Rehab EX RD | FT PARKER STATE PARK |
0625-01-001 · let Jul 2, 2026 · Limestone, Waco · Rehabilitation of Existing Road
$1,849,328Low bid: BIG CREEK CONSTRUCTION, LTD.-14.0% vs estimate $2,150,633
$29,531Left on the table1.6% gap to the second bid
6BiddersSpread 87% low to high
65Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | BIG CREEK CONSTRUCTION, LTD. | $1,849,328 | -14.0% | $29,531 | 2+$24,406 | 4-$555,069 | |
| 2 | TEXAS MATERIALS GROUP, INC. | $1,878,858 | +1.6% | -12.6% | $479,383 | 0 | 4-$552,674 |
| 3 | KNIFE RIVER CORPORATION - SOUTH | $2,358,241 | +27.5% | 9.7% | $301,579 | 4+$102,720 | 4-$463,875 |
| 4 | PRATER DIRT WORK LLC | $2,659,820 | +43.8% | 23.7% | $132,179 | 7+$237,067 | 3-$374,367 |
| 5 | JOE BLAND CONSTRUCTION LLC | $2,791,999 | +51.0% | 29.8% | $672,816 | 6+$497,996 | 3-$528,573 |
| 6 | A. L. HELMCAMP, INC. | $3,464,815 | +87.4% | 61.1% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
BIG CREEK CONSTRUCTION, LTD. vs TEXAS MATERIALS GROUP, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 344-7021 SP MIXES SP-C SAC-B PG70-22 | 6,408 TON | $110.00 | $125.00 | $120.21 | $96,120 |
| 275-7031 CEMENT TRT (EXIST MATL)(5") | 23,296 SY | $2.75 | $1.60 | $2.75 | -$26,790 |
| 480-7001 CLEAN EXIST CULVERTS | 14 EA | $1,000.00 | $2,000.00 | $1,712.97 | $14,000 |
| 500-7001 MOBILIZATION | 1 LS | $120,000.00 | $133,110.00 | $523,850.32 | $13,110 |
| 531-7027 FIXED BOLLARD | 28 EA | $1,200.00 | $800.00 | $1,113.43 | -$11,200 |
| 134-7005 BACKFILL (TY A)(VEH) | 605 CY | $50.00 | $33.00 | $55.07 | -$10,285 |
| 251-7049 REWORK BS MTL (TY C)(6")(ORD COMP) | 23,296 SY | $1.50 | $1.10 | $2.17 | -$9,318 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 2 EA | $10,000.00 | $5,500.00 | $9,253.78 | -$9,000 |
| 105-7028 RMV (8") TRT/UNTRT BASE & ASPH PAV | 2,600 SY | $11.00 | $8.20 | $5.21 | -$7,280 |
| 505-7001 TMA (STATIONARY) | 34 DAY | $250.00 | $91.00 | $217.57 | -$5,406 |
| 132-7018 EMBANK (VEH)(DC)(TY C) | 192 CY | $65.00 | $38.00 | $16.31 | -$5,184 |
| 506-7039 TEMP SEDMT CONT FENCE (INSTALL) | 6,180 LF | $3.25 | $4.00 | $3.92 | $4,635 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 9 MO | $1,500.00 | $1,002.00 | $11,585.04 | -$4,482 |
| 423-7013 RETAINING WALL (CONC BLOCK) | 295 SF | $65.00 | $79.69 | $52.00 | $4,334 |
| 556-7012 PIPE UNDERDRAINS (TY 6)(4") | 165 LF | $65.00 | $40.00 | $65.00 | -$4,125 |
| 194-7011 RDSIDE AMENITY | 2 EA | $450.00 | $2,500.00 | $4,594.44 | $4,100 |
| 505-7003 TMA (MOBILE OPERATION) | 9 DAY | $400.00 | $1.00 | $229.60 | -$3,591 |
| 3006-7001 UNDERSEAL COURSE | 13,925 GAL | $4.50 | $4.25 | $3.65 | -$3,481 |
| 496-7042 REMOV STR (WOOD STR) | 3,473 LF | $4.50 | $3.55 | $10.43 | -$3,299 |
| 496-7025 REMOV STR (RR TIMBER TIES) | 18 EA | $300.00 | $137.00 | $2,514.29 | -$2,934 |
Positive: the low bidder was cheaper on that item. These 20 items account for $29,922 of the $29,531 gap.
