Bid Day Forecast: 0528-01-113

Hidalgo · Dec 1, 2026 Sign up free
Set your company to personalize scores

CCSJ 0528-01-113 · lets Dec 1, 2026 · Hidalgo, Pharr · SH 107 · Widen Road - Add Lanes

$24,134,502Engineer's estimate Items at market: $26,811,582 (+11.1%)
$20,302,484Most likely low bid$19,402,770 to $22,032,394 (middle half)
4.2Expected bidders6 plan holders, 6 regular bidders
51/100Worth a lookMarket only. Set your company for a personal score

Where the low bid should land

$18,515,329 (1 in 10 go lower)$23,649,923 (1 in 10 go higher)

From 14 comparable let jobs (district, estimates of $9,653,801 to $60,336,254, last 3 years). 93% of them went under the estimate; the typical low bid was -15.9% vs estimate.

Bid / no-bid score

  • Competition20 / 25Jobs like this draw about 4.2 bidders.
  • Margin3 / 20Low bids land at 84% of the estimate.

Set your company to add your experience, win rate and size fit.

Comparable jobs

Nov 2026 0220-01-038Hidalgo · 2 bidders $11,560,279-10.2%
Sep 2026 1505-01-016Cameron · 5 bidders $9,595,502-14.6%
May 2026 1064-01-027Hidalgo · 6 bidders $24,782,061-25.9%
May 2026 2094-01-063Hidalgo · 6 bidders $25,599,271-24.6%
Dec 2025 0331-03-022Cameron · 6 bidders $14,628,509-20.1%
Dec 2025 0863-01-075Hidalgo · 5 bidders $11,224,907-20.3%
Sep 2025 0039-18-122Hidalgo · 3 bidders $10,273,483-15.1%
Sep 2025 0528-01-118Hidalgo · 7 bidders $32,261,532-8.2%

The field: plan holders and how they bid

Last 3 years in Texas
Plan holderBidsWinsIn PharrAvg bid vs est.Avg win vs est.Their typical bid here
REIM CONSTRUCTION, INC. SharpestBidders 1333 of 12 -4.5%-11.1% $23,048,814
TEXAS CORDIA CONSTRUCTION, LLCBidders 2777 of 27 3.8%-15.4% $25,063,521
JAMES CONSTRUCTION GROUP, LLCBidders 101120 of 4 5.8%-8.5% $25,527,300
FOREMOST PAVING, INC.Bidders 521414 of 48 6.1%-9.4% $25,602,860
IOC COMPANY LLCBidders 482020 of 44 6.1%-8.0% $25,605,133
GO UNDERGROUND, LIMITED LIABILITY COMPANYBidders 1500 of 10 15.6% $27,901,145

"Typical bid here" is the estimate times that contractor's average bid ratio. Plan holders with no bids are usually suppliers or subs.

Items that decide this job

224 of 230 items priced from low bids
ItemQtyMarket priceRange of low bidsAt marketShare
344-7065 SP MIXES SP-D SAC-B PG76-2210 low bids 18,974 TON$118.07$100.00 – $205.00 $2,240,3448.4%
346-7009 STONE-MTRX-ASPH SMA-D SAC-A PG76-2261 low bids · prices swing 4x 11,671 TON$152.44$105.75 – $383.00 $1,779,1146.6%
400-7010 CEM STABIL BKFL452 low bids · prices swing 1,000x 10,660 CY$138.14$1.00 – $1,000.00 $1,472,6125.5%
464-7028 RC PIPE (CL IV)(60 IN)3 low bids 3,237 LF$430.84$400.00 – $560.00 $1,394,6445.2%
545-7006 CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)94 low bids · prices swing 440x 52 EA$26,188.60$100.00 – $44,000.00 $1,361,8075.1%
536-7002 CONC MEDIAN72 low bids · prices swing 20x 11,270 SY$92.13$50.00 – $1,000.00 $1,038,2923.9%
508-7001 CONSTRUCTING DETOURS174 low bids · prices swing 79x 11,912 SY$83.58$3.80 – $300.00 $995,6633.7%
531-7001 CONC SIDEWALKS (4")222 low bids · prices swing 57x 13,972 SY$70.57$21.64 – $1,237.00 $985,9413.7%
260-7005 LIME (COM OR QK)(SLURRY)66 low bids 2,253 TON$295.18$200.00 – $504.00 $665,0432.5%
110-7001 EXCAV (ROADWAY)586 low bids · prices swing 2,000x 50,695 CY$11.68$1.00 – $2,000.00 $592,2302.2%
100-7002 PREPARING ROW593 low bids · prices swing 86,117,000x 96 STA$6,072.92$0.0100 – $861,170.00 $583,0002.2%
500-7001 MOBILIZATION2229 low bids · prices swing 42,200,000,000x 1 LS$523,850.32$0.0010 – $42,200,000.00 $523,8502.0%
468-7001 THERMOPLASTIC PIPE (PP) (18")18 low bids · prices swing 4x 5,516 LF$86.05$33.33 – $125.61 $474,6421.8%
247-7277 FL BS (RDWY DEL)(TY E GR 4)(FNL POS)20 low bids · prices swing 4x 15,836 CY$29.59$20.00 – $75.00 $468,6591.7%
464-7003 RC PIPE (CL III)(18 IN)318 low bids · prices swing 13x 5,516 LF$83.08$36.17 – $475.00 $458,2781.7%