MISC. BRIDGE REPAIR (BPM 2027)
6503-72-001 · let Oct 7, 2026 · Lampasas, Brownwood · Bridge Preventative Maintenance
$719,494Low bid: TAYLOR BRIDGE LLC-20.2% vs estimate $902,155
$170,395Left on the table23.7% gap to the second bid
9BiddersSpread 98% low to high
28Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | TAYLOR BRIDGE LLC | $719,494 | -20.2% | $170,395 | 6+$116,174 | 5-$624,854 | |
| 2 | THE TRUESDELL CORPORATION | $889,889 | +23.7% | -1.4% | $47,909 | 10+$216,558 | 6-$500,539 |
| 3 | MPB, INC. | $937,798 | +30.3% | 4.0% | $16,515 | 5+$185,127 | 4-$527,593 |
| 4 | SCOTT TUCKER CONSTRUCTION COMPANY, LLC | $954,313 | +32.6% | 5.8% | $40,441 | 7+$151,529 | 4-$465,545 |
| 5 | STRUCTURAL INTEGRITY GROUP LLC | $994,754 | +38.3% | 10.3% | $18,745 | 6+$220,248 | 6-$533,767 |
| 6 | ICOS MANAGEMENT, LLC | $1,013,499 | +40.9% | 12.3% | $65,201 | ||
| 7 | ROAD DOCTORS LLC | $1,078,700 | +49.9% | 19.6% | $149,320 | ||
| 8 | BLACKSMITH VENTURES LLC | $1,228,020 | +70.7% | 36.1% | $198,586 | ||
| 9 | THK CONSTRUCTION LLC | $1,426,606 | +98.3% | 58.1% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
TAYLOR BRIDGE LLC vs THE TRUESDELL CORPORATION, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $30,000.00 | $168,564.00 | $523,850.32 | $138,564 |
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 97 SF | $750.00 | $155.00 | $150.68 | -$57,715 |
| 401-7001 FLOWABLE BACKFILL | 217 CY | $325.00 | $550.00 | $298.77 | $48,825 |
| 432-7043 RIPRAP (STONE PROTECTION)(18 IN) | 810 CY | $200.00 | $155.00 | $184.74 | -$36,450 |
| 432-7048 RIPRAP (STONE PROTECTION)(36 IN) | 314 CY | $300.00 | $188.00 | $174.48 | -$35,168 |
| 776-7024 REPLACE(STEEL RAIL) | 25 LF | $100.00 | $1,250.00 | $193.52 | $28,750 |
| 787-7001 REPLACING ELASTOMERIC BEARING PADS | 10 EA | $5,500.00 | $8,000.00 | $2,783.49 | $25,000 |
| 110-7002 EXCAV (CHANNEL) | 243 CY | $25.00 | $110.00 | $16.69 | $20,655 |
| 752-7003 TREE TRIMMING / BRUSH REMOVAL(CHANNELS) | 5.1 AC | $1,000.00 | $4,000.00 | $1,602.83 | $15,300 |
| 785-7002 BRIDGE JOINT REPAIR (HEADER) | 43 LF | $200.00 | $500.00 | $199.12 | $12,900 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $1.00 | $2,000.00 | $11,585.04 | $11,994 |
| 780-7002 CNC CRACK REPAIR (DISCRETE)(INJECT) | 23 LF | $575.00 | $150.00 | $76.83 | -$9,775 |
| 735-7060 DRIFTWOOD REMOVAL | 739 CY | $100.00 | $90.00 | $72.46 | -$7,390 |
| 752-7007 TREE REMOVAL (18" - 24" DIA) | 8 EA | $500.00 | $1,350.00 | $141.37 | $6,800 |
| 420-7067 CL C CONC (MISC) | 10 CY | $1,000.00 | $1,600.00 | $1,569.38 | $6,000 |
| 506-7044 BIODEG EROSN CONT LOGS (INSTL) (12") | 6,500 LF | $1.00 | $0.1000 | $5.23 | -$5,850 |
| 432-7045 RIPRAP (STONE PROTECTION)(24 IN) | 100 CY | $275.00 | $225.00 | $190.61 | -$5,000 |
| 403-7001 TEMPORARY SPL SHORING | 135 SF | $1.00 | $35.00 | $25.56 | $4,590 |
| 480-7002 CLEAN EXIST CULVERTS | 90 CY | $100.00 | $150.00 | $42.86 | $4,500 |
| 432-7003 RIPRAP (CONC)(6 IN) | 35 CY | $650.00 | $750.00 | $580.25 | $3,500 |
Positive: the low bidder was cheaper on that item. These 20 items account for $170,030 of the $170,395 gap.
