FY 2027 Districtwide Crack Seal
6504-81-001 · let Sep 2, 2026 · El Paso, El Paso · Routine Maintenance Project
$1,548,900Low bid: DIGG COMMERCIAL, LLC-4.7% vs estimate $1,625,640
$592,550Left on the table38.3% gap to the second bid
3BiddersSpread 70% low to high
3Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | DIGG COMMERCIAL, LLC | $1,548,900 | -4.7% | $592,550 | 1+$231,297 | 1-$361,350 | |
| 2 | D & M CONTRACTORS, LLC | $2,141,450 | +38.3% | 31.7% | $495,990 | 0 | 0 |
| 3 | CRACKSEAL OF TEXAS, LLC | $2,637,440 | +70.3% | 62.2% | 2+$1,184,607 | 1-$323,850 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
DIGG COMMERCIAL, LLC vs D & M CONTRACTORS, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 712-7001 JT / CRCK SEAL (RUBBER - ASPHALT) | 1,433 LMI | $800.00 | $1,250.00 | $868.20 | $644,850 |
| 505-7001 TMA (STATIONARY) | 40 DAY | $6,000.00 | $5.00 | $217.57 | -$239,800 |
| 500-7001 MOBILIZATION | 1 LS | $162,500.00 | $350,000.00 | $523,850.32 | $187,500 |
Positive: the low bidder was cheaper on that item. These 3 items account for $592,550 of the $592,550 gap.