 | +13.3% | -1.0% | $13,062 | 1+$206,122 | 7-$1,366,762 |
| 3 | LARRY YOUNG PAVING, INC. | $4,285,538 | +13.6% | -0.7% | $98,945 | 1+$24,341 | 5-$1,335,361 |
| 4 | BRAZOS PAVING, INC. | $4,384,483 | +16.3% | 1.6% | $1,015,641 | 2+$46,640 | 5-$1,399,406 |
| 5 | TEXAS MATERIALS GROUP, INC. | $5,400,124 | +43.2% | 25.1% | $117,808 | 5+$1,397,352 | 3-$1,152,975 |
| 6 | CLARK CONSTRUCTION OF TEXAS, INC. | $5,517,932 | +46.3% | 27.9% | $147,171 | ||
| 7 | STX CIVIL | $5,665,104 | +50.2% | 31.3% | $646,748 | ||
| 8 | A. L. HELMCAMP, INC. | $6,311,852 | +67.4% | 46.2% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
BIG CREEK CONSTRUCTION, LTD. vs KNIFE RIVER CORPORATION - SOUTH, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 530-7016 DRIVEWAYS (SURF TREAT) | 2,279 SY | $25.00 | $125.00 | $34.56 | $227,900 |
| 247-7090 FL BS (CMP IN PLC)(TY A GR 1-2) (10") | 52,999 SY | $23.00 | $27.00 | $18.50 | $211,996 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 15 MO | $3,000.00 | $13,000.00 | $11,585.04 | $150,000 |
| 275-7004 CEMENT TRT (EXIST MATL)(10") | 60,066 SY | $2.50 | $1.25 | $3.71 | -$75,083 |
| 251-7027 REWORK BS MTL (TY B)(8")(ORD COMP) | 42,405 SY | $3.00 | $1.25 | $3.97 | -$74,209 |
| 500-7001 MOBILIZATION | 1 LS | $275,000.00 | $339,069.00 | $523,850.32 | $64,069 |
| 100-7002 PREPARING ROW | 159 STA | $750.00 | $370.00 | $6,072.92 | -$60,420 |
| 316-7241 AGGR (TY-PB OR PL, GR-4)(SAC-A) | 853 CY | $160.00 | $227.00 | $180.75 | $57,151 |
| 110-7001 EXCAV (ROADWAY) | 11,856.4 CY | $15.00 | $12.00 | $11.68 | -$35,569 |
| 316-7251 AGGR (TY-B OR L, GR-5) | 406 CY | $105.00 | $180.00 | $136.70 | $30,450 |
| 316-7007 ASPH (AC-20-5TR) | 41,335 GAL | $3.75 | $4.45 | $3.27 | $28,935 |
| 134-7004 BACKFILL (TY A OR B) | 159 STA | $225.00 | $75.00 | $211.21 | -$23,850 |
| 275-7001 CEMENT | 853 TON | $225.00 | $199.00 | $224.93 | -$22,178 |
| 168-7001 VEGETATIVE WATERING | 426 TGL | $10.00 | $58.00 | $8.43 | $20,448 |
| 530-7010 DRIVEWAYS (ACP) | 490 SY | $45.00 | $85.00 | $54.96 | $19,600 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 103 CY | $650.00 | $800.00 | $616.83 | $15,450 |
| 530-7006 DRIVEWAYS (CONC) | 87 SY | $150.00 | $300.00 | $109.20 | $13,050 |
| 496-7004 REMOV STR (SET) | 62 EA | $500.00 | $300.00 | $514.07 | -$12,400 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 2 EA | $10,000.00 | $5,000.00 | $9,253.78 | -$10,000 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 2,424.9 CY | $15.00 | $11.00 | $13.19 | -$9,700 |
Positive: the low bidder was cheaper on that item. These 20 items account for $515,640 of the $500,884 gap.
