CTTS Lighting Upgrade SH 130/45SE
6499-28-001 · let Sep 9, 2026 · Williamson, Austin · Routine Maintenance Project - Sealed
$660,385Low bid: VACA UNDERGROUND UTILITIES INC-31.6% vs estimate $965,583
$180,208Left on the table27.3% gap to the second bid
5BiddersSpread 141% low to high
18Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | VACA UNDERGROUND UTILITIES INC | $660,385 | -31.6% | $180,208 | 3+$35,628 | 4-$671,743 | |
| 2 | ELECNOR BELCO ELECTRIC, INC. | $840,593 | +27.3% | -12.9% | $371,118 | 1+$9,888 | 4-$560,463 |
| 3 | JASCO | $1,211,711 | +83.5% | 25.5% | $17,089 | 2+$88,306 | 1-$389,850 |
| 4 | AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., LLC | $1,228,800 | +86.1% | 27.3% | $361,120 | 6+$170,730 | 2-$549,871 |
| 5 | E-Z BEL CONSTRUCTION, LLC | $1,589,920 | +140.8% | 64.7% | 5+$405,360 | 2-$426,764 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
VACA UNDERGROUND UTILITIES INC vs ELECNOR BELCO ELECTRIC, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 365 DAY | $25.00 | $156.00 | $217.57 | $47,815 |
| 500-7001 MOBILIZATION | 1 LS | $60,000.00 | $103,469.00 | $523,850.32 | $43,469 |
| 690-7242 TROUBLESHOOT FOR REPAIRS | 440 HR | $100.00 | $184.00 | $142.93 | $36,960 |
| 690-7181 REPLACE LUMINAIRE FIXTURE (LED) | 606 EA | $550.00 | $605.00 | $547.29 | $33,330 |
| 618-7037 CONDT (PVC) (SCH 40) (3") (BORE) | 2,200 LF | $14.00 | $24.00 | $26.79 | $22,000 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 12 MO | $500.00 | $2,302.00 | $11,585.04 | $21,624 |
| 618-7031 CONDT (PVC) (SCH 40) (2") (BORE) | 2,200 LF | $13.00 | $22.00 | $25.51 | $19,800 |
| 6071-7004 ALUMINUM ELECTRICAL COND (#8 XHHW) | 4,400 LF | $4.00 | $1.20 | $2.69 | -$12,320 |
| 6071-7001 ALUMINUM ELECTRICAL COND (#4 XHHW) | 4,400 LF | $4.00 | $1.40 | $2.08 | -$11,440 |
| 6071-7003 ALUMINUM ELECTRICAL COND (#6 XHHW) | 4,400 LF | $4.00 | $1.40 | $1.62 | -$11,440 |
| 6013-7006 GROUND BOX (PREPARE) | 110 EA | $250.00 | $184.00 | $385.19 | -$7,260 |
| 624-7015 RETRO GROUND BOX (W/SECURE LID) | 10 EA | $2,000.00 | $1,319.00 | $330.23 | -$6,810 |
| 6013-7005 MANHOLE (PREPARE) | 110 EA | $240.00 | $277.00 | $306.51 | $4,070 |
| 690-7198 REPLACE TRANSFORMER BASE COVER | 10 EA | $250.00 | $577.00 | $178.41 | $3,270 |
| 620-7011 ELEC CONDR (NO.4) BARE | 2,200 LF | $3.40 | $2.50 | $2.88 | -$1,980 |
| 618-7090 CONDUIT (PREPARE) | 2,200 LF | $1.00 | $1.50 | $3.08 | $1,100 |
| 620-7007 ELEC CONDR (NO.8) BARE | 2,200 LF | $2.00 | $1.50 | $1.94 | -$1,100 |
| 620-7009 ELEC CONDR (NO.6) BARE | 2,200 LF | $2.40 | $2.00 | $2.23 | -$880 |
Positive: the low bidder was cheaper on that item. These 18 items account for $180,208 of the $180,208 gap.
