Routine Maintenance Project
CCSJ 6510-86-001 · lets Dec 9, 2026 · El Paso, El Paso · IH0010
$963,350Engineer's estimate
Items at market: $1,308,850 (+35.9%)
$877,277Most likely low bid$826,086 to $1,067,667 (middle half)
2.5Expected bidders0 plan holders, 0 regular bidders
71/100Strong fit: bid itMarket only. Set your company for a personal score
Where the low bid should land
$877,277
Estimate $963,350
$704,026 (1 in 10 go lower)$1,571,533 (1 in 10 go higher)
From 29 comparable let jobs (district + work type, estimates of $385,340 to $2,408,375, last 3 years). 69% of them went under the estimate; the typical low bid was -8.9% vs estimate.
Bid / no-bid score
- Competition25 / 25Jobs like this draw about 2.5 bidders.
- Margin7 / 20Low bids land at 91% of the estimate.
Set your company to add your experience, win rate and size fit.
Comparable jobs
| Oct 2026 | 6507-39-001El Paso · 6 bidders | $845,627+4.4% |
| Sep 2026 | 6504-81-001El Paso · 3 bidders | $1,548,900-4.7% |
| Aug 2026 | 6498-87-001El Paso · 3 bidders | $531,000-4.3% |
| Aug 2026 | 6500-72-001Culberson · 3 bidders | $1,106,900+10.8% |
| Aug 2026 | 6505-39-001El Paso · 3 bidders | $715,750-8.9% |
| Jul 2026 | 6498-87-001El Paso · 3 bidders | $478,000-14.4% |
| Jul 2026 | 6500-67-001El Paso · 4 bidders | $426,250-19.7% |
| Jul 2026 | 6500-71-001El Paso · 4 bidders | $381,500-11.0% |
The field: plan holders and how they bid
Last 3 years in TexasNo plan holders posted for this job yet. Check back closer to the letting.
Items that decide this job
27 of 27 items priced from low bids| Item | Qty | Market price | Range of low bids | At market | Share |
|---|---|---|---|---|---|
| 505-7002 TMA (MOBILE OPERATION)336 low bids · prices swing 1,107,000x | 8,900 HR | $64.00 | $0.0010 – $1,107.00 | $569,565 | 43.5% |
| 500-7001 MOBILIZATION2229 low bids · prices swing 42,200,000,000x | 1 LS | $523,850.32 | $0.0010 – $42,200,000.00 | $523,850 | 40.0% |
| 505-7001 TMA (STATIONARY)2363 low bids · prices swing 16,487,000x | 150 DAY | $217.57 | $0.0010 – $16,487.00 | $32,636 | 2.5% |
| 790-7058 ADDITIONAL LANE CLOSURE ITEM(TYPE 20)66 low bids · prices swing 250x | 500 HR | $48.40 | $1.00 – $250.00 | $24,200 | 1.8% |
| 790-7049 LANE CLOSURE(HOURLY ONLY)(TYP 11)29 low bids · prices swing 10x | 250 HR | $89.75 | $20.00 – $190.00 | $22,437 | 1.7% |
| 790-7056 LANE CLOSURE(HOURLY ONLY)(TYP 18)23 low bids · prices swing 195x | 500 HR | $35.34 | $1.00 – $195.00 | $17,670 | 1.4% |
| 545-7014 CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)188 low bids · prices swing 2,940,000x | 2 EA | $8,780.51 | $0.0100 – $29,400.00 | $17,561 | 1.3% |
| 790-7039 LANE CLOSURE(HOURLY ONLY)(TYP 1)31 low bids · prices swing 325x | 250 HR | $69.23 | $1.00 – $325.00 | $17,309 | 1.3% |
| 790-7052 LANE CLOSURE(HOURLY ONLY)(TYP 14)21 low bids · prices swing 148x | 250 HR | $42.05 | $1.00 – $148.00 | $10,513 | 0.8% |
| 500-7033 MOBILIZATION (EMERGENCY)256 low bids · prices swing 20,000,000x | 10 EA | $844.81 | $0.0010 – $20,000.00 | $8,448 | 0.6% |
| 790-7045 LANE CLOSURE(HOURLY ONLY)(TYP 7)27 low bids · prices swing 350x | 80 HR | $101.18 | $1.00 – $350.00 | $8,095 | 0.6% |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN975 low bids · prices swing 7,870,000x | 85 DAY | $87.82 | $0.0010 – $7,870.00 | $7,464 | 0.6% |
| 790-7043 LANE CLOSURE(HOURLY ONLY)(TYP 5)30 low bids · prices swing 140x | 125 HR | $58.58 | $1.00 – $140.00 | $7,323 | 0.6% |
| 500-7003 MOBILIZATION (CALLOUT 1)44 low bids · prices swing 520,000,000x | 10 EA | $599.93 | $0.0010 – $520,000.00 | $5,999 | 0.5% |
| 512-7017 PORT CTB (DES SOURCE)(F-SHAPE)(TY 1)29 low bids · prices swing 12,500x | 200 LF | $25.07 | $0.0100 – $125.00 | $5,015 | 0.4% |