Flexible Pavement Str Repair 0826
6496-74-001 · let Aug 12, 2026 · Navarro, Dallas · Routine Maintenance Project - Sealed
$955,633Low bid: TEXAS MATERIALS GROUP, INC.-3.6% vs estimate $991,443
$23,076Left on the table2.4% gap to the second bid
4BiddersSpread 97% low to high
10Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | TEXAS MATERIALS GROUP, INC. | $955,633 | -3.6% | $23,076 | 1+$399,419 | 2-$536,170 | |
| 2 | BIG CREEK CONSTRUCTION, LTD. | $978,709 | +2.4% | -1.3% | $104,170 | 1+$417,419 | 1-$503,850 |
| 3 | KNIFE RIVER CORPORATION - SOUTH | $1,082,879 | +13.3% | 9.2% | $803,270 | 1+$445,019 | 1-$451,558 |
| 4 | PEACHTREE CONSTRUCTION, LTD. | $1,886,149 | +97.4% | 90.2% | 3+$1,248,330 | 1-$398,850 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
TEXAS MATERIALS GROUP, INC. vs BIG CREEK CONSTRUCTION, LTD., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $1,625.00 | $12,000.00 | $11,585.04 | $20,750 |
| 344-7021 SP MIXES SP-C SAC-B PG70-22 | 1,198 TON | $155.70 | $140.00 | $120.21 | -$18,809 |
| 354-7004 PLANE & TEXT ASPH CONC PAV(0" TO 4") | 6,258 SY | $8.00 | $5.00 | $4.74 | -$18,774 |
| 351-7029 FLEXIBLE PAV STR REPAIR 12" -TYPICAL E | 12,000 SY | $58.50 | $60.00 | $25.22 | $18,000 |
| 500-7001 MOBILIZATION | 1 LS | $7,600.00 | $20,000.00 | $523,850.32 | $12,400 |
| 505-7001 TMA (STATIONARY) | 25 DAY | $85.00 | $300.00 | $217.57 | $5,375 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 24 DAY | $32.00 | $170.00 | $87.82 | $3,312 |
| 344-7077 TACK COAT | 689 GAL | $3.80 | $4.50 | $3.25 | $482 |
| 662-7113 WK ZN PAV MRK SHT TERM (TAB)TY Y | 639 EA | $1.00 | $1.50 | $1.11 | $320 |
| 662-7112 WK ZN PAV MRK SHT TERM (TAB)TY W | 40 EA | $1.00 | $1.50 | $1.03 | $20 |
Positive: the low bidder was cheaper on that item. These 10 items account for $23,076 of the $23,076 gap.
TEXAS MATERIALS GROUP, INC.: unbalanced items
Placed 1BIG CREEK CONSTRUCTION, LTD.: unbalanced items
Placed 2KNIFE RIVER CORPORATION - SOUTH: unbalanced items
Placed 3PEACHTREE CONSTRUCTION, LTD.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 351-7029 FLEXIBLE PAV STR REPAIR 12" -TYPICAL E | 12,000 SY | $116.50 | $25.22 | 4.62x | $1,095,419 |
| 344-7021 SP MIXES SP-C SAC-B PG70-22 | 1,198 TON | $217.75 | $120.21 | 1.81x | $116,854 |
| 354-7004 PLANE & TEXT ASPH CONC PAV(0" TO 4") | 6,258 SY | $10.50 | $4.74 | 2.22x | $36,057 |
| 500-7001 MOBILIZATION | 1 LS | $125,000.00 | $523,850.32 | 0.24x | -$398,850 |