TAYLOR BRIDGE LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 97 SF | $750.00 | $150.68 | 4.98x | $58,134 |
| 787-7001 REPLACING ELASTOMERIC BEARING PADS | 10 EA | $5,500.00 | $2,783.49 | 1.98x | $27,165 |
| 780-7002 CNC CRACK REPAIR (DISCRETE)(INJECT) | 23 LF | $575.00 | $76.83 | 7.48x | $11,458 |
| 438-7004 CLEANING AND SEALING EXIST JOINTS (CL3) | 278 LF | $50.00 | $19.19 | 2.61x | $8,564 |
| 752-7005 TREE REMOVAL (4" - 12" DIA) | 13 EA | $500.00 | $60.77 | 8.23x | $5,710 |
| 480-7002 CLEAN EXIST CULVERTS | 90 CY | $100.00 | $42.86 | 2.33x | $5,143 |
| 500-7001 MOBILIZATION | 1 LS | $30,000.00 | $523,850.32 | 0.06x | -$493,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $1.00 | $11,585.04 | 0.00x | -$69,504 |
| 506-7044 BIODEG EROSN CONT LOGS (INSTL) (12") | 6,500 LF | $1.00 | $5.23 | 0.19x | -$27,474 |
| 505-7001 TMA (STATIONARY) | 120 DAY | $1.00 | $217.57 | 0.00x | -$25,989 |
| 506-7046 BIODEG EROSN CONT LOGS (REMOVE) | 6,500 LF | $0.0500 | $1.29 | 0.04x | -$8,037 |
THE TRUESDELL CORPORATION: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 401-7001 FLOWABLE BACKFILL | 217 CY | $550.00 | $298.77 | 1.84x | $54,518 |
| 787-7001 REPLACING ELASTOMERIC BEARING PADS | 10 EA | $8,000.00 | $2,783.49 | 2.87x | $52,165 |
| 776-7024 REPLACE(STEEL RAIL) | 25 LF | $1,250.00 | $193.52 | 6.46x | $26,412 |
| 110-7002 EXCAV (CHANNEL) | 243 CY | $110.00 | $16.69 | 6.59x | $22,673 |
| 785-7002 BRIDGE JOINT REPAIR (HEADER) | 43 LF | $500.00 | $199.12 | 2.51x | $12,938 |
| 752-7003 TREE TRIMMING / BRUSH REMOVAL(CHANNELS) | 5.1 AC | $4,000.00 | $1,602.83 | 2.50x | $12,226 |
| 438-7004 CLEANING AND SEALING EXIST JOINTS (CL3) | 278 LF | $55.00 | $19.19 | 2.87x | $9,954 |
| 752-7007 TREE REMOVAL (18" - 24" DIA) | 8 EA | $1,350.00 | $141.37 | 9.55x | $9,669 |
| 480-7002 CLEAN EXIST CULVERTS | 90 CY | $150.00 | $42.86 | 3.50x | $9,643 |
| 752-7005 TREE REMOVAL (4" - 12" DIA) | 13 EA | $550.00 | $60.77 | 9.05x | $6,360 |
| 500-7001 MOBILIZATION | 1 LS | $168,564.00 | $523,850.32 | 0.32x | -$355,286 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $2,000.00 | $11,585.04 | 0.17x | -$57,510 |
| 506-7044 BIODEG EROSN CONT LOGS (INSTL) (12") | 6,500 LF | $0.1000 | $5.23 | 0.02x | -$33,324 |
| 505-7001 TMA (STATIONARY) | 120 DAY | $1.00 | $217.57 | 0.00x | -$25,989 |
| 420-7064 CL C CONC (COLUMN ENCASEMENT) | 20 CY | $900.00 | $1,935.90 | 0.46x | -$20,718 |
| 506-7046 BIODEG EROSN CONT LOGS (REMOVE) | 6,500 LF | $0.1000 | $1.29 | 0.08x | -$7,712 |
MPB, INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 432-7048 RIPRAP (STONE PROTECTION)(36 IN) | 314 CY | $485.79 | $174.48 | 2.78x | $97,751 |
| 787-7001 REPLACING ELASTOMERIC BEARING PADS | 10 EA | $6,825.00 | $2,783.49 | 2.45x | $40,415 |
