$114.29Avg low bid / TON
$119.16Avg of all bids
$125.75Avg engineer's estimate
6Jobs · 650 TON
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2026 | 3 | 300 | $114.85 | $122.55 |
| 2025 | 3 | 350 | $113.82 | $116.26 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Sep 8, 2026 | 6508-40-001 | Tom GreenSan Angelo | 200 TON | $106.08 | VULCAN CONSTRUCTION MATERIALS, LLC |
| Jun 9, 2026 | 6501-38-001 | EctorOdessa | 50 TON | $139.12 | MARTIN MARIETTA MATERIALS, INC. |
| Apr 28, 2026 | 6501-36-001 | PecosOdessa | 50 TON | $125.67 | VULCAN CONSTRUCTION MATERIALS, LLC |
| Jun 24, 2025 | 6485-24-001 | EctorOdessa | 100 TON | $133.76 | MARTIN MARIETTA MATERIALS, INC. |
| Jun 24, 2025 | 6485-22-001 | PecosOdessa | 50 TON | $119.67 | VULCAN CONSTRUCTION MATERIALS, LLC |
| Mar 27, 2025 | 6480-73-001 | Tom GreenSan Angelo | 200 TON | $102.38 | VULCAN CONSTRUCTION MATERIALS, LLC |