BIG CREEK CONSTRUCTION, LTD.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 159 STA | $750.00 | $6,072.92 | 0.12x | -$846,344 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 15 MO | $3,000.00 | $11,585.04 | 0.26x | -$128,776 |
| 668-7137 PRFB RUMBLE STRIP (BLK)(1')(EDGELINE) | 31,436 LF | $0.1000 | $2.68 | 0.04x | -$81,146 |
| 668-7002 PRFB RUMBLE STRIP (BLK)(1')(CENTERLINE) | 15,898 LF | $0.1000 | $2.80 | 0.04x | -$42,891 |
KNIFE RIVER CORPORATION - SOUTH: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 530-7016 DRIVEWAYS (SURF TREAT) | 2,279 SY | $125.00 | $34.56 | 3.62x | $206,122 |
| 100-7002 PREPARING ROW | 159 STA | $370.00 | $6,072.92 | 0.06x | -$906,764 |
| 275-7004 CEMENT TRT (EXIST MATL)(10") | 60,066 SY | $1.25 | $3.71 | 0.34x | -$147,546 |
| 251-7027 REWORK BS MTL (TY B)(8")(ORD COMP) | 42,405 SY | $1.25 | $3.97 | 0.31x | -$115,477 |
| 668-7137 PRFB RUMBLE STRIP (BLK)(1')(EDGELINE) | 31,436 LF | $0.1000 | $2.68 | 0.04x | -$81,146 |
| 260-7008 LIME TRT (EXIST MATL)(10") | 15,015 SY | $2.50 | $5.92 | 0.42x | -$51,279 |
| 668-7002 PRFB RUMBLE STRIP (BLK)(1')(CENTERLINE) | 15,898 LF | $0.1000 | $2.80 | 0.04x | -$42,891 |
| 134-7004 BACKFILL (TY A OR B) | 159 STA | $75.00 | $211.21 | 0.36x | -$21,657 |
LARRY YOUNG PAVING, INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 666-7411 REFL PAV MRK TY I (W)6"(SLD)(100MIL) | 31,436 LF | $1.25 | $0.4757 | 2.63x | $24,341 |
| 100-7002 PREPARING ROW | 159 STA | $380.00 | $6,072.92 | 0.06x | -$905,174 |
| 500-7001 MOBILIZATION | 1 LS | $250,000.00 | $523,850.32 | 0.48x | -$273,850 |
| 668-7137 PRFB RUMBLE STRIP (BLK)(1')(EDGELINE) | 31,436 LF | $0.2500 | $2.68 | 0.09x | -$76,430 |
| 668-7002 PRFB RUMBLE STRIP (BLK)(1')(CENTERLINE) | 15,898 LF | $0.2500 | $2.80 | 0.09x | -$40,507 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 42,397 SY | $0.5000 | $1.43 | 0.35x | -$39,400 |
BRAZOS PAVING, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 168-7001 VEGETATIVE WATERING | 426 TGL | $65.00 | $8.43 | 7.71x | $24,097 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 2 EA | $20,525.00 | $9,253.78 | 2.22x | $22,542 |
| 100-7002 PREPARING ROW | 159 STA | $690.00 | $6,072.92 | 0.11x | -$855,884 |
| 500-7001 MOBILIZATION | 1 LS | $193,720.00 | $523,850.32 | 0.37x | -$330,130 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 15 MO | $2,472.50 | $11,585.04 | 0.21x | -$136,688 |
| 668-7137 PRFB RUMBLE STRIP (BLK)(1')(EDGELINE) | 31,436 LF | $1.10 | $2.68 | 0.41x | -$49,710 |
| 668-7002 PRFB RUMBLE STRIP (BLK)(1')(CENTERLINE) | 15,898 LF | $1.10 | $2.80 | 0.39x | -$26,993 |
TEXAS MATERIALS GROUP, INC.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 247-7090 FL BS (CMP IN PLC)(TY A GR 1-2) (10") | 52,999 SY | $34.50 | $18.50 | 1.87x | $848,154 |
| 110-7001 EXCAV (ROADWAY) | 11,856.4 CY | $37.00 | $11.68 | 3.17x | $300,178 |
| 530-7016 DRIVEWAYS (SURF TREAT) | 2,279 SY | $102.00 | $34.56 | 2.95x | $153,705 |
| 505-7001 TMA (STATIONARY) | 218 DAY | $450.00 | $217.57 | 2.07x | $50,669 |
| 134-7004 BACKFILL (TY A OR B) | 159 STA | $492.00 | $211.21 | 2.33x | $44,646 |
| 100-7002 PREPARING ROW | 159 STA | $545.00 | $6,072.92 | 0.09x | -$878,939 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 15 MO | $950.00 | $11,585.04 | 0.08x | -$159,526 |
| 275-7004 CEMENT TRT (EXIST MATL)(10") | 60,066 SY | $1.80 | $3.71 | 0.49x | -$114,510 |