Bid Day Forecast: 6512-48-001

Terrell · Dec 8, 2026 Sign up free
Set your company to personalize scores

Routine Maintenance Project

CCSJ 6512-48-001 · lets Dec 8, 2026 · Terrell, Odessa · US0090

$106,560Engineer's estimate Items at market: $56,466 (-47.0%)
$101,518Most likely low bid$93,152 to $108,503 (middle half)
2.5Expected bidders4 plan holders, 3 regular bidders
78/100Strong fit: bid itMarket only. Set your company for a personal score

Where the low bid should land

$77,073 (1 in 10 go lower)$111,812 (1 in 10 go higher)

From 52 comparable let jobs (district, estimates of $42,624 to $266,400, last 3 years). 67% of them went under the estimate; the typical low bid was -4.7% vs estimate.

Bid / no-bid score

  • Competition25 / 25Jobs like this draw about 2.5 bidders.
  • Margin10 / 20Low bids land at 95% of the estimate.

Set your company to add your experience, win rate and size fit.

Comparable jobs

Oct 2026 6509-64-001Ector · 2 bidders $159,798-4.9%
Aug 2026 6505-33-001Midland · 2 bidders $78,720-4.6%
Aug 2026 6505-34-001Ector · 2 bidders $60,720-8.0%
Aug 2026 6506-41-001Pecos · 3 bidders $103,000-4.2%
Jun 2026 6501-38-001Ector · 2 bidders $254,624-1.1%
Jun 2026 6503-23-001Midland · 4 bidders $22,987-58.0%
Jun 2026 6503-68-001Midland · 1 bidders $249,128+4.5%
May 2026 6501-27-001Midland · 1 bidders $59,250+6.2%

The field: plan holders and how they bid

Last 3 years in Texas
Plan holderBidsWinsIn OdessaAvg bid vs est.Avg win vs est.Their typical bid here
LUKEDA SANDBLASTING & SERVICES LLC SharpestBidders 16124 of 5 -19.3%-23.0% $86,022
THOMAS 11 DEVELOPMENT LLCBidders 81 7.6%-29.1% $114,697
ADVANCED BARRICADES OF AMERICA, LLCBidders 141 17.1%-23.8% $124,806
TS CONSTRUCTION AND HEAVY EQUIPMENTBidders 00

"Typical bid here" is the estimate times that contractor's average bid ratio. Plan holders with no bids are usually suppliers or subs.

Items that decide this job

9 of 12 items priced from low bids
ItemQtyMarket priceRange of low bidsAt marketShare
745-7001 JANITORIAL MAINT - PICNIC AREA-SITE (1)4 low bids · prices swing 10x 104 CYC$204.92$86.50 – $900.00 $21,31237.7%
7012-7038 LITTER PICKUP - SITE 12 low bids 104 CYC$70.76$70.76 – $70.76 $7,35913.0%
7012-7039 LITTER PICKUP - SITE 22 low bids 104 CYC$68.88$68.88 – $68.88 $7,16412.7%
7012-7040 LITTER PICKUP - SITE 32 low bids 104 CYC$55.46$55.46 – $55.46 $5,76810.2%
745-7002 JANITORIAL MAINT - PICNIC AREA-SITE (2)2 low bids 104 CYC$54.50$54.50 – $54.50 $5,66810.0%
745-7003 JANITORIAL MAINT - PICNIC AREA-SITE (3)1 low bids 104 CYC$50.00$50.00 – $50.00 $5,2009.2%
745-7020 GROUNDS MAINT - PICNIC MOW/TRIM-SITE(1)5 low bids · prices swing 9x 8 CYC$266.27$112.52 – $1,000.00 $2,1303.8%
745-7022 GROUNDS MAINT - PICNIC MOW/TRIM-SITE(3)3 low bids · prices swing 6x 8 CYC$123.86$49.00 – $300.00 $9911.8%
745-7021 GROUNDS MAINT - PICNIC MOW/TRIM-SITE(2)5 low bids 8 CYC$109.31$81.00 – $200.00 $8741.5%