6504-67-001 FULL DEPTH CONCRETE
6504-67-001 · let Oct 7, 2026 · Harris, Houston · Routine Maintenance Project - Sealed
$2,731,500Low bid: ISI CONTRACTING, INC.-10.4% vs estimate $3,049,175
$42,900Left on the table1.6% gap to the second bid
4BiddersSpread 27% low to high
20Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | ISI CONTRACTING, INC. | $2,731,500 | -10.4% | $42,900 | 1+$1,029,728 | 5-$797,092 | |
| 2 | MC2 CIVIL, LLC | $2,774,400 | +1.6% | -9.0% | $558,074 | 0 | 0 |
| 3 | STRUCTURAL INTEGRITY GROUP LLC | $3,332,474 | +22.0% | 9.3% | $123,676 | 3+$525,902 | 0 |
| 4 | DIGG COMMERCIAL, LLC | $3,456,150 | +26.5% | 13.3% | 4+$678,670 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
ISI CONTRACTING, INC. vs MC2 CIVIL, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 300 DAY | $3,650.00 | $250.00 | $217.57 | -$1,020,000 |
| 429-7004 CONC STR REPAIR(RAPID DECK REP(PRT DPT) | 7,000 SF | $36.00 | $100.00 | $85.28 | $448,000 |
| 438-7007 CLEANING AND SEALING EXIST JOINTS (CL7) | 7,000 LF | $9.00 | $44.00 | $38.57 | $245,000 |
| 785-7011 BRIDGE JOINT REPLACEMENT (SEJ) | 200 LF | $283.00 | $1,000.00 | $634.97 | $143,400 |
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 1,000 SF | $30.00 | $150.00 | $150.68 | $120,000 |
| 429-7006 CONC STR REPR(RAPID DECK REP(FULL DPT)) | 500 SF | $45.00 | $200.00 | $153.06 | $77,500 |
| 361-7068 FULL-DEPTH REP(BR APPR SLAB)(9"-13") | 150 SY | $380.00 | $500.00 | $550.34 | $18,000 |
| 500-7033 MOBILIZATION (EMERGENCY) | 12 EA | $500.00 | $2,000.00 | $844.81 | $18,000 |
| 438-7004 CLEANING AND SEALING EXIST JOINTS (CL3) | 500 LF | $12.00 | $25.00 | $19.19 | $6,500 |
| 401-7001 FLOWABLE BACKFILL | 50 CY | $250.00 | $350.00 | $298.77 | $5,000 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 50 DAY | $250.00 | $150.00 | $87.82 | -$5,000 |
| 361-7060 FULL-DEPTH REPAIR CRCP (12") | 1,500 SY | $338.00 | $335.00 | $313.15 | -$4,500 |
| 529-7014 CONC CURB (DOWEL) | 150 LF | $6.00 | $35.00 | $33.73 | $4,350 |
| 400-7010 CEM STABIL BKFL | 20 CY | $250.00 | $60.00 | $138.14 | -$3,800 |
| 361-7057 FULL - DEPTH REPAIR CRCP (10") | 500 SY | $317.00 | $310.00 | $239.80 | -$3,500 |
| 361-7070 FULL - DEPTH REPAIR CRCP (13"-15") | 1,000 SY | $368.00 | $365.00 | $390.67 | -$3,000 |
| 361-7067 FULL - DEPTH REPAIR CRCP (14") | 200 SY | $366.00 | $355.00 | $300.63 | -$2,200 |
| 500-7002 MOBILIZATION (CALLOUT) | 12 EA | $250.00 | $100.00 | $600.85 | -$1,800 |
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 50 LF | $12.00 | $25.00 | $15.92 | $650 |
| 104-7006 REMOV CONC (RIPRAP) | 100 SY | $22.00 | $25.00 | $14.32 | $300 |
Positive: the low bidder was cheaper on that item. These 20 items account for $42,900 of the $42,900 gap.
ISI CONTRACTING, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 300 DAY | $3,650.00 | $217.57 | 16.78x | $1,029,728 |
| 429-7004 CONC STR REPAIR(RAPID DECK REP(PRT DPT) | 7,000 SF | $36.00 | $85.28 | 0.42x | -$344,990 |
| 438-7007 CLEANING AND SEALING EXIST JOINTS (CL7) | 7,000 LF | $9.00 | $38.57 | 0.23x | -$206,998 |
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 1,000 SF | $30.00 | $150.68 | 0.20x | -$120,680 |
| 785-7011 BRIDGE JOINT REPLACEMENT (SEJ) | 200 LF | $283.00 | $634.97 | 0.45x | -$70,394 |
| 429-7006 CONC STR REPR(RAPID DECK REP(FULL DPT)) | 500 SF | $45.00 | $153.06 | 0.29x | -$54,030 |
STRUCTURAL INTEGRITY GROUP LLC: unbalanced items
Placed 3DIGG COMMERCIAL, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 300 DAY | $2,000.00 | $217.57 | 9.19x | $534,728 |
| 429-7006 CONC STR REPR(RAPID DECK REP(FULL DPT)) | 500 SF | $300.00 | $153.06 | 1.96x | $73,470 |
| 500-7033 MOBILIZATION (EMERGENCY) | 12 EA | $5,000.00 | $844.81 | 5.92x | $49,862 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 50 DAY | $500.00 | $87.82 | 5.69x | $20,609 |