BIG CREEK CONSTRUCTION, LTD.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 105-7028 RMV (8") TRT/UNTRT BASE & ASPH PAV | 2,600 SY | $11.00 | $5.21 | 2.11x | $15,058 |
| 132-7018 EMBANK (VEH)(DC)(TY C) | 192 CY | $65.00 | $16.31 | 3.98x | $9,348 |
| 500-7001 MOBILIZATION | 1 LS | $120,000.00 | $523,850.32 | 0.23x | -$403,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 9 MO | $1,500.00 | $11,585.04 | 0.13x | -$90,765 |
| 496-7025 REMOV STR (RR TIMBER TIES) | 18 EA | $300.00 | $2,514.29 | 0.12x | -$39,857 |
| 496-7042 REMOV STR (WOOD STR) | 3,473 LF | $4.50 | $10.43 | 0.43x | -$20,596 |
TEXAS MATERIALS GROUP, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $133,110.00 | $523,850.32 | 0.25x | -$390,740 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 9 MO | $1,002.00 | $11,585.04 | 0.09x | -$95,247 |
| 496-7025 REMOV STR (RR TIMBER TIES) | 18 EA | $137.00 | $2,514.29 | 0.05x | -$42,791 |
| 496-7042 REMOV STR (WOOD STR) | 3,473 LF | $3.55 | $10.43 | 0.34x | -$23,895 |
KNIFE RIVER CORPORATION - SOUTH: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 134-7005 BACKFILL (TY A)(VEH) | 605 CY | $150.00 | $55.07 | 2.72x | $57,436 |
| 351-7005 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") | 500 SY | $89.35 | $49.06 | 1.82x | $20,143 |
| 423-7013 RETAINING WALL (CONC BLOCK) | 295 SF | $95.00 | $52.00 | 1.83x | $12,684 |
| 105-7028 RMV (8") TRT/UNTRT BASE & ASPH PAV | 2,600 SY | $10.00 | $5.21 | 1.92x | $12,458 |
| 500-7001 MOBILIZATION | 1 LS | $194,385.00 | $523,850.32 | 0.37x | -$329,465 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 9 MO | $3,550.00 | $11,585.04 | 0.31x | -$72,315 |
| 496-7025 REMOV STR (RR TIMBER TIES) | 18 EA | $60.00 | $2,514.29 | 0.02x | -$44,177 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 2 EA | $295.00 | $9,253.78 | 0.03x | -$17,918 |
PRATER DIRT WORK LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 275-7031 CEMENT TRT (EXIST MATL)(5") | 23,296 SY | $7.00 | $2.75 | 2.55x | $99,008 |
| 194-7025 RDSIDE AMENITY (REMOV) | 28 EA | $1,500.00 | $302.07 | 4.97x | $33,542 |
| 194-7011 RDSIDE AMENITY | 2 EA | $20,000.00 | $4,594.44 | 4.35x | $30,811 |
| 132-7018 EMBANK (VEH)(DC)(TY C) | 192 CY | $150.00 | $16.31 | 9.20x | $25,668 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 2 EA | $18,000.00 | $9,253.78 | 1.95x | $17,492 |
| 110-7001 EXCAV (ROADWAY) | 89 CY | $200.00 | $11.68 | 17.12x | $16,760 |
| 432-7004 RIPRAP (CONC)(CL A) | 36 CY | $852.00 | $469.09 | 1.82x | $13,785 |
| 500-7001 MOBILIZATION | 1 LS | $210,000.00 | $523,850.32 | 0.40x | -$313,850 |
| 496-7025 REMOV STR (RR TIMBER TIES) | 18 EA | $200.00 | $2,514.29 | 0.08x | -$41,657 |
| 496-7042 REMOV STR (WOOD STR) | 3,473 LF | $5.00 | $10.43 | 0.48x | -$18,859 |
JOE BLAND CONSTRUCTION LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 275-7031 CEMENT TRT (EXIST MATL)(5") | 23,296 SY | $14.00 | $2.75 | 5.09x | $262,080 |
| 105-7028 RMV (8") TRT/UNTRT BASE & ASPH PAV | 2,600 SY | $32.00 | $5.21 | 6.14x | $69,658 |
| 251-7049 REWORK BS MTL (TY C)(6")(ORD COMP) | 23,296 SY | $5.00 | $2.17 | 2.31x | $65,949 |
| 275-7001 CEMENT | 176 TON | $450.00 | $224.93 | 2.00x | $39,612 |
| 432-7004 RIPRAP (CONC)(CL A) | 36 CY | $1,400.00 | $469.09 | 2.98x | $33,513 |
| 134-7005 BACKFILL (TY A)(VEH) | 605 CY | $100.00 | $55.07 | 1.82x | $27,186 |
| 500-7001 MOBILIZATION | 1 LS | $125,000.00 | $523,850.32 | 0.24x | -$398,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 9 MO | $1,500.00 | $11,585.04 | 0.13x | -$90,765 |
| 496-7025 REMOV STR (RR TIMBER TIES) | 18 EA | $350.00 | $2,514.29 | 0.14x | -$38,957 |