Widen Non-Freeway
CCSJ 0528-01-113 · lets Dec 1, 2026 · Hidalgo, Pharr · SH 107 · Widen Road - Add Lanes
$24,134,502Engineer's estimate
Items at market: $26,811,582 (+11.1%)
$20,302,484Most likely low bid$19,402,770 to $22,032,394 (middle half)
4.2Expected bidders6 plan holders, 6 regular bidders
51/100Worth a lookMarket only. Set your company for a personal score
Where the low bid should land
$20,302,484
Estimate $24,134,502
$18,515,329 (1 in 10 go lower)$23,649,923 (1 in 10 go higher)
From 14 comparable let jobs (district, estimates of $9,653,801 to $60,336,254, last 3 years). 93% of them went under the estimate; the typical low bid was -15.9% vs estimate.
Bid / no-bid score
- Competition20 / 25Jobs like this draw about 4.2 bidders.
- Margin3 / 20Low bids land at 84% of the estimate.
Set your company to add your experience, win rate and size fit.
Comparable jobs
| Nov 2026 | 0220-01-038Hidalgo · 2 bidders | $11,560,279-10.2% |
| Sep 2026 | 1505-01-016Cameron · 5 bidders | $9,595,502-14.6% |
| May 2026 | 1064-01-027Hidalgo · 6 bidders | $24,782,061-25.9% |
| May 2026 | 2094-01-063Hidalgo · 6 bidders | $25,599,271-24.6% |
| Dec 2025 | 0331-03-022Cameron · 6 bidders | $14,628,509-20.1% |
| Dec 2025 | 0863-01-075Hidalgo · 5 bidders | $11,224,907-20.3% |
| Sep 2025 | 0039-18-122Hidalgo · 3 bidders | $10,273,483-15.1% |
| Sep 2025 | 0528-01-118Hidalgo · 7 bidders | $32,261,532-8.2% |
The field: plan holders and how they bid
Last 3 years in Texas| Plan holder | Bids | Wins | In Pharr | Avg bid vs est. | Avg win vs est. | Their typical bid here |
|---|---|---|---|---|---|---|
| REIM CONSTRUCTION, INC. SharpestBidders | 13 | 3 | 3 of 12 | -4.5% | -11.1% | $23,048,814 |
| TEXAS CORDIA CONSTRUCTION, LLCBidders | 27 | 7 | 7 of 27 | 3.8% | -15.4% | $25,063,521 |
| JAMES CONSTRUCTION GROUP, LLCBidders | 101 | 12 | 0 of 4 | 5.8% | -8.5% | $25,527,300 |
| FOREMOST PAVING, INC.Bidders | 52 | 14 | 14 of 48 | 6.1% | -9.4% | $25,602,860 |
| IOC COMPANY LLCBidders | 48 | 20 | 20 of 44 | 6.1% | -8.0% | $25,605,133 |
| GO UNDERGROUND, LIMITED LIABILITY COMPANYBidders | 15 | 0 | 0 of 10 | 15.6% | $27,901,145 |
"Typical bid here" is the estimate times that contractor's average bid ratio. Plan holders with no bids are usually suppliers or subs.
Items that decide this job
224 of 230 items priced from low bids| Item | Qty | Market price | Range of low bids | At market | Share |
|---|---|---|---|---|---|
| 344-7065 SP MIXES SP-D SAC-B PG76-2210 low bids | 18,974 TON | $118.07 | $100.00 – $205.00 | $2,240,344 | 8.4% |
| 346-7009 STONE-MTRX-ASPH SMA-D SAC-A PG76-2261 low bids · prices swing 4x | 11,671 TON | $152.44 | $105.75 – $383.00 | $1,779,114 | 6.6% |
| 400-7010 CEM STABIL BKFL452 low bids · prices swing 1,000x | 10,660 CY | $138.14 | $1.00 – $1,000.00 | $1,472,612 | 5.5% |
| 464-7028 RC PIPE (CL IV)(60 IN)3 low bids | 3,237 LF | $430.84 | $400.00 – $560.00 | $1,394,644 | 5.2% |
| 545-7006 CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)94 low bids · prices swing 440x | 52 EA | $26,188.60 | $100.00 – $44,000.00 | $1,361,807 | 5.1% |
| 536-7002 CONC MEDIAN72 low bids · prices swing 20x | 11,270 SY | $92.13 | $50.00 – $1,000.00 | $1,038,292 | 3.9% |
| 508-7001 CONSTRUCTING DETOURS174 low bids · prices swing 79x | 11,912 SY | $83.58 | $3.80 – $300.00 | $995,663 | 3.7% |
| 531-7001 CONC SIDEWALKS (4")222 low bids · prices swing 57x | 13,972 SY | $70.57 | $21.64 – $1,237.00 | $985,941 | 3.7% |
| 260-7005 LIME (COM OR QK)(SLURRY)66 low bids | 2,253 TON | $295.18 | $200.00 – $504.00 | $665,043 | 2.5% |
| 110-7001 EXCAV (ROADWAY)586 low bids · prices swing 2,000x | 50,695 CY | $11.68 | $1.00 – $2,000.00 | $592,230 | 2.2% |
| 100-7002 PREPARING ROW593 low bids · prices swing 86,117,000x | 96 STA | $6,072.92 | $0.0100 – $861,170.00 | $583,000 | 2.2% |
| 500-7001 MOBILIZATION2229 low bids · prices swing 42,200,000,000x | 1 LS | $523,850.32 | $0.0010 – $42,200,000.00 | $523,850 | 2.0% |
| 468-7001 THERMOPLASTIC PIPE (PP) (18")18 low bids · prices swing 4x | 5,516 LF | $86.05 | $33.33 – $125.61 | $474,642 | 1.8% |
| 247-7277 FL BS (RDWY DEL)(TY E GR 4)(FNL POS)20 low bids · prices swing 4x | 15,836 CY | $29.59 | $20.00 – $75.00 | $468,659 | 1.7% |
| 464-7003 RC PIPE (CL III)(18 IN)318 low bids · prices swing 13x | 5,516 LF | $83.08 | $36.17 – $475.00 | $458,278 | 1.7% |