Bid Day Forecast: 0923-00-086

Brown · Dec 1, 2026 Sign up free
Set your company to personalize scores

Traffic Control Devices

CCSJ 0923-00-086 · lets Dec 1, 2026 · Brown, Brownwood · Various

$1,832,003Engineer's estimate Items at market: $2,670,026 (+45.7%)
$1,562,736Most likely low bid$1,359,106 to $1,735,407 (middle half)
5.4Expected bidders3 plan holders, 3 regular bidders
42/100Weak fitMarket only. Set your company for a personal score

Where the low bid should land

$1,223,439 (1 in 10 go lower)$2,061,129 (1 in 10 go higher)

From 46 comparable let jobs (district, estimates of $732,801 to $4,580,008, last 3 years). 83% of them went under the estimate; the typical low bid was -14.7% vs estimate.

Bid / no-bid score

  • Competition15 / 25Jobs like this draw about 5.4 bidders.
  • Margin4 / 20Low bids land at 85% of the estimate.

Set your company to add your experience, win rate and size fit.

Comparable jobs

Nov 2026 0923-06-068Brown · 6 bidders $1,561,729-10.3%
Nov 2026 0054-05-027Coleman · 4 bidders $2,929,127+19.6%
Nov 2026 6494-86-001Brown · 5 bidders $561,742-40.2%
Oct 2026 6503-72-001Lampasas · 9 bidders $719,494-20.2%
Oct 2026 6496-56-001Brown · 7 bidders $3,276,697-25.8%
Oct 2026 6499-74-001Comanche · 11 bidders $727,661-25.8%
Sep 2026 6500-62-001Comanche · 3 bidders $777,883-21.0%
Aug 2026 6505-22-001Eastland · 9 bidders $2,982,235-7.3%

The field: plan holders and how they bid

Last 3 years in Texas
Plan holderBidsWinsIn BrownwoodAvg bid vs est.Avg win vs est.Their typical bid here
CENTERLINE TECHNOLOGIES, LLC SharpestBidders 98260 of 7 -14.5%-23.4% $1,566,053
TRP INFRASTRUCTURE SERVICES, LLCBidders 272782 of 9 -9.4%-24.1% $1,659,918
STRIPE-A-ZONE, LLCBidders 188511 of 9 -8.9%-22.7% $1,669,441

"Typical bid here" is the estimate times that contractor's average bid ratio. Plan holders with no bids are usually suppliers or subs.

Items that decide this job

25 of 28 items priced from low bids
ItemQtyMarket priceRange of low bidsAt marketShare
666-7523 REFL PAV MRK TY I (Y)6"(SLD)(125MIL)5 low bids 1,674,709 LF$0.6108$0.5500 – $1.00 $1,022,92738.3%
666-7519 REFL PAV MRK TY I (W)6"(SLD)(125MIL)5 low bids 1,038,174 LF$0.6060$0.5500 – $1.00 $629,15123.6%
500-7001 MOBILIZATION2229 low bids · prices swing 42,200,000,000x 1 LS$523,850.32$0.0010 – $42,200,000.00 $523,85019.6%
672-7004 REFL PAV MRKR TY II-A-A1023 low bids · prices swing 23,500x 30,127 EA$3.97$0.0400 – $940.00 $119,7104.5%
666-7522 REFL PAV MRK TY I (Y)6"(BRK)(125MIL)4 low bids 142,790 LF$0.6313$0.5500 – $1.00 $90,1383.4%
668-7089 PREFAB PM TY C (W)(24")(SLD)330 low bids · prices swing 172x 4,101 LF$13.72$1.27 – $218.00 $56,2812.1%
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING2018 low bids · prices swing 273,686,480x 4 MO$11,585.04$0.0010 – $273,686.48 $46,3401.7%
533-7002 MILL RUMBLE STRIPS (ASPH) (CENTERLINE)260 low bids · prices swing 250x 188,712 LF$0.2394$0.0800 – $20.00 $45,1781.7%
505-7003 TMA (MOBILE OPERATION)1256 low bids · prices swing 3,000,000x 110 DAY$229.60$0.0010 – $3,000.00 $25,2560.9%
316-7032 ASPH (RC-250)14 low bids · prices swing 6x 21.5 TON$1,089.28$877.50 – $5,000.00 $23,4200.9%
533-7001 MILL RUMBLE STRIPS (ASPHALT) (SHLDR)352 low bids · prices swing 380x 93,862 LF$0.2040$0.0500 – $19.00 $19,1480.7%
316-7175 AGGR (TY-B, GR-5)(SAC-B)22 low bids · prices swing 54x 213.2 CY$88.19$35.00 – $1,900.00 $18,8030.7%
666-7518 REFL PAV MRK TY I (W)6"(BRK)(125MIL)5 low bids 19,510 LF$0.6495$0.5500 – $1.00 $12,6720.5%
668-7108 PREFAB PM TY C (W)(RR XING)160 low bids · prices swing 7x 14 EA$602.94$250.00 – $1,751.00 $8,4410.3%
668-7100 PREFAB PM TY C (W)(LN REDUCT ARROW)107 low bids · prices swing 4x 12 EA$467.68$240.09 – $1,000.00 $5,6120.2%