US 281 - Overlay
0220-01-038 · let Nov 3, 2026 · Hidalgo, Pharr · Overlay
$11,560,279Low bid: FOREMOST PAVING, INC.-10.2% vs estimate $12,874,559
$148,657Left on the table1.3% gap to the second bid
2BiddersSpread 1% low to high
88Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | FOREMOST PAVING, INC. | $11,560,279 | -10.2% | $148,657 | 0 | 2-$487,726 | |
| 2 | IOC COMPANY LLC | $11,708,936 | +1.3% | -9.1% | 0 | 2-$432,626 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
FOREMOST PAVING, INC. vs IOC COMPANY LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 354-7051 PLANE ASPH CONC PAV(2") | 421,691 SY | $2.59 | $1.00 | $1.86 | -$670,489 |
| 351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") | 57,313 SY | $49.70 | $59.70 | $60.19 | $573,130 |
| 346-7009 STONE-MTRX-ASPH SMA-D SAC-A PG76-22 | 48,073 TON | $135.30 | $140.00 | $152.44 | $225,943 |
| 500-7001 MOBILIZATION | 1 LS | $187,400.00 | $250,000.00 | $523,850.32 | $62,600 |
| 505-7001 TMA (STATIONARY) | 231 DAY | $62.75 | $1.00 | $217.57 | -$14,264 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 153 CY | $429.43 | $520.00 | $616.83 | $13,857 |
| 540-7001 MTL W-BEAM GD FEN (TIM POST) | 2,675 LF | $30.30 | $25.89 | $25.60 | -$11,797 |
| 666-7036 REFL PAV MRK TY I (W)24"(SLD)(100MIL) | 4,848 LF | $5.56 | $7.47 | $7.19 | $9,260 |
| 104-7005 REMOV CONC (MOWSTRIP) | 3,278 LF | $7.42 | $5.00 | $9.49 | -$7,933 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 15 MO | $1,500.00 | $1,000.00 | $11,585.04 | -$7,500 |
| 544-7001 GUARDRAIL END TREATMENT (INSTALL) | 12 EA | $4,040.00 | $3,475.00 | $3,190.07 | -$6,780 |
| 672-7004 REFL PAV MRKR TY II-A-A | 1,674 EA | $7.58 | $3.63 | $3.97 | -$6,612 |
| 672-7006 REFL PAV MRKR TY II-C-R | 1,665 EA | $7.58 | $3.63 | $4.19 | -$6,577 |
| 666-7411 REFL PAV MRK TY I (W)6"(SLD)(100MIL) | 90,030 LF | $0.7100 | $0.6400 | $0.4757 | -$6,302 |
| 6017-7014 VDS (HVDS) (VIVDS AND RVDS) | 14 EA | $6,767.00 | $7,193.73 | $12,214.27 | $5,974 |
| 3007-7001 BONDING COURSE | 29,518 GAL | $2.83 | $3.00 | $3.32 | $5,018 |
| 506-7044 BIODEG EROSN CONT LOGS (INSTL) (12") | 1,230 LF | $6.32 | $2.50 | $5.23 | -$4,699 |
| 666-7423 REFL PAV MRK TY I (Y)6"(SLD)(100MIL) | 63,922 LF | $0.7600 | $0.6900 | $0.4986 | -$4,475 |
| 666-7536 RE PM TY II (Y)6"(SLD)(018 MIL) | 63,922 LF | $0.3100 | $0.2400 | $0.1961 | -$4,475 |
| 668-7091 PREFAB PM TY C (W)(ARROW) | 89 EA | $151.50 | $196.73 | $201.69 | $4,025 |
Positive: the low bidder was cheaper on that item. These 20 items account for $147,906 of the $148,657 gap.