Traffic Control Devices
CCSJ 0923-00-086 · lets Dec 1, 2026 · Brown, Brownwood · Various
$1,832,003Engineer's estimate
Items at market: $2,670,026 (+45.7%)
$1,562,736Most likely low bid$1,359,106 to $1,735,407 (middle half)
5.4Expected bidders3 plan holders, 3 regular bidders
42/100Weak fitMarket only. Set your company for a personal score
Where the low bid should land
$1,562,736
Estimate $1,832,003
$1,223,439 (1 in 10 go lower)$2,061,129 (1 in 10 go higher)
From 46 comparable let jobs (district, estimates of $732,801 to $4,580,008, last 3 years). 83% of them went under the estimate; the typical low bid was -14.7% vs estimate.
Bid / no-bid score
- Competition15 / 25Jobs like this draw about 5.4 bidders.
- Margin4 / 20Low bids land at 85% of the estimate.
Set your company to add your experience, win rate and size fit.
Comparable jobs
| Nov 2026 | 0923-06-068Brown · 6 bidders | $1,561,729-10.3% |
| Nov 2026 | 0054-05-027Coleman · 4 bidders | $2,929,127+19.6% |
| Nov 2026 | 6494-86-001Brown · 5 bidders | $561,742-40.2% |
| Oct 2026 | 6503-72-001Lampasas · 9 bidders | $719,494-20.2% |
| Oct 2026 | 6496-56-001Brown · 7 bidders | $3,276,697-25.8% |
| Oct 2026 | 6499-74-001Comanche · 11 bidders | $727,661-25.8% |
| Sep 2026 | 6500-62-001Comanche · 3 bidders | $777,883-21.0% |
| Aug 2026 | 6505-22-001Eastland · 9 bidders | $2,982,235-7.3% |
The field: plan holders and how they bid
Last 3 years in Texas| Plan holder | Bids | Wins | In Brownwood | Avg bid vs est. | Avg win vs est. | Their typical bid here |
|---|---|---|---|---|---|---|
| CENTERLINE TECHNOLOGIES, LLC SharpestBidders | 98 | 26 | 0 of 7 | -14.5% | -23.4% | $1,566,053 |
| TRP INFRASTRUCTURE SERVICES, LLCBidders | 272 | 78 | 2 of 9 | -9.4% | -24.1% | $1,659,918 |
| STRIPE-A-ZONE, LLCBidders | 188 | 51 | 1 of 9 | -8.9% | -22.7% | $1,669,441 |
"Typical bid here" is the estimate times that contractor's average bid ratio. Plan holders with no bids are usually suppliers or subs.
Items that decide this job
25 of 28 items priced from low bids| Item | Qty | Market price | Range of low bids | At market | Share |
|---|---|---|---|---|---|
| 666-7523 REFL PAV MRK TY I (Y)6"(SLD)(125MIL)5 low bids | 1,674,709 LF | $0.6108 | $0.5500 – $1.00 | $1,022,927 | 38.3% |
| 666-7519 REFL PAV MRK TY I (W)6"(SLD)(125MIL)5 low bids | 1,038,174 LF | $0.6060 | $0.5500 – $1.00 | $629,151 | 23.6% |
| 500-7001 MOBILIZATION2229 low bids · prices swing 42,200,000,000x | 1 LS | $523,850.32 | $0.0010 – $42,200,000.00 | $523,850 | 19.6% |
| 672-7004 REFL PAV MRKR TY II-A-A1023 low bids · prices swing 23,500x | 30,127 EA | $3.97 | $0.0400 – $940.00 | $119,710 | 4.5% |
| 666-7522 REFL PAV MRK TY I (Y)6"(BRK)(125MIL)4 low bids | 142,790 LF | $0.6313 | $0.5500 – $1.00 | $90,138 | 3.4% |
| 668-7089 PREFAB PM TY C (W)(24")(SLD)330 low bids · prices swing 172x | 4,101 LF | $13.72 | $1.27 – $218.00 | $56,281 | 2.1% |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING2018 low bids · prices swing 273,686,480x | 4 MO | $11,585.04 | $0.0010 – $273,686.48 | $46,340 | 1.7% |
| 533-7002 MILL RUMBLE STRIPS (ASPH) (CENTERLINE)260 low bids · prices swing 250x | 188,712 LF | $0.2394 | $0.0800 – $20.00 | $45,178 | 1.7% |
| 505-7003 TMA (MOBILE OPERATION)1256 low bids · prices swing 3,000,000x | 110 DAY | $229.60 | $0.0010 – $3,000.00 | $25,256 | 0.9% |
| 316-7032 ASPH (RC-250)14 low bids · prices swing 6x | 21.5 TON | $1,089.28 | $877.50 – $5,000.00 | $23,420 | 0.9% |
| 533-7001 MILL RUMBLE STRIPS (ASPHALT) (SHLDR)352 low bids · prices swing 380x | 93,862 LF | $0.2040 | $0.0500 – $19.00 | $19,148 | 0.7% |
| 316-7175 AGGR (TY-B, GR-5)(SAC-B)22 low bids · prices swing 54x | 213.2 CY | $88.19 | $35.00 – $1,900.00 | $18,803 | 0.7% |
| 666-7518 REFL PAV MRK TY I (W)6"(BRK)(125MIL)5 low bids | 19,510 LF | $0.6495 | $0.5500 – $1.00 | $12,672 | 0.5% |
| 668-7108 PREFAB PM TY C (W)(RR XING)160 low bids · prices swing 7x | 14 EA | $602.94 | $250.00 – $1,751.00 | $8,441 | 0.3% |
| 668-7100 PREFAB PM TY C (W)(LN REDUCT ARROW)107 low bids · prices swing 4x | 12 EA | $467.68 | $240.09 – $1,000.00 | $5,612 | 0.2% |