Routine Maintenance Project - Sealed
CCSJ 6496-63-001 · lets Jan 6, 2027 · Burnet, Austin · US0281
$2,048,175Engineer's estimate
Items at market: $2,496,294 (+21.9%)
$1,506,607Most likely low bid$1,393,358 to $1,796,421 (middle half)
4.1Expected bidders0 plan holders, 0 regular bidders
44/100Weak fitMarket only. Set your company for a personal score
Where the low bid should land
$1,506,607
Estimate $2,048,175
$1,308,520 (1 in 10 go lower)$2,022,995 (1 in 10 go higher)
From 19 comparable let jobs (district + work type, estimates of $819,270 to $5,120,438, last 3 years). 89% of them went under the estimate; the typical low bid was -26.4% vs estimate.
Bid / no-bid score
- Competition20 / 25Jobs like this draw about 4.1 bidders.
- Margin0 / 20Low bids land at 74% of the estimate.
Set your company to add your experience, win rate and size fit.
Comparable jobs
| Nov 2026 | 6484-51-001Williamson · 7 bidders | $962,812-17.0% |
| Sep 2026 | 6498-20-001Travis · 4 bidders | $668,419-26.4% |
| Sep 2026 | 6499-28-001Williamson · 5 bidders | $660,385-31.6% |
| Aug 2026 | 6487-45-001Hays · 5 bidders | $1,975,939+13.2% |
| Jul 2026 | 6484-37-001Travis · 3 bidders | $756,200-35.9% |
| May 2026 | 6499-06-001Bastrop · 5 bidders | $757,352-22.0% |
| May 2026 | 6495-92-001Hays · 3 bidders | $890,314-5.2% |
| May 2026 | 6498-17-001Hays · 4 bidders | $754,625-18.8% |
The field: plan holders and how they bid
Last 3 years in TexasNo plan holders posted for this job yet. Check back closer to the letting.
Items that decide this job
31 of 31 items priced from low bids| Item | Qty | Market price | Range of low bids | At market | Share |
|---|---|---|---|---|---|
| 770-7037 REPLACE GUARDRAIL END TREATMENT SYSTEM29 low bids · prices swing 8x | 400 EA | $3,116.90 | $1,300.00 – $10,000.00 | $1,246,758 | 49.9% |
| 770-7035 REPLACE W-BEAM RAIL29 low bids · prices swing 6x | 20,000 LF | $24.10 | $10.00 – $55.00 | $482,032 | 19.3% |
| 500-7002 MOBILIZATION (CALLOUT)748 low bids · prices swing 535,000,000x | 400 EA | $600.85 | $0.0010 – $535,000.00 | $240,340 | 9.6% |
| 770-7006 REPLACE TIMBER POST W/O CONC FND99 low bids · prices swing 750x | 1,000 EA | $89.82 | $1.00 – $750.00 | $89,821 | 3.6% |
| 505-7001 TMA (STATIONARY)2363 low bids · prices swing 16,487,000x | 350 DAY | $217.57 | $0.0010 – $16,487.00 | $76,150 | 3.1% |
| 770-7018 REPLACE BLOCKOUT93 low bids · prices swing 25,000x | 1,500 EA | $44.95 | $0.1000 – $2,500.00 | $67,432 | 2.7% |
| 770-7008 REPLACE TIMBER POST W/ CONC FND79 low bids · prices swing 4,650x | 700 EA | $94.21 | $1.00 – $4,650.00 | $65,948 | 2.6% |
| 451-7020 RETROFIT RAIL (TY T631)28 low bids · prices swing 5x | 550 LF | $110.49 | $60.00 – $270.00 | $60,769 | 2.4% |
| 770-7036 REPLACE THRIE-BEAM RAIL26 low bids · prices swing 500x | 800 LF | $48.04 | $1.00 – $500.00 | $38,431 | 1.5% |
| 770-7026 REPLACE DOWNSTREAM ANCHOR TERMINAL62 low bids · prices swing 2,500x | 50 EA | $534.87 | $1.00 – $2,500.00 | $26,743 | 1.1% |
| 770-7010 REALIGN POSTS95 low bids · prices swing 100,000x | 1,000 EA | $24.32 | $0.0100 – $1,000.00 | $24,323 | 1.0% |
| 771-7026 REPLACE LINE OR TERMINAL POST (GIBRAL)20 low bids · prices swing 500x | 100 EA | $176.83 | $1.00 – $500.00 | $17,683 | 0.7% |
| 770-7016 REPLACE SINGLE GDRAIL TERMINAL RAIL83 low bids · prices swing 175x | 250 LF | $31.82 | $1.00 – $175.00 | $7,954 | 0.3% |
| 132-7003 EMBANK (FNL)(OC)(TY B)179 low bids · prices swing 1,000x | 400 CY | $16.96 | $1.00 – $1,000.00 | $6,785 | 0.3% |
| 770-7038 REPLACE CURVED RAIL21 low bids · prices swing 100x | 250 LF | $26.19 | $1.00 – $100.00 | $6,547 | 0.3% |