Bridge Maintenance
CCSJ 0179-02-092 · lets Jan 6, 2027 · Brazoria, Houston · SH 35 · Bridge Maintenance
$2,043,210Engineer's estimate
Items at market: $2,916,074 (+42.7%)
$1,736,649Most likely low bid$1,506,781 to $1,962,957 (middle half)
5.2Expected bidders0 plan holders, 0 regular bidders
42/100Weak fitMarket only. Set your company for a personal score
Where the low bid should land
$1,736,649
Estimate $2,043,210
$1,329,473 (1 in 10 go lower)$2,290,897 (1 in 10 go higher)
From 221 comparable let jobs (district, estimates of $817,284 to $5,108,026, last 3 years). 82% of them went under the estimate; the typical low bid was -15.0% vs estimate.
Bid / no-bid score
- Competition16 / 25Jobs like this draw about 5.2 bidders.
- Margin3 / 20Low bids land at 85% of the estimate.
Set your company to add your experience, win rate and size fit.
Comparable jobs
| Nov 2026 | 6509-27-001Harris · 2 bidders | $4,204,328+15.6% |
| Nov 2026 | 6504-89-001Harris · 7 bidders | $2,035,047+53.8% |
| Nov 2026 | 6509-25-001Harris · 2 bidders | $4,495,312+18.1% |
| Nov 2026 | 0271-06-141Harris · 5 bidders | $1,151,035-32.0% |
| Oct 2026 | 0912-72-848Harris · 6 bidders | $4,064,176-6.8% |
| Oct 2026 | 6504-67-001Harris · 4 bidders | $2,731,500-10.4% |
| Oct 2026 | 0912-34-209Fort Bend · 9 bidders | $1,963,405-7.7% |
| Oct 2026 | 1414-03-043Brazoria · 2 bidders | $974,716-9.6% |
The field: plan holders and how they bid
Last 3 years in TexasNo plan holders posted for this job yet. Check back closer to the letting.
Items that decide this job
51 of 54 items priced from low bids| Item | Qty | Market price | Range of low bids | At market | Share |
|---|---|---|---|---|---|
| 432-7046 RIPRAP (STONE PROTECTION)(27 IN)1 low bids | 1,738 CY | $325.00 | $325.00 – $325.00 | $564,850 | 19.4% |
| 432-7046 RIPRAP (STONE PROTECTION)(27 IN)1 low bids | 1,738 CY | $325.00 | $325.00 – $325.00 | $564,850 | 19.4% |
| 500-7001 MOBILIZATION2229 low bids · prices swing 42,200,000,000x | 1 LS | $523,850.32 | $0.0010 – $42,200,000.00 | $523,850 | 18.0% |
| 446-7002 CLEAN & PAINT EXIST STR (SYSTEM II)15 low bids · prices swing 39x | 1 LS | $301,243.48 | $50,000.00 – $1,950,000.00 | $301,243 | 10.3% |
| 780-7005 CNC CRACK REPAIR (FLOOD)(GRAVITY)16 low bids · prices swing 100x | 29,670 SF | $9.78 | $2.00 – $200.00 | $290,180 | 10.0% |
| 780-7005 CNC CRACK REPAIR (FLOOD)(GRAVITY)16 low bids · prices swing 100x | 25,800 SF | $9.78 | $2.00 – $200.00 | $252,331 | 8.7% |
| 400-7010 CEM STABIL BKFL452 low bids · prices swing 1,000x | 473 CY | $138.14 | $1.00 – $1,000.00 | $65,342 | 2.2% |
| 400-7010 CEM STABIL BKFL452 low bids · prices swing 1,000x | 473 CY | $138.14 | $1.00 – $1,000.00 | $65,342 | 2.2% |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING2018 low bids · prices swing 273,686,480x | 3 MO | $11,585.04 | $0.0010 – $273,686.48 | $34,755 | 1.2% |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING2018 low bids · prices swing 273,686,480x | 3 MO | $11,585.04 | $0.0010 – $273,686.48 | $34,755 | 1.2% |
| 403-7002 TEMPORARY SPL SHORING (COFFERDAM)32 low bids · prices swing 100x | 1,050 SF | $28.47 | $1.00 – $100.00 | $29,894 | 1.0% |
| 403-7002 TEMPORARY SPL SHORING (COFFERDAM)32 low bids · prices swing 100x | 1,050 SF | $28.47 | $1.00 – $100.00 | $29,894 | 1.0% |
| 505-7001 TMA (STATIONARY)2363 low bids · prices swing 16,487,000x | 90 DAY | $217.57 | $0.0010 – $16,487.00 | $19,581 | 0.7% |
| 505-7001 TMA (STATIONARY)2363 low bids · prices swing 16,487,000x | 90 DAY | $217.57 | $0.0010 – $16,487.00 | $19,581 | 0.7% |
| 483-7016 SHOT BLASTING34 low bids · prices swing 65x | 3,297 SY | $5.25 | $2.00 – $130.00 | $17,322 | 0.6% |