6506-41-001 ASPPM
6506-41-001 · let Aug 11, 2026 · Pecos, Odessa · Material Maintenance Project
$103,000Low bid: TOUCHSTONE RESOURCES, LLC-4.2% vs estimate $107,500
$2,862Left on the table2.8% gap to the second bid
3BiddersSpread 27% low to high
5Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | TOUCHSTONE RESOURCES, LLC | $103,000 | -4.2% | $2,862 | 0 | 0 | |
| 2 | SOUTHERN SOURCING SOLUTIONS, LLC | $105,862 | +2.8% | -1.5% | $24,871 | 0 | 0 |
| 3 | HALL BROTHERS, INC. | $130,733 | +26.9% | 21.6% | 0 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
TOUCHSTONE RESOURCES, LLC vs SOUTHERN SOURCING SOLUTIONS, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 8012-7041 ASPH CONC PATCH MAT (DEL)(ST2) | 100 TON | $195.00 | $223.69 | $175.27 | $2,869 |
| 8012-7040 ASPH CONC PATCH MAT (DEL)(ST1) | 100 TON | $195.00 | $223.44 | $158.39 | $2,844 |
| 8012-7044 ASPH CONC PATCH MAT (DEL)(ST5) | 100 TON | $220.00 | $195.12 | $197.24 | -$2,488 |
| 8012-7043 ASPH CONC PATCH MAT (DEL)(ST4) | 100 TON | $220.00 | $205.62 | $197.37 | -$1,438 |
| 8012-7042 ASPH CONC PATCH MAT (DEL)(ST3) | 100 TON | $200.00 | $210.75 | $195.54 | $1,075 |
Positive: the low bidder was cheaper on that item. These 5 items account for $2,862 of the $2,862 gap.