003918122 IH 2 HIDALGO (OVERLAY)
0039-18-122 · let Sep 5, 2025 · Hidalgo, Pharr · Overlay
$10,273,483Low bid: IOC COMPANY LLC-15.1% vs estimate $12,098,637
$542,068Left on the table5.3% gap to the second bid
3BiddersSpread 16% low to high
135Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | IOC COMPANY LLC | $10,273,483 | -15.1% | $542,068 | 0 | 3-$743,346 | |
| 2 | FOREMOST PAVING, INC. | $10,815,550 | +5.3% | -10.6% | $1,135,524 | 0 | 2-$348,816 |
| 3 | POSILLICO CIVIL, INC. | $11,951,074 | +16.3% | -1.2% | 2+$707,084 | 1-$303,825 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
IOC COMPANY LLC vs FOREMOST PAVING, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 354-7051 PLANE ASPH CONC PAV(2") | 547,608 SY | $1.00 | $2.15 | $1.86 | $629,749 |
| 346-7009 STONE-MTRX-ASPH SMA-D SAC-A PG76-22 | 29,369 TON | $145.00 | $137.00 | $152.44 | -$234,952 |
| 346-7017 STONE-MTRX-ASPH SMA-F SAC-A PG76-22 | 33,059 TON | $125.00 | $120.00 | $148.63 | -$165,295 |
| 351-7011 FLEXIBLE PAVEMENT STRUCTURE REPAIR(12") | 3,893 SY | $25.00 | $67.00 | $98.88 | $163,506 |
| 500-7001 MOBILIZATION | 1 LS | $140,000.00 | $246,000.00 | $523,850.32 | $106,000 |
| 505-7001 TMA (STATIONARY) | 180 DAY | $0.1000 | $161.00 | $217.57 | $28,962 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 126 CY | $595.00 | $484.00 | $616.83 | -$13,986 |
| 506-7044 BIODEG EROSN CONT LOGS (INSTL) (12") | 3,264 LF | $3.00 | $5.90 | $5.23 | $9,466 |
| 3007-7001 BONDING COURSE | 38,334 GAL | $3.00 | $2.78 | $3.32 | -$8,433 |
| 677-7001 ELIM EXT PM & MRKS (4") | 59,991 LF | $0.4000 | $0.5000 | $0.2643 | $5,999 |
| 104-7005 REMOV CONC (MOWSTRIP) | 865 LF | $15.00 | $11.00 | $9.49 | -$3,460 |
| 666-7408 REFL PAV MRK TY I (W)6"(BRK)(100MIL) | 35,170 LF | $0.7200 | $0.8000 | $0.5627 | $2,814 |
| 506-7042 BIODEG EROSN CONT LOGS (INSTL) (6") | 876 LF | $3.00 | $5.80 | $3.11 | $2,453 |
| 506-7046 BIODEG EROSN CONT LOGS (REMOVE) | 4,140 LF | $0.7500 | $1.30 | $1.29 | $2,277 |
| 666-7411 REFL PAV MRK TY I (W)6"(SLD)(100MIL) | 87,357 LF | $0.6800 | $0.7000 | $0.4757 | $1,747 |
| 666-7027 REFL PAV MRK TY I (W)12"(LNDP)(100MIL) | 27,280 LF | $0.9400 | $1.00 | $1.59 | $1,637 |
| 666-7423 REFL PAV MRK TY I (Y)6"(SLD)(100MIL) | 77,910 LF | $0.6800 | $0.7000 | $0.4986 | $1,558 |
| 668-7012 PREFAB PM TY B (W)(6")(BRK)CONTRAST | 7,538 LF | $11.50 | $11.70 | $10.48 | $1,508 |
| 666-7236 RE PM TY III (W)(6")(SLD) | 27,000 LF | $1.75 | $1.80 | $0.6919 | $1,350 |
| 662-7114 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 | 4,462 EA | $1.40 | $1.10 | $0.5715 | -$1,339 |
Positive: the low bidder was cheaper on that item. These 20 items account for $531,560 of the $542,068 gap.