| 438-7004 CLEANING AND SEALING EXIST JOINTS (CL3) | 278 LF | $106.84 | $19.19 | 5.57x | $24,366 |
| 432-7045 RIPRAP (STONE PROTECTION)(24 IN) | 100 CY | $353.30 | $190.61 | 1.85x | $16,269 |
| 480-7002 CLEAN EXIST CULVERTS | 90 CY | $113.14 | $42.86 | 2.64x | $6,325 |
| 500-7001 MOBILIZATION | 1 LS | $114,550.60 | $523,850.32 | 0.22x | -$409,300 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $625.00 | $11,585.04 | 0.05x | -$65,760 |
| 420-7064 CL C CONC (COLUMN ENCASEMENT) | 20 CY | $608.67 | $1,935.90 | 0.31x | -$26,545 |
| 505-7001 TMA (STATIONARY) | 120 DAY | $1.00 | $217.57 | 0.00x | -$25,989 |
SCOTT TUCKER CONSTRUCTION COMPANY, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 787-7001 REPLACING ELASTOMERIC BEARING PADS | 10 EA | $8,278.00 | $2,783.49 | 2.97x | $54,945 |
| 735-7060 DRIFTWOOD REMOVAL | 739 CY | $137.00 | $72.46 | 1.89x | $47,696 |
| 110-7002 EXCAV (CHANNEL) | 243 CY | $97.00 | $16.69 | 5.81x | $19,514 |
| 438-7004 CLEANING AND SEALING EXIST JOINTS (CL3) | 278 LF | $54.00 | $19.19 | 2.81x | $9,676 |
| 480-7002 CLEAN EXIST CULVERTS | 90 CY | $133.00 | $42.86 | 3.10x | $8,113 |
| 752-7007 TREE REMOVAL (18" - 24" DIA) | 8 EA | $931.00 | $141.37 | 6.59x | $6,317 |
| 752-7005 TREE REMOVAL (4" - 12" DIA) | 13 EA | $466.00 | $60.77 | 7.67x | $5,268 |
| 500-7001 MOBILIZATION | 1 LS | $95,000.00 | $523,850.32 | 0.18x | -$428,850 |
| 506-7044 BIODEG EROSN CONT LOGS (INSTL) (12") | 6,500 LF | $1.50 | $5.23 | 0.29x | -$24,224 |
| 752-7003 TREE TRIMMING / BRUSH REMOVAL(CHANNELS) | 5.1 AC | $160.00 | $1,602.83 | 0.10x | -$7,358 |
| 506-7046 BIODEG EROSN CONT LOGS (REMOVE) | 6,500 LF | $0.5000 | $1.29 | 0.39x | -$5,112 |
STRUCTURAL INTEGRITY GROUP LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 735-7060 DRIFTWOOD REMOVAL | 739 CY | $240.00 | $72.46 | 3.31x | $123,813 |
| 787-7001 REPLACING ELASTOMERIC BEARING PADS | 10 EA | $6,500.00 | $2,783.49 | 2.34x | $37,165 |
| 110-7002 EXCAV (CHANNEL) | 243 CY | $125.00 | $16.69 | 7.49x | $26,318 |
| 480-7002 CLEAN EXIST CULVERTS | 90 CY | $197.00 | $42.86 | 4.60x | $13,873 |
| 752-7005 TREE REMOVAL (4" - 12" DIA) | 13 EA | $1,000.00 | $60.77 | 16.45x | $12,210 |
| 752-7007 TREE REMOVAL (18" - 24" DIA) | 8 EA | $1,000.00 | $141.37 | 7.07x | $6,869 |
| 500-7001 MOBILIZATION | 1 LS | $103,000.00 | $523,850.32 | 0.20x | -$420,850 |
| 420-7064 CL C CONC (COLUMN ENCASEMENT) | 20 CY | $50.00 | $1,935.90 | 0.03x | -$37,718 |
| 506-7044 BIODEG EROSN CONT LOGS (INSTL) (12") | 6,500 LF | $0.1000 | $5.23 | 0.02x | -$33,324 |
| 505-7001 TMA (STATIONARY) | 120 DAY | $1.00 | $217.57 | 0.00x | -$25,989 |
| 752-7003 TREE TRIMMING / BRUSH REMOVAL(CHANNELS) | 5.1 AC | $0.1000 | $1,602.83 | 0.00x | -$8,174 |
| 506-7046 BIODEG EROSN CONT LOGS (REMOVE) | 6,500 LF | $0.1000 | $1.29 | 0.08x | -$7,712 |