Bid Tab X-ray: 6501-38-001

Jun 9, 2026 · Ector Sign up free
Set your company to personalize scores

6501-38-001 LRA

6501-38-001 · let Jun 9, 2026 · Ector, Odessa · Material Maintenance Project

$254,624Low bid: MARTIN MARIETTA MATERIALS, INC.-1.1% vs estimate $257,500
$5,318Left on the table2.1% gap to the second bid
2BiddersSpread 2% low to high
10Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1MARTIN MARIETTA MATERIALS, INC. $254,624-1.1% $5,318 0 0
2VULCAN CONSTRUCTION MATERIALS, LLC $259,942+2.1%0.9% 0 0

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.

Where the job was won

MARTIN MARIETTA MATERIALS, INC. vs VULCAN CONSTRUCTION MATERIALS, LLC, biggest item swings
ItemQtyLow2ndMarket2nd minus low
8001-7038 LRA (TY I GR B) (DEL) (ST2)400 TON $142.84$146.41$153.94 $1,428
8001-7011 LRA (TY I GR AA) (DEL) (ST3)200 TON $136.05$141.16$127.41 $1,022
8001-7082 LRA (TY I GR D) (DEL) (ST4)400 TON $143.95$145.73$137.41 $712
8001-7081 LRA (TY I GR D) (DEL) (ST3)350 TON $140.55$142.16$138.98 $563
8001-7110 LRA (TY II GR DS) (DEL) (ST4)200 TON $143.95$146.73$127.32 $556
8001-7026 LRA (TY I GR A) (DEL) (ST4)50 TON $139.12$144.73$114.29 $280
8001-7010 LRA (TY I GR AA) (DEL) (ST2)50 TON $140.84$146.41$124.75 $279
8001-7040 LRA (TY I GR B) (DEL) (ST4)50 TON $141.12$144.73$133.33 $180
8001-7039 LRA (TY I GR B) (DEL) (ST3)50 TON $138.05$141.16$134.52 $155
8001-7037 LRA (TY I GR B) (DEL) (ST1)50 TON $135.18$138.01$152.70 $141

Positive: the low bidder was cheaper on that item. These 10 items account for $5,318 of the $5,318 gap.