VACA UNDERGROUND UTILITIES INC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 624-7015 RETRO GROUND BOX (W/SECURE LID) | 10 EA | $2,000.00 | $330.23 | 6.06x | $16,698 |
| 6071-7003 ALUMINUM ELECTRICAL COND (#6 XHHW) | 4,400 LF | $4.00 | $1.62 | 2.47x | $10,477 |
| 6071-7001 ALUMINUM ELECTRICAL COND (#4 XHHW) | 4,400 LF | $4.00 | $2.08 | 1.92x | $8,453 |
| 500-7001 MOBILIZATION | 1 LS | $60,000.00 | $523,850.32 | 0.11x | -$463,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 12 MO | $500.00 | $11,585.04 | 0.04x | -$133,021 |
| 505-7001 TMA (STATIONARY) | 365 DAY | $25.00 | $217.57 | 0.11x | -$70,289 |
| 618-7090 CONDUIT (PREPARE) | 2,200 LF | $1.00 | $3.08 | 0.32x | -$4,584 |
ELECNOR BELCO ELECTRIC, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 624-7015 RETRO GROUND BOX (W/SECURE LID) | 10 EA | $1,319.00 | $330.23 | 3.99x | $9,888 |
| 500-7001 MOBILIZATION | 1 LS | $103,469.00 | $523,850.32 | 0.20x | -$420,381 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 12 MO | $2,302.00 | $11,585.04 | 0.20x | -$111,397 |
| 6013-7006 GROUND BOX (PREPARE) | 110 EA | $184.00 | $385.19 | 0.48x | -$22,131 |
| 6071-7004 ALUMINUM ELECTRICAL COND (#8 XHHW) | 4,400 LF | $1.20 | $2.69 | 0.45x | -$6,554 |
JASCO: unbalanced items
Placed 3AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 618-7037 CONDT (PVC) (SCH 40) (3") (BORE) | 2,200 LF | $50.00 | $26.79 | 1.87x | $51,063 |
| 6013-7005 MANHOLE (PREPARE) | 110 EA | $750.00 | $306.51 | 2.45x | $48,784 |
| 618-7031 CONDT (PVC) (SCH 40) (2") (BORE) | 2,200 LF | $45.00 | $25.51 | 1.76x | $42,873 |
| 624-7015 RETRO GROUND BOX (W/SECURE LID) | 10 EA | $1,600.00 | $330.23 | 4.85x | $12,698 |
| 6071-7001 ALUMINUM ELECTRICAL COND (#4 XHHW) | 4,400 LF | $4.00 | $2.08 | 1.92x | $8,453 |
| 620-7011 ELEC CONDR (NO.4) BARE | 2,200 LF | $6.00 | $2.88 | 2.08x | $6,859 |
| 500-7001 MOBILIZATION | 1 LS | $65,000.00 | $523,850.32 | 0.12x | -$458,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 12 MO | $4,000.00 | $11,585.04 | 0.35x | -$91,021 |
E-Z BEL CONSTRUCTION, LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 12 MO | $35,000.00 | $11,585.04 | 3.02x | $280,979 |
| 690-7242 TROUBLESHOOT FOR REPAIRS | 440 HR | $275.00 | $142.93 | 1.92x | $58,109 |
| 6013-7006 GROUND BOX (PREPARE) | 110 EA | $800.00 | $385.19 | 2.08x | $45,629 |
| 6071-7003 ALUMINUM ELECTRICAL COND (#6 XHHW) | 4,400 LF | $4.00 | $1.62 | 2.47x | $10,477 |
| 6071-7004 ALUMINUM ELECTRICAL COND (#8 XHHW) | 4,400 LF | $5.00 | $2.69 | 1.86x | $10,166 |
| 500-7001 MOBILIZATION | 1 LS | $140,000.00 | $523,850.32 | 0.27x | -$383,850 |
| 505-7001 TMA (STATIONARY) | 365 DAY | $100.00 | $217.57 | 0.46x | -$